E. Cornell Malone Corporation v. Marshall County School District

Court of Appeals of Mississippi·Decided April 15, 2025·No. 2024-CA-00047-COA·Published

Opinion

IN THE COURT OF APPEALS OF THE STATE OF MISSISSIPPI NO. 2024-CA-00047-COA

E. CORNELL MALONE CORPORATION APPELLANT v. MARSHALL COUNTY SCHOOL DISTRICT APPELLEE

DATE OF JUDGMENT: 12/15/2023 TRIAL JUDGE: HON. KENT E. SMITH COURT FROM WHICH APPEALED: MARSHALL COUNTY CIRCUIT COURT ATTORNEYS FOR APPELLANT: PHILIP J. SIEGEL G. TODD BURWELL

RICHARD ALLEN EISENBERGER JR.

ATTORNEY FOR APPELLEE: LORI WHALEY SHAW NATURE OF THE CASE: CIVIL - CONTRACT DISPOSITION: AFFIRMED - 04/15/2025 MOTION FOR REHEARING FILED:

BEFORE WILSON, P.J., LAWRENCE AND EMFINGER, JJ.

EMFINGER, J., FOR THE COURT:

¶1. E. Cornell Malone Corporation (Malone) filed a complaint against the Marshall County School District (the District) in the Circuit Court of Marshall County, Mississippi, seeking to recover damages for services rendered pursuant to a contract for the repair of the roofing on two elementary schools in the District. In its complaint, Malone sought to recover damages for breach of contract in Claim I, quantum meruit and unjust enrichment in Claim II, and in Claim III “Claim Pursuant to Miss. Code Ann. § 31-5-25 ” (which governs the method of payments for “public construction contracts”). The District filed a motion to dismiss pursuant to Mississippi Rule of Civil Procedure 12(b)(6), which the circuit court granted in part and denied in part, dismissing all of Malone’s claims except one claim for

$752.05 that was resolved by agreement. See infra note 2. Aggrieved, Malone appealed.

FACTS AND PROCEDURAL HISTORY

¶2. Malone and the District entered into an American Institute of Architects (AIA) “Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum” dated October 15, 2019. In the AIA form agreement, the identity of the Architect and “The Work of this Contract” were left to be determined at a later date. The “Date of Commencement and Substantial Completion” was established as “A date set forth in a Notice to Proceed by the Architect or Owner.” The “Substantial Completion” in § 3.3.1 of the agreement states as follows: “By the following date: To be determined after settlement of Insurance Claim.” Payments are governed by Article 5 of the agreement. Applications for payment had to be submitted by Malone to the Architect. If received by the 25th day of the month, payment was due by the 25th day of the next month. The trigger that placed the burden on the District to make a payment was a “Certificate for Payment” issued by the Architect to the District. The payments were subject to a five-percent retainage according to § 5.1.7.1 of the agreement. Final payment, constituting the entire unpaid balance of the contract sum, was required to be made within thirty days of the issuance of the final “Certificate of Payment” by the Architect.1

¶3. In May 2020, the parties executed a “change order,” which provided the details not determined in the original AIA form. The scope of the work is stated as:

1 Neither party made any reference, in their pleadings or at the hearing, to progress payments made or requested during the course of the work. There is no mention of “Applications for Payment” made by Malone to the Architect or any “Certificate for Payment” issued by the Architect to the District.

Roofing of Galena Elementary School and HW Byers per the attached Scope of Work marked Exhibit “A”. Scope of Work based on Insurance Claim #5630042916.

The contract sum to be paid to Malone for this work was $900,642.00. There was no time set for substantial completion. William T. Mills of Mills & Mills Architects P.C. signed the change order as the Architect for the project.

¶4. Malone alleges that after it began performing the work according to the first change order described above, it discovered bad decking that needed to be replaced at both schools. The first change order did not include replacing the decking in the scope of work to be performed by Malone and did not include the cost to replace the decking.

