E. Corey Co. v. H. P. Cummings Construction Co.

105 A. 405, 118 Me. 34, 1919 Me. LEXIS 13
CourtSupreme Judicial Court of Maine
DecidedJanuary 28, 1919
StatusPublished
Cited by6 cases

This text of 105 A. 405 (E. Corey Co. v. H. P. Cummings Construction Co.) is published on Counsel Stack Legal Research, covering Supreme Judicial Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
E. Corey Co. v. H. P. Cummings Construction Co., 105 A. 405, 118 Me. 34, 1919 Me. LEXIS 13 (Me. 1919).

Opinion

Morrill, J.

The plaintiff claims to establish a lien on the land of Rumford Falls Power Company and the buildings thereon occupied by Maine Coated Paper Company, for materials used in the construction of an addition to the mill of the latter corporation, furnished to Fletcher & Crowell Company, a sub-contractor under H. P. [36]*36Cummings Construction Company, the general contractor for the entire work. The case is reported upon a stipulation and agreed statement of facts.

On the eighth day of August, 1913, Rumford Falls Power Company leased to Maine .Coated Paper Company the land described in the bill for a term of twenty-five years from the first day of August, 1913, with an option to purchase the same, which has not been exercised by the lessee.

Later, (the exact date does not appear), Maine Coated Paper Company erected a mill on the leased premises, and on the twenty-seventh day of April, 1916, made a contract with H. P. Cummings Construction Company to “do and perform all the work and provide all the materials required” in building an addition adjoining and attaching to the present building of the Maine Coated Paper Company. This contract was made ‘ 'with the actual knowledge and consent of the Rumford Falls Power Company.”

By correspondence between April 24, 1916, and June 7, 1916, both inclusive, H. P. Cummings Construction Company made a contract or contracts with Fletcher & Crowell Company to furnish certain portions of the iron and steel materials for installation in said building under construction.

By correspondence and personal interviews between May 9, 1916, and June 7, 1916, both inclusive, Fletcher & Crowell Company, with the actual knowledge and consent of H. P. Cummings Construction Company, contracted with E. Corey & Company for certain of the materials which, as E. Corey & Company knew, were for the building then in process of construction at Rumford under the contract between H. P. Cummings Construction Company and Maine Coated Paper Company. The material so contracted for was actually furnished and delivered by E. Corey & Company at the forge shop in Portland, of Fletcher & Crowell Company between May 29,1916, and June 22, 1916, both inclusive, as H. P. Cummings Construction Company at the time actually knew; the agreed price therefor was $1654.05; all of the material so delivered by E. Corey & Company at the forge shop of Fletcher & Crowell Company was delivered and received for the purpose of being shipped to Rumford for incorporation into the building there under construction as aforesaid, “after the material should have been painted, put together, drilled with holes, [37]*37bolted, welded or otherwise worked into the shape and condition necessary for meeting the requirements of the building contract in so far as the materials in the shape in which they were supplied by E. Corey & Company were, not already in such necessary shape and condition;” but E. Corey & Company had no control whatever over the disposition of said material after it was delivered to Fletcher & Crowell Company.

Certain portions of the material supplied by E. Corey & Company and delivered to Fletcher & Crowell Company, at their shop, in Portland, were actually incorporated and used in erecting, constructing, altering and repairing the building and appurtenances then being erected on the leased premises by H. P. Cummings Construction Company under its contract with Maine Coated Paper Company, after having been, as hereinbefore stated, painted, welded, bolted, drilled with holes and otherwise worked into the shape and condition necessary for meeting the requirements of the building contract of H. P. Cummings Construction Company; the value of such material at the original contract prices between Fletcher & Crowell Company and E. Corey & Company was $1530.90.

The Rumford Falls Power Company had no actual knowledge that Fletcher & Crowell Company were furnishing materials in the erection of said building for'Maine Coated Paper Company, but knew that a contract had been entered into between Maine Coated Paper Company and H. P. Cummings Construction Company, and that said building was being erected-and the materials required by the contract for its erection were being furnished and installed.

The claim of a lien upon the interest of Rumford Falls Power Company in the leased premises cannot be sustained. The lease contained an express provision that the building “shall remain and be personalty and not become a part of the realty, and that the said lessee, its successors or assigns, may enter and remove the same from said premises at the expiration of this lease.” The lessor did not participate in the improvement; nor was it to reap any ultimate benefit therefrom; it was not an affirmative factor in procuring the erection of the addition to the then existing mill. As long as the Maine Coated Paper Company observed the conditions and terms of the lease, and particularly'the condition that it should “never occupy or use said premises, or any part thereof, for any purpose other than [38]*38those in which it is authorized under its certificate of organization to engage/’ the lessor could not prevent the erection of the addition, and therefore cannot be said to have given or withheld its consent; and its interest cannot be charged with the lien claimed by plaintiff, (2 Jones on Liens, Secs. 1275, 1276; Francis v. Sayles, 101 Mass., 435; Rice v. Culver, 172 N. Y., 60, 65) although, as the case states, the general contract for erecting the building was made with the actual knowledge and consent of the lessor. In such a case, consent amounts only to acquiescense in that which the lessor could not prevent. “Consent within the meaning of the statute means something more than acquiescense. It implies an agreement to that which could not exist without such consent.” 2 Jones on Liens, Sec. 1253; Hanson v. News Publishing Co., 97 Maine, 99,103; De Klyn v. Gould, 165 N. Y., 282, 80 Am. St. Rep., 719.

This case is clearly distinguishable from cases like Baker v. Waldron, 92 Maine, 17; Borden v. Mercer, 163 Mass., 7; Burkett v. Harper, 79 N. Y., 273; Otis v. Dodd, 90 N. Y., 236.

We pass also without discussion, and without expressing any opinion thereon, the point which has been exhaustively argued, whether the materials were furnished by E. Corey & Company in erecting, altering or repairing the building. See Munroe v. Clark, 107 Maine, 134; Boston Furnace Co. v. Dimock, 158 Mass., 552; Scannell v. Hub Brewing Co., 178 Mass., 288.

It is incumbent upon the plaintiff to show that the materials for which he would establish a lien were furnished “by virtue of a contract with or by consent of the owner.” The word “owner” is comprehensive enough to include the owner of a leasehold estate. 2 Jones on Liens, Sec. 1272.

It is not claimed that the plaintiff had a contract with Maine Coated Paper Company; its contract was with Fletcher & Crowell Company, a sub-contractor under the general contractor for the entire work, H. P. Cummings Construction Company. It is agreed that “Maine Coated Paper Company had no actual knowledge that Fletcher & Crowell Company were furnishing the materials which were furni'shed by Fletcher & Crowell Company for the building, nor did it have actual knowledge that E.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

F.R. Carroll, Inc. v. TD Bank, N.A.
2010 ME 115 (Supreme Judicial Court of Maine, 2010)
United States v. Jett
14 M.J. 941 (U.S. Army Court of Military Review, 1982)
Lyon v. Dunn
402 A.2d 461 (Supreme Judicial Court of Maine, 1979)
Carey v. Boulette
182 A.2d 473 (Supreme Judicial Court of Maine, 1962)
Bangor Roofing & Sheet Metal Co. v. Robbins Plumbing Co.
116 A.2d 664 (Supreme Judicial Court of Maine, 1955)

Cite This Page — Counsel Stack

Bluebook (online)
105 A. 405, 118 Me. 34, 1919 Me. LEXIS 13, Counsel Stack Legal Research, https://law.counselstack.com/opinion/e-corey-co-v-h-p-cummings-construction-co-me-1919.