Dynamic Construction Company, Inc. v. Village of Archbold

61 F.3d 903, 1995 U.S. App. LEXIS 26242, 1995 WL 418294
CourtCourt of Appeals for the Sixth Circuit
DecidedJuly 13, 1995
Docket94-3023
StatusUnpublished
Cited by1 cases

This text of 61 F.3d 903 (Dynamic Construction Company, Inc. v. Village of Archbold) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dynamic Construction Company, Inc. v. Village of Archbold, 61 F.3d 903, 1995 U.S. App. LEXIS 26242, 1995 WL 418294 (6th Cir. 1995).

Opinion

61 F.3d 903

NOTICE: Sixth Circuit Rule 24(c) states that citation of unpublished dispositions is disfavored except for establishing res judicata, estoppel, or the law of the case and requires service of copies of cited unpublished dispositions of the Sixth Circuit.
DYNAMIC CONSTRUCTION COMPANY, INC., Plaintiff-Appellant,
v.
VILLAGE OF ARCHBOLD, Defendant-Appellee.

No. 94-3023.

United States Court of Appeals, Sixth Circuit.

July 13, 1995.

Before: JONES, NELSON, and RONEY, Circuit Judges.*

PER CURIAM.

Plaintiff Dynamic Construction Company, Inc. ("Dynamic") is appealing a district court's decisions granting Defendant Village of Archbold's ("Archbold") Motion for Judgment on the Pleadings and denying Dynamic's Motion for Reconsideration and Motion for Leave to File an Amended Complaint. Dynamic claims that the district court erred in making these decisions. We affirm.

I.

The district court's decisions stemmed from a complaint that Dynamic filed against Archbold and Jones & Henry Engineers, Ltd. ("J&H"). The complaint set forth twelve "causes of action" against the Defendants that arose from a construction contract, "Contract 40," between Dynamic and Archbold. Contract 40 was executed to provide an addition to Archbold's water treatment plant. Dynamic sought damages of approximately $800,000, plus interest, for undue delays, contract payments withheld, and non-payment for extra work. Dynamic also sought damages of $2,000,000 for injury to its business reputation.

Because this case was resolved through a motion for judgment on the pleadings filed pursuant to Federal Rule of Civil Procedure 12(c), the district court was required to take all factual allegations in the complaint as true. Paskvan v. City of Cleveland Civil Serv. Comm'n, 946 F.2d 1233, 1235 (6th Cir. 1991). Dynamic's complaint revealed the following facts.

In 1981, Archbold solicited bids for an addition to its water treatment plant. J.A. at 15. Archbold retained J&H, as engineer, to design the addition and prepare various contract documents, all of which came to be known as Contract 40. J.A. at 16. Contract 40, as originally drafted, contemplated a general contractor that would subcontract various aspects of the project. Archbold subsequently divided the contract into four prime contracts pursuant to an injunction. Archbold awarded the contract for Division A (General Work) to Dynamic and awarded the other prime contracts to Meinhart Electric, Inc., W.F. Plumbing and Heating, Inc., and L.R. Babcock Plumbing & heating Co., Inc. Under Contract 40, J&H was designated and authorized to act as Archbold's agent, particularly during the construction period. J.A. at 16-17.

Contract 40 provided that Dynamic was responsible for all work and materials needed to complete the addition to Archbold's water treatment plant and appurtenant work, except for work to be performed and materials to be furnished by the other prime contractors, who were also responsible for their respective appurtenant work. Contract 40, as between Archbold and Dynamic for General Work, included a lump sum contract price of $4,071,000 plus unit price amounts of $247,000 for reinforcing steel and $733,410 for concrete, bringing the total contract price to $5,051,410. During the course of performance of Contract 40, Archbold and/or J&H issued change orders modifying the scope of Dynamic's contract work and adding a total of $3794.10 to the contract price. This brought the total contract price to $5,055,204.10. J.A. at 17. In breach of Contract 40, Archbold allegedly refuses to pay Dynamic $69,813.15, which is due on the contract. J.A. at 20 (First Cause of Action).

During the course of the construction, Dynamic provided an additional 38,972 pounds of reinforcing steel above J&H's estimated quantity of 650,000 pounds for which Dynamic claims Archbold owes it $14,809.36, plus a lump sum cost of $540. J.A. at 17. Archbold allegedly approved and allowed 28,793 pounds of the 38,972 pounds of reinforcing steel claimed by Dynamic, but Archbold allegedly refuses to pay for any extra reinforcing steel unless Dynamic releases its claims for the balance and all other claims. J.A. at 22 (Third Cause of Action).

Dynamic also provided 666.75 cubic yards of Class A concrete over and above J&H's estimated quantity of 5,220 cubic yards, for which Archbold allegedly owes Dynamic $93,678. J.A. at 18. Dynamic contends that Archbold and J&H approved and allowed 182.69 of the 666.75 cubic yards claimed by Dynamic, but Archbold allegedly refuses to pay for any extra Class A concrete unless Dynamic releases its claims for the balance and all other claims. J.A. at 22 (Third Cause of Action). Furthermore, Dynamic provided 251.25 cubic yards of 4-sack concrete and 141 cubic yards of 5-sack concrete for which Archbold allegedly owes Dynamic $52,596, which Archbold refuses to pay. J.A. at 18, 22-23 (Third Cause of Action).

During construction, a dispute arose concerning certain washwater pumps that Dynamic installed. J.A. at 20 (Second Cause of Action). J&H prepared the specifications for the washwater pumps and approved pre-manufacturing specifications that the manufacturer submitted. Meinhart Electric installed the electrical connection for the pumps based on J&H's design. J&H refused to approve the start-up of the pumps on the basis of "improper" electrical controls, and J&H refused to accept the pumps on the basis of "improper" motor installation. J.A. at 20-21. These refusals, which Dynamic claims were arbitrary, unreasonable, capricious and in bad faith, allegedly caused Dynamic to suffer direct damages of $6,106.73 (the cost of the washwater pumps) and delay damages incident to a 95-day delay of $172,088. J.A. at 21.

During construction, Dynamic claims that it performed substantial work and provided substantial materials, totalling approximately $19,500, which was the responsibility of the other prime contractors. J.A. at 23 (Fourth, Fifth, and Sixth Causes of Action). Dynamic also allegedly performed substantial work and provided substantial services not called for by any of the four prime contracts, but Archbold refuses to pay Dynamic for this extra work, too. J.A. at 23-24 (Seventh Cause of Action).

In preparing the plans and specifications for the construction, J&H specified a lead-based paint for application to the filter walls. J.A. at 24 (Eighth Cause of Action). As a result, the painting subcontractor applied the lead-based paint as specified. Id. When Dynamic discovered this error, it removed the lead-based paint from the filter walls and repainted the filter walls with non-lead-based paint. Id. As a result of J&H's error, Dynamic allegedly suffered direct damages of $30,550.16 and delay damages incident to an 80-day delay of $141,929.07. Id.

Dynamic claims that J&H's plans and specifications relating to the design and placement of certain valves were negligent and incorrect in that the shear pins provided in the valves were reversed and the valves were designed to operate in the wrong direction. J.A.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Curb v. MCA Records, Inc.
898 F. Supp. 586 (M.D. Tennessee, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
61 F.3d 903, 1995 U.S. App. LEXIS 26242, 1995 WL 418294, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dynamic-construction-company-inc-v-village-of-archbold-ca6-1995.