¶5. Malone made the following allegations in its complaint, all denied by the District:

8. Shortly after Malone began performing the work pursuant to the Contract, Malone discovered both schools had bad decking that needed to be replaced. The bad decking was a latent and unforeseen condition that prevented Malone from proceeding with its contractual scope of work.

9. The necessary deck replacement work was in addition to the $900,642.00 pursuant to [the change order].

10. Shortly after the discovery of the bad decking, Malone began assisting [the District in submitting] a claim to [the District’s] insurer to cover the additional cost of replacing the bad decking. However, due to a wear and tear exclusion in the insurance policy, [the District’s] insurer denied coverage.

11. With [the District] knowing that Malone intended to be paid for the work outside the original scope of work pursuant to [the change order], [the District] permitted Malone to proceed with the work, including the necessary deck replacement work. [The District] continued to permit [Malone] to proceed with the necessary deck replacement work knowing that its insurer had denied the claim and would not cover the additional costs, and also knowing that Malone was expecting to be

paid for the deck replacement work, which was for the benefit of the [District].

12. Malone performed the deck replacement work in plain view, and the [District] never instructed Malone to cease with the work, even after [the District] knew its insurance claim was denied.

¶6. According to the complaint, Malone substantially completed its work on the project on September 23, 2020. The complaint alleges that the District “accepted the Project and all of Malone’s roof and deck replacement work under the scope of the Contract and Change Order #1 and Change Order #2.” However, it was not until October 20, 2020, after the work was completed, that Malone sent a “Proposal” for Change Order #2 to the Architect. This proposal sought to cover the cost of the decking replacement in the amount of $143,896.00. However, the proposal was not signed by either the District or the Architect as being accepted.

¶7. Malone alleged in the complaint that the District paid Malone $31,852.90 on July 20, 2022, which left a balance of $752.05 owing as to Change Order #1. The complaint further alleged that the District refused to pay Malone the $752.05 owed on Change Order #1 and refused to pay any of the $143,896.00 related to Change Order #2. As a result, Malone filed its complaint against the District on October 4, 2022. Attached to the complaint were the October 15, 2019 original AIA form agreement, Change Order #1 with the scope of work attachments, and the unsigned proposal dated October 20, 2020, as discussed above. The District filed its answer on November 4, 2022, citing multiple affirmative defenses, including, among others, that Malone’s complaint failed to set forth a claim upon which relief could be granted and that the claims were barred by the applicable statute of

limitations, and also generally denying all of Malone’s grounds for recovery.

¶8. On January 31, 2023, the District filed its motion to dismiss the complaint. On February 10, 2023, Malone filed a motion for leave to amend the complaint “to clarify the underlying facts and circumstances raised in the Complaint that are proper subject of relief.” The same day, Malone also filed a response in opposition to the District’s motion to dismiss.

Free access — add to your briefcase to read the full text and ask questions with AI

E. Cornell Malone Corporation v. Marshall County School District, (Mich. Ct. App. 2025).

E. Cornell Malone Corporation v. Marshall County School District (E. Cornell Malone Corporation v. Marshall County School District) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Harmon v. Regions Bank
961 So. 2d 693 (Mississippi Supreme Court, 2007)
Hartford Cas. Ins. Co. v. Halliburton Co.
826 So. 2d 1206 (Mississippi Supreme Court, 2001)
Rose v. Tullos
994 So. 2d 734 (Mississippi Supreme Court, 2008)
Webb v. DeSoto County
843 So. 2d 682 (Mississippi Supreme Court, 2003)
Caves v. Yarbrough
991 So. 2d 142 (Mississippi Supreme Court, 2008)
Jourdan River Estates, LLC v. Scott M. Favre
212 So. 3d 800 (Mississippi Supreme Court, 2015)
Mississippi Department of Human Services v. S.C.
119 So. 3d 1011 (Mississippi Supreme Court, 2013)