Dynasty Stainless Steel & Metal Industries, Inc. v. Hill International, Inc.

CourtDistrict Court, E.D. New York
DecidedSeptember 26, 2021
Docket1:17-cv-02345
StatusUnknown

This text of Dynasty Stainless Steel & Metal Industries, Inc. v. Hill International, Inc. (Dynasty Stainless Steel & Metal Industries, Inc. v. Hill International, Inc.) is published on Counsel Stack Legal Research, covering District Court, E.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dynasty Stainless Steel & Metal Industries, Inc. v. Hill International, Inc., (E.D.N.Y. 2021).

Opinion

UNITED STATES DISTRICT COURT EASTERN DISTRICT OF NEW YORK ---------------------------------------------------------x DYNASTY STAINLESS STEEL & METAL INDUSTRIES, INC.,

Plaintiff, MEMORANDUM AND ORDER

v. 17-CV-2345 (RPK) (RLM)

HILL INTERNATIONAL, INC.,

Defendant. ---------------------------------------------------------x RACHEL P. KOVNER, United States District Judge: Plaintiff Dynasty Stainless Steel & Metal Industries, Inc., a construction contractor, filed this diversity suit against defendant Hill International, Inc. (“Hill”), a construction manager, alleging state-law causes of action in connection with a contract between the parties. See Compl. (Dkt. #1). Defendant moved to compel arbitration and the Court granted the motion. Order Compelling Arbitration (Dkt. #15). While the arbitration was pending, plaintiff filed a motion to appoint an independent arbitrator or, in the alternative, to vacate the arbitration award. (Dkt. #47) (sealed); (Dkt. #48) (redacted). In a report and recommendation (“R. & R.”), Judge Mann recommends that I deny the request to appoint an independent arbitrator as moot and deny without prejudice the request to vacate the arbitration award as premature. R. & R. at 10 (Dkt. #57). For the reasons set out below, I adopt Judge Mann’s recommendation in full and deny the motion. BACKGROUND I assume familiarity with the underlying facts and procedural history, see R. & R. at 2-6, which I describe here only as needed to address defendant’s R. & R. objections. In December 2014, plaintiff contracted with defendant to perform construction work on a performing arts center at a City University of New York (“CUNY”) campus. Compl. ¶¶ 1-2 (“First Count”); Contract at 5 (Dkt. #12-4). Plaintiff alleges that defendant did not make the project site available until April 2016, more than two years after plaintiff’s anticipated start date.

See Compl. ¶ 16 (“First Count”). Plaintiff further alleges that defendant knew that the site would not be ready on time and fraudulently induced plaintiff to underbid on the project, interfered with plaintiff’s work, committed fraud, wrongfully terminated the contract, interfered with plaintiff’s ability to obtain future construction contracts, violated New York trust law, and discriminated against plaintiff. See id. ¶¶ 5-17, 18 (“First Count”); id. ¶¶ 1-11 (“Second Count”); id. ¶¶ 1-19 (“Third Count”); id. ¶¶ 1-8 (“Fourth Count”); id. ¶¶ 1-3 (“Fifth Count”); id. ¶¶ 1-12 (“Sixth Count”). The contract included a process for resolving disputes between the parties. Contract at 41-43. To initiate the process, plaintiff could file a dispute report. Id. at 42. Then, the Executive Director of CUNY could negotiate a resolution or unilaterally resolve the dispute. Id.

at 43. The contract also provided a means for plaintiff to appeal the Executive Director’s decision to the Vice Chancellor of CUNY. Ibid. And if the Vice Chancellor failed to resolve the dispute within thirty days of receiving a notice of appeal, the contract limited plaintiff’s remedy to “an appeal pursuant to Article 78 of the Civil Practice Laws and Rules of the State of New York.” Ibid. On April 19, 2017, plaintiff filed suit in federal court. The suit contains state-law claims. It also seeks a declaration that the contract’s dispute resolution terms did not govern its claims. See Compl. ¶¶ 1-10 (“Count Seven”). Defendant filed a motion to dismiss or, in the alternative, to stay the proceedings pending arbitration. (Dkt. #12). Judge Kiyo A. Matsumoto construed the relevant contract provisions as an agreement to arbitrate under the Federal Arbitration Act (“FAA”), 9 U.S.C. § 1 et seq., and granted defendant’s motion to compel arbitration. Order Compelling Arbitration at 9, 19. The parties proceeded to arbitration, Decl. of David C. Dreifuss ¶¶ 3-4 (Dkt. #48-1), and the case was subsequently reassigned to me.

