DWP General Contracting, Inc., V Wilson Architects, Pllc

CourtCourt of Appeals of Washington
DecidedMarch 4, 2025
Docket59099-9
StatusUnpublished

This text of DWP General Contracting, Inc., V Wilson Architects, Pllc (DWP General Contracting, Inc., V Wilson Architects, Pllc) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
DWP General Contracting, Inc., V Wilson Architects, Pllc, (Wash. Ct. App. 2025).

Opinion

Filed Washington State Court of Appeals Division Two

March 4, 2025

IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON

DIVISION II DWP GENERAL CONTRACTING, INC., a No. 59099-9-II Washington Corporation,

Appellant,

v.

WILSON ARCHITECTS, PLLC, a Washington UNPUBLISHED OPINION professional limited liability company; and RYAN WILSON, an individual,

Respondents.

LEE, J. — DWP General Contracting (DWP) appeals a trial court order granting Ryan

Wilson and Wilson Architects’1 motion for summary judgment and dismissing DWP’s claims.

DWP argues that there was a genuine issue of material fact as to whether Wilson proximately

caused DWP’s injury. Wilson seeks appellate attorney fees and costs.

We affirm the summary judgment order. And we deny Wilson’s request for appellate

attorney fees and costs.

FACTS

A. BACKGROUND AND LEE’S LAWSUIT AGAINST DWP

In 2015, Dr. Harold Lee hired DWP as a general contractor to build an apartment complex.

Dennis Pavlina, DWP’s president, drafted the contract for the project. The parties’ contract gave

1 DWP sued both Wilson Architects as a professional limited liability corporation and Ryan Wilson as an individual. For clarity, we refer to Ryan Wilson by his first name and to the respondents collectively as Wilson. We mean no disrespect. No. 59099-9-II

DWP 180 days after the start of construction to substantially complete the project. Wilson

Architects was the architect for the project.

DWP began construction in September 2015. In September 2016, six months after the

contracted completion date, DWP stopped work because Lee had stopped making payments.

When DWP stopped work on the project, the project was still incomplete; the apartment complex

was about only 60 percent complete at that time.

Lee contacted Ryan, an intern architect working on the project, asking him “to see if there

was anything [he] could do to help” resolve the work stoppage. Clerk’s Papers (CP) at 137. Ryan

then met with Pavlina to discuss the work stoppage. Ryan determined that the work stoppage was

the result of a breakdown in communication between DWP and Lee, so Ryan offered to act as a

mediator between the two parties and to manage the construction going forward.

Ryan e-mailed Pavlina a draft “Agreed Upon Procedures” (AUP), which set forth the terms

for DWP to resume work on the project. In that e-mail, Ryan said, “I think you have most of the

leverage at this point, so let me know . . . what changes you would like to see to get this project

moving forward again.” CP at 481. Pavlina asked Ryan to add details allowing DWP to terminate

the contract if Lee was late on payments. Throughout his communications with Ryan, Pavlina was

insistent that Lee had breached the contract by failing to timely make payments. Pavlina did not

ask Ryan to incorporate any provisions waiving consequential damages or extending the original

substantial completion date. Ryan did not know that the project was past the original contract

deadline when he drafted the AUP.

2 No. 59099-9-II

The AUP was incorporated into the original contract via a change order. Pavlina signed

the change order incorporating the AUP into the original contract without having an attorney

review the AUP.

The AUP provided that Wilson Architects would regularly visit the work site and oversee

the administration of the project, as well as coordinate and oversee the process by which DWP

applied for and received progress payments. The AUP did not mention the contract price or

deadline. And the change order incorporating the AUP, which Pavlina signed, clearly stated that

the AUP did not change the original contract price or deadline.

After Pavlina and Lee signed the change order incorporating the AUP into the original

contract, Ryan asked Pavlina to send over an updated construction schedule for the project,

commenting: “I’m sure that whatever schedule you created before is now void, which is fine. . . .

[P]lease update based on where things stand today and send it over.” CP at 37. But Pavlina never

put together an updated construction schedule for the project. Instead, Ryan regularly visited the

project site to discuss progress with Pavlina.

