Dyer v. Wm. M. Sutherland Building & Contracting Co.

13 S.W.2d 1056, 321 Mo. 1015, 1929 Mo. LEXIS 718
CourtSupreme Court of Missouri
DecidedFebruary 11, 1929
StatusPublished
Cited by5 cases

This text of 13 S.W.2d 1056 (Dyer v. Wm. M. Sutherland Building & Contracting Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dyer v. Wm. M. Sutherland Building & Contracting Co., 13 S.W.2d 1056, 321 Mo. 1015, 1929 Mo. LEXIS 718 (Mo. 1929).

Opinion

*1018 RAGLAND, J.

This is an action for personal injuries. Respondent states the ease from one angle and the appellant from another. In order to save time we adopt in part the statement of each as constituting a general statement oi; the case as a whole.

“The appellant, Frank P. Dyer, a carpenter by trade, was employed by the respondent, W. M. Sutherland Building & Contracting Company, on construction work which it was doing for the Continental Portland Cement Company at Continental, Missouri, near St. Louis.

“The respondent was engaged in constructing six concrete silos, which were built in tvro parallel rows of three each, the silos being connected by walls running from the bottom to the top, so that there were two enclosed wells between the six silos, one between the two to the north and the two in the middle, and one between the two to the south and the two in the middle.

“Plaintiff was employed as a carpenter, and on October 29, 1920, the day on which he claims to have been injured, he was working at the bottom of the south well — that is, the well formed by the four curving walls and connecting walls of the two southernmost silos and the two immediately north thereof.

“At the time of his alleged injuries three of the silos had been completed, with the exception of capping, and each of the other three silos upon which -work was progressing had reached a level of about twenty-four feet in height.

*1019 “All oí the evidence showed that the silos were constructed in four-foot sections, the forms, being made by segments eight feet long and four feet high, and the carpenters would set up a form for a foui’-foot section and after the concrete had been poured and had hardened another four-foot form would be placed on top of the first, and so the silos were built up four feet at a time.

“All of the evidence showed that inside the well in which plaintiff was working' there was built a scaffold formed by 4x4’s, which ran from the ground or foundation up to the top, and 2x6 ledgers were fastened across the 4x4’s at whatever height was desired for the platform, 2x10 planks then being laid on top of the ledgers to form the surface of the platform. This scaffold or platform was, of course, built within the irregularly-shaped space formed by the conjunction of the four convex walls of the silo with the connecting or abutting walls.

“The plaintiff testified that at the time he was injured he was working in the bottom of the well, with concrete walls rising' some twenty-four feet on all sides of him. He was engaged, with his partner, Mr. Patrick Morrison, also a carpénter, in taking out and nailing on braces to the 4x4’s which supported the scaffold or platform. While engaged in this work he was struck, on the shoulder by a piece ol 2x4 lumber about five feet long. He did not see the piece of 2x4 fall and had no knowledge where it came from, except that it came from above. . . .

“The defendant’s evidence was descriptive of the method used in constructing the silos, and was all to the effect that as the work progressed and a four-foot section on a silo had been completed, it was necessary to raise the forms up through the platform and to raise up the platform from time to time so that forms; were taken up through the platform nearly every day, and the platform was raised about four times a week. It also appears from the evidence of both plaintiff. and defendant that in the progress of the work it was necessary for workmen to pass continually up and down through the platform and to be taking material through the platform.

“The defendant’s evidence is also to the effect that it was necessary to have openings in the platform, not only to permit the moving of the concrete forms and other materials necessary in the work, but! to provide light for men who were constantly working below the platform and down in the well, and that all light came from above and through the platform.” . . .

“The amended petition, on which the cause was tried, as ground for recovery, sets out Section 6802 of the Revised Statutes of Missouri 1919, which provision is as follows:

“ ‘All scaffolds or structures used in or for the erection, repairing or taking down of any kind of building shall be well and safely supported, and of sufficient width, and so secured as to insure the safety *1020 of persons working thereon, or passing under or about the same, against the falling thereof, or the falling of such materials or articles as may be used, placed or deposited thereon.’

“The petition also charges common-law negligence in the failure to exercise ordinary care to furnish plaintiff a reasonably safe place in which to work, in that defendant negligently failed to have lumber which was in use on the overhead platform so placed or guarded with standards, or to have placed covers over each of the holes or open places left in the platform, as to prevent materials from falling from the platform to the place where plaintiff was at work.

“The answer of the defendant was a general denial of the allegations of the petition, and a further answer alleging that the statute pleaded in the petition, to-wit, Section 6802 of the Revised Statutes of Missouri 1919, was beyond the competence and power of the Legislature of the State of Missouri to enact and is unconstitutional and void, in six respects, separately and specially pleaded, including the' fifth ground, which was sustained by the trial court, to-wit, that the statute violated and was in conflict with Section 28 of Article IV of the Constitution of the State of Missouri, in that the subject-matter of said Section 6802 was not within the purview of the title of the act of the Legislature of Missouri, of which said section is a part, nor is said subject-matter of said Section 6802 clearly expressed in the title to said act.”

At the close of the evidence the court by an instruction withdrew from the consideration of the jury the alleged statutory negligence, on the ground that the statute isi unconstitutional. The case was then submitted on the charges of common-law negligence, and a verdict for defendant was returned. On this appeal but one ruling of the trial court is assigned as error, that holding said Section 6802 unconstitutional.

I. The validity of Section 6802 is challenged in this court on the single ground that the title of the act of which it was originally a part did not conform to the requirements of Section 28, Article IV, of the Constitution. The title of that act, passed in 1891 (Laws 1891, p. 159), was: “An Act relating to manufactur-mechanical, mercantile and other establishments and places, and the employment, safety, health and work hours of employees.” For a statement of the specific grounds of respondent’s challenge to Section 6802 we quote from its brief:

“The addition of the words (‘and other establishments and places’) does not broaden the subject of the act to include establishments and places other than those relating- to manufacturing and mechanical and mercantile businesses, and the title of the act clearly indicates on its face that the subject of the act is solely a regulation of the safety, health and work hours of employees working in such busi

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pentecost v. Terminal Railroad Co.
66 S.W.2d 533 (Supreme Court of Missouri, 1933)
Pentecost v. St. Louis Merchants Bridge Terminal Railroad
66 S.W.2d 533 (Supreme Court of Missouri, 1933)
Gordon v. Muehling Packing Co.
40 S.W.2d 693 (Supreme Court of Missouri, 1931)
Brackett v. James Black Masonry & Contracting Co.
32 S.W.2d 288 (Supreme Court of Missouri, 1930)
Sloan v. Polar Wave Ice & Fuel Co.
19 S.W.2d 476 (Supreme Court of Missouri, 1929)

Cite This Page — Counsel Stack

Bluebook (online)
13 S.W.2d 1056, 321 Mo. 1015, 1929 Mo. LEXIS 718, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dyer-v-wm-m-sutherland-building-contracting-co-mo-1929.