Dusenberry v. Westchester and Connecticut Traction Co.

46 A.D. 267
CourtAppellate Division of the Supreme Court of the State of New York
DecidedJuly 1, 1899
StatusPublished
Cited by5 cases

This text of 46 A.D. 267 (Dusenberry v. Westchester and Connecticut Traction Co.) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dusenberry v. Westchester and Connecticut Traction Co., 46 A.D. 267 (N.Y. Ct. App. 1899).

Opinion

Hatch, J.:

This is a motion upon the return of an order to show cause why a temporary injunction granted herein restraining the defendant from constructing or operating its railroad on any street or avenue in the town' of Eastchester,/in the county of ’Westchester,, should not be continued. The motion to continue the temporary injunction' is rested upon two grounds : First, that the consent given by the commissioner of highways of the town of Eastchester to the predecessor of the defendant, to construct, maintain and operate.its railroad, was subject to a condition that such road, its branches and extensions, should be completed and in running order by the 1st day of January, 1897, else the franchise based upon such consent should cease and determine. It is claimed that this condition was not complied with, and in consequence the predecessor of the defendant forfeited its right to construct the road; and that the defendant has acquired no other or different right than it possessed, and is, therefore, without authority in law to construct its road. Second, that even though it possesses such authority, yet that it has failed to obtain.the .consents of the owners of two-thirds in valúe of the property bounded upon the street where it is presently engaged in constructing its. road. If either or both of these contentions are well founded, then it follows that the plaintiff established a