E. C. Machin, Inc. v. American Cement Corp.

53 Pa. D. & C.2d 334, 1971 Pa. Dist. & Cnty. Dec. LEXIS 365
CourtPennsylvania Court of Common Pleas, Northampton County
DecidedNovember 1, 1971
Docketno. 197
StatusPublished

This text of 53 Pa. D. & C.2d 334 (E. C. Machin, Inc. v. American Cement Corp.) is published on Counsel Stack Legal Research, covering Pennsylvania Court of Common Pleas, Northampton County primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
E. C. Machin, Inc. v. American Cement Corp., 53 Pa. D. & C.2d 334, 1971 Pa. Dist. & Cnty. Dec. LEXIS 365 (Pa. Super. Ct. 1971).

Opinion

FRANCIOSA, J.,

In the assumpsit action before us, plaintiff has filed a complaint alleging that it is owed the sum of $50,457.14 for labor and materials furnished to defendant from March 9, 1970, to May 27, 1970. The complaint specifies that the work performed by plaintiff involved the installation of roof support steel for certain “silos” used by defendant in the manufacture of cement at its Stockertown facility.

Defendant has filed an answer which includes new matter and a counterclaim. Although the complaint seeks recovery for work performed during the year 1970, defendant’s new matter and counterclaim refer to work done by plaintiff at the time of the original construction of the “silos.” The pleadings on both sides of the case reveal that the original construction was completed on May 5,1958.

By way of new matter, defendant alleges that work performed by plaintiff in 1970 resulted from the improper design and construction of the “silos” in 1958 and that it was plaintiff’s responsibility to correct those defects without charge to defendant. Under the counterclaim, defendant seeks an affirmative verdict against plaintiff in the amount of $9,370 as the cost of repairs which plaintiff failed to undertake in the year 1970.

Since the design and construction of the “silos” was completed on May 5, 1958, plaintiff has filed preliminary objections in the nature of a demurrer to both the new matter and counterclaim contained in [336]*336defendant’s answer. The demurrer pleads the limitation period established by the Act of December 22, 1965, P. L. 1183, sec. 1, 12 PS §65.1, which provides that:

“No action ... to recover damages . . . shall be brought against any person lawfully performing or furnishing the design, planning, supervision or observation of construction, or construction of such improvement more than twelve years after completion of such an improvement.’.’

Plaintiff contends that the application of the Act of 1965, supra, bars the new matter and the counterclaim because defendant’s pleadings were not filed until July 9, 1971, more than 13 years after completion of the construction out of which the alleged defects occurred.

In response, defendant has adopted two alternative positions with regard to the act’s application to its new matter and counterclaim.

First, defendant argues that application of the act to this case would be retroactive in nature because the construction in question was completed prior to the passage of the act.

The issue of the retroactive application of the Act of 1965, supra, was before our Supreme Court in Misitis v. Steel City Piping Co., 441 Pa. 339, 272 A. 2d 883. There, Mr. Justice O’Brien concluded that the Act of 1965 was not intended to apply retroactively. However, Misitis clearly indicates that the matter of retroactive application is to be determined by looking to the date of the cause of action rather than upon the date of the construction.

The reason we perceive such a holding in Misitis is that the Supreme Court made no mention of a date of construction in arriving at its decision. Instead, the court found a legislative intent to eliminate all [337]*337causes of action which referred back to construction completed more than 12 years before the alleged cause of action arose. In this connection, the court stated:

“After the effective date of the statute, in a case like this, even if a would-be plaintiff attempted to file suit immediately after the accident while on his way to the hospital, his haste would be to no avail. He would have no cause of action”: Misitis, supra, at page 343.

Section 7 of the Act of 1965, supra, provides that it shall take effect July 1, 1966. In the instant case, the claims set up in defendant’s new matter and counterclaim arose on September 15, 1969. Since that date is more than three years after the effective date of the act, its application to this case would not be giving the act retroactive effect.

As an alternative argument, defendant contends that application of the Act of 1965, supra, does not afford it a “reasonable period” of time to commence an action. Defendant points out that its cause of action arose on September 15, 1969, and that under the act it was required to bring suit prior to May 5, 1970, a period of approximately eight months. We cannot accept this contention, since the period which was available to defendant exceeded the grace period of six months provided by the legislature for causes of action arising between the time of the act’s passage and the date it became effective.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Misitis v. Steel City Piping Co.
272 A.2d 883 (Supreme Court of Pennsylvania, 1971)
Enterline v. Miller
27 Pa. Super. 463 (Superior Court of Pennsylvania, 1905)

Cite This Page — Counsel Stack

Bluebook (online)
53 Pa. D. & C.2d 334, 1971 Pa. Dist. & Cnty. Dec. LEXIS 365, Counsel Stack Legal Research, https://law.counselstack.com/opinion/e-c-machin-inc-v-american-cement-corp-pactcomplnortha-1971.