DWP resumed construction in October 2016 and finished the project in June 2017. When

another dispute about construction delays and payments arose, Ryan mediated the dispute at the

request of both DWP and Lee. Ryan issued a decision memo about the dispute, observing that

Lee’s complaints about the construction delays and DWP’s complains about late payments were

“more correctly treated as a breach of contract” dispute. CP at 89 (underlining omitted). Lee then

sued DWP for breach of contract, seeking damages for lost profits from the delay in finishing

construction.

3 No. 59099-9-II

At a jury trial in Lee’s lawsuit against DWP, Ryan testified that, if he had known that DWP

was well beyond the original construction deadline and in breach of the contract when he drafted

the AUP, he “would have addressed it” in the AUP. CP at 140. Ryan also testified that he had e-

mailed Pavlina about the construction schedule being void based entirely on his own assumption

that the original schedule was void. He explained, “I had not seen any previous construction

schedules and because of the walk-off, I assumed that even if one had been created, it was no

longer applicable. So I was just saying create a new construction schedule and get it to me as soon

as you can.” CP at 143.

Pavlina testified that the primary purpose of the AUP was to ensure timely responses to

construction administration matters, timely payments, and to have Ryan, not Lee, determine when

the project was substantially complete.

The jury found that DWP breached its contract with Lee. The jury awarded Lee

approximately $500,000 in damages for DWP’s breach of contract.

B. CURRENT LAWSUIT

After the jury found DWP liable for breaching its contract with Lee, DWP sued Wilson for

negligence, unauthorized practice of law, and a violation of Washington’s Consumer Protection

Act. For the negligence claim, DWP alleged that Wilson owed DWP a duty in preparing the AUP.

CP at 6. DWP alleged that “Defendants breached that duty by improperly documenting the status

of the construction, by failing to review the Construction Contract, and by failing to modify the

completion date despite stating that it was void.” CP at 6. “As a result of Defendants’ breach of

their duty,” DWP alleged that it suffered damages in the form of the “amount awarded by the jury”

4 No. 59099-9-II

in Lee’s lawsuit “plus attorneys’ fees and costs.” CP at 6. DWP also alleged that Ryan’s actions

in drafting the AUP and change order constituted the unauthorized practice of law.

1. Summary Judgment Motions

Wilson moved for summary judgment, seeking dismissal of all of DWP’s claims, and DWP

moved for partial summary judgment on its unauthorized practice of law and negligence claims.2

Wilson argued that DWP lacked “evidence to support that any action of Wilson

proximately caused DWP’s damages, let alone[] was a violation of a recognized duty.” CP at 634.

Wilson insisted that, for DWP to prevail on its negligence claim, “DWP must show that they would

have been in a better position had Wilson included language waiving the consequential damages

Free access — add to your briefcase to read the full text and ask questions with AI

Related

HERTOG, EX REL., SAH v. City of Seattle
979 P.2d 400 (Washington Supreme Court, 1999)
HIPPLE v. McFadden
255 P.3d 730 (Court of Appeals of Washington, 2011)
Smith v. Preston Gates Ellis, LLP
147 P.3d 600 (Court of Appeals of Washington, 2006)
Lutz Tile, Inc. v. Krech
151 P.3d 219 (Court of Appeals of Washington, 2007)
James F. Behla v. R.J. Jung, LLC
453 P.3d 729 (Court of Appeals of Washington, 2019)
Christopher W. Sartin v. Alonzo Mcpike
475 P.3d 522 (Court of Appeals of Washington, 2020)
Hertog v. City of Seattle
138 Wash. 2d 265 (Washington Supreme Court, 1999)
Hungerford v. Department of Corrections
139 P.3d 1131 (Court of Appeals of Washington, 2006)
Smith v. Ellis
135 Wash. App. 859 (Court of Appeals of Washington, 2006)
Lutz Tile, Inc. v. Krech
136 Wash. App. 899 (Court of Appeals of Washington, 2007)
Hipple v. McFadden
161 Wash. App. 550 (Court of Appeals of Washington, 2011)
Viking Bank v. Firgrove Commons 3, LLC
334 P.3d 116 (Court of Appeals of Washington, 2014)
W.m. And Erin Olson, V. State Of Washington
498 P.3d 48 (Court of Appeals of Washington, 2021)

Cite This Page — Counsel Stack

Bluebook (online)
DWP General Contracting, Inc., V Wilson Architects, Pllc, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dwp-general-contracting-inc-v-wilson-architects-pllc-washctapp-2025.