During the pendency of the arbitration, plaintiff filed a motion to appoint an independent arbitrator or, in the alternative, to vacate the arbitration award. See Mot. to Appoint Independent Arbitrator (Dkt. #47) (sealed); Mot. to Appoint Independent Arbitrator (Dkt. #48) (redacted). I referred plaintiff’s motion to Judge Mann for an R. & R on December 3, 2020. The motion was fully briefed on January 25, 2021. The arbitrator ruled against plaintiff on April 5, 2021. See Pl.’s Letter dated Apr. 19, 2021 at 2 (Dkt. #54). Plaintiff filed a letter two weeks later informing the Court about the arbitrator’s decision and asking the Court to vacate the award and appoint an independent arbitrator. Ibid. Defendant filed a responsive letter stating that plaintiff had appealed the award to the Vice Chancellor. Def.’s Letter dated Apr. 23, 2021 at 1-2 (Dkt. #55). Plaintiff did not file

a further response—or seek leave to file a further response—concerning the status of its appeal. On July 26, 2021, Judge Mann issued an R. & R. concluding that plaintiff’s motion should be denied. Judge Mann concluded that the motion to appoint an independent arbitrator was moot because the arbitrator had already issued an award. R. & R. at 6. In addition, Judge Mann concluded that the motion to vacate the arbitration award was premature. Id. at 10. Judge Mann reasoned that the award had not yet become final on account of plaintiff’s appeal to the Vice Chancellor. Id. at 7-9. Judge Mann therefore recommended that I deny the motion. Id. at 10. Plaintiff objects. In its objections, plaintiff argued for the first time that even if the arbitration award was not final when the parties finished briefing the motion, the decision later became final. Pl.’s Objection at 1-2, 4 (Dkt. #58). Plaintiff relies on the portion of the parties’ contract that provides that when the Vice Chancellor takes more than thirty days to resolve an

appeal, plaintiff’s “only remedy” is an Article 78 proceeding in state court. Id. at 4. Plaintiff argues that such a proceeding can only be “filed from a final decision of an administrative body.” Ibid. Since more than thirty days had elapsed from the filing of the notice of appeal when Judge Mann issued the R. & R., plaintiff contends that the award was actually final. See id. at 4-6. On that basis, plaintiff objects that its “motion to appoint an independent arbitrator was not premature and should be granted on the merits.” Id. at 6. Plaintiff also “requests clarification from the Court as to whether it must file and fully adjudicate an Article 78 proceeding” to obtain a final award that can be reviewed in federal court. Id. at 6-7. STANDARD OF REVIEW The standard of review a district court should use when considering an order or

recommendation from a magistrate judge depends on whether the issue “is dispositive of a party's claim or defense.” Fed. R. Civ. P. 72(a); see 28 U.S.C. § 636(b)(1). If a party timely objects to a magistrate judge's recommendation on a dispositive issue, then the district court must “determine de novo” those parts of the ruling that have been “properly objected to.” Fed. R. Civ. P. 72(b)(3); see 28 U.S.C. § 636(b)(1). Those parts of an R. & R. that are uncontested or are not properly objected to may be reviewed, at most, for “clear error.” Alvarez Sosa v. Barr, 369 F. Supp. 3d 492, 497 (E.D.N.Y. 2019) (citation omitted); see Nelson v. Smith, 618 F. Supp. 1186, 1189 (S.D.N.Y. 1985) (citing Fed. R. Civ. P.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Dynasty Stainless Steel & Metal Industries, Inc. v. Hill International, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/dynasty-stainless-steel-metal-industries-inc-v-hill-international-nyed-2021.