Dynamic Heating & Pumping Company v. Insurance Company of North America Walbridge-Aldinger Company, Comp-Aire Systems, Inc.

912 F.2d 123, 1990 U.S. App. LEXIS 14535, 1990 WL 120315
CourtCourt of Appeals for the Sixth Circuit
DecidedAugust 22, 1990
Docket89-1641
StatusPublished

This text of 912 F.2d 123 (Dynamic Heating & Pumping Company v. Insurance Company of North America Walbridge-Aldinger Company, Comp-Aire Systems, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dynamic Heating & Pumping Company v. Insurance Company of North America Walbridge-Aldinger Company, Comp-Aire Systems, Inc., 912 F.2d 123, 1990 U.S. App. LEXIS 14535, 1990 WL 120315 (6th Cir. 1990).

Opinion

RYAN, Circuit Judge.

This is an appeal from a judgment awarded to a sub-sub-subcontractor on a construction project for The University of Michigan. Defendant-appellants, the project’s principal contractor and the principal contractor’s surety, appeal the award alleging, foremost, that Mich.Comp.Laws § 129.201, pursuant to which the judgment was awarded, does not apply to the construction project involved in this case. We agree, and now reverse.

I.

In 1984, the Regents of The University of Michigan announced plans to construct additions to the University’s College of Engineering Building. Rather than contracting for the project directly, the Regents, in a 1984 agreement, conveyed the Engineering Building site to the State of Michigan Building Authority, a public corporation, which agreed to finance the construction work and, upon its completion, lease the completed building to the University. The University hired Walbridge-Aldinger Company as principal contractor to supervise the project. The University also arranged for the Insurance Company of North America (“INA”) to give it a Contractor’s Payment Surety Bond to cover claims of certain other contractors.

Walbridge-Aldinger thereafter contracted with Comp-Aire Systems, Inc. to design a “clean room” for the project. A “clean room” is a contaminant-free area for solid state electronics research. Comp-Aire, in turn, contracted with Pullman Construction Industries to install piping in the clean room. Pullman subsequently contracted with Dynamic Heating and Piping Company, the plaintiff-appellee, to assist it in the installation of pipes for the clean room. Dynamic’s relation to Walbridge-Aldinger may thus be characterized as that of a “sub-sub-subcontractor. ’ ’

The work was begun and the project was nearly completed when, in May 1987, Pullman filed for bankruptcy. Among Pullman’s outstanding obligations at the time of the bankruptcy was a debt of $253,-647.18 allegedly owed to Dynamic for work performed on the Engineering Building project at Pullman’s behest.

Having exhausted all other remedies against Pullman without success, Dynamic, an Illinois corporation, filed a diversity suit in United States District Court for the *125 Eastern District of Michigan against Comp-Aire, a Michigan corporation, and INA, a Pennsylvania corporation. Shortly thereafter, pursuant to stipulation, Dynamic amended its complaint by adding Wal-bridge-Aldinger, a Michigan corporation, and claimed entitlement to the funds Pullman allegedly owed it under the bond INA issued for Walbridge-Aldinger to the University.

Walbridge-Aldinger and INA promptly moved to dismiss the suit under Fed.R. Civ.P. 12(b)(6), arguing that Dynamic, a sub-sub-subcontractor, was not a “claimant” as defined in the INA bond and thus could not recover under it. According to INA’s bond, a “claimant” is “one having a direct contract with the Principal or with a Subcontractor of the Principal for labor, material, or both, used or reasonably required for use in the performance of the Contract_” The bond, therefore, protected only labor or material suppliers which could be deemed “sub-subcontractors.”

In its brief in opposition to the defendants’ motion to dismiss, Dynamic conceded that it was not a “claimant” under the INA bond but made the following three-part argument:

- The INA bond was required by the act set out at Mich.Comp.Laws §§ 129.201-129.211.
- That act requires a bond to cover all those who provide labor or materials to a public project, and
- The INA bond must be read as though it complied with the terms of that act.

After a flurry of briefing, the district court allowed Dynamic to file another amended complaint incorporating its new theory of entitlement to recover under the INA bond.

Walbridge-Aldinger and INA moved to dismiss the second amended complaint on the ground that the requirements of Mich. Comp.Laws §§ 129.201-129.211 (“the bonding act”) did not apply to Walbridge-Al-dinger’s construction contract with the University and that, at any rate, its liability did not, by the terms of its bond, extend to remote claimants like Dynamic. The motion was denied, as was a later motion for summary judgment. However, the district court granted Dynamic a partial motion for summary judgment, holding that Dynamic had performed all its duties under the Pullman contract; that the amount in dispute was $253,647.18; and that it could assert a claim against Walbridge-Aldinger and INA’s bond because, as read in connection with the bonding act, the bond protected all labor and material suppliers to the project. The only remaining issue was whether Dynamic timely notified Walbridge-Aldinger and INA of its claim according to the terms of the INA bond. Following a bench trial on April 17 and 18, 1989, the district court found that Dynamic’s claim was timely filed and entered a $253,647.18 judgment for Dynamic, plus $40,541.18 interest and costs, on May 17, 1989.

Walbridge-Aldinger and INA now appeal from that judgment, assigning five errors alternatively. They assert: 1) the bonding act is not applicable to the Walbridge-Al-dinger/University of Michigan construction contract; 2) if the bonding act applies, it does not protect sub-sub-subcontractors like Dynamic; 3) if the bonding act applies and protects sub-sub-subcontractors, Dynamic nevertheless cannot claim under it because Dynamic failed to comply with its notice provisions; 4) if all their above claims fail, they are entitled to reversal because the district court erred when it engrafted provisions of the bonding act into their bond agreement; and 5) regardless of the prior issues, the district court erred in granting summary judgment on the amount of damages involved in this case.

Because we reverse the district court’s ruling on the threshold question of the bonding act’s applicability, we do not address Walbridge-Aldinger’s and INA’s other assignments of error. We are guided by our obligation to apply Michigan substantive law, see Erie R.R. Co. v. Tompkins, 304 U.S. 64, 58 S.Ct. 817, 82 L.Ed. 1188 (1938), and engage in a de novo review of the legal question of the bonding act’s applicability. See Michigan Consol. *126 Gas Co. v. Panhandle E. Pipe Line Co., 887 F.2d 1295, 1299 (6th Cir.1989), cert. denied, — U.S. -, 110 S.Ct. 1806, 108 L.Ed.2d 937 (1990).

II.

The portion of the bonding act upon which the district court predicated its judgment for Dynamic states, in pertinent part:

Before any contract, exceeding $50,-000.00 for the construction, alteration, or repair of any public building or public work or improvement of the state or a county, city, village, township, school district, public educational institution, other political subdivision, public authority, or public agency hereinafter referred to as the governmental unit,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
912 F.2d 123, 1990 U.S. App. LEXIS 14535, 1990 WL 120315, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dynamic-heating-pumping-company-v-insurance-company-of-north-america-ca6-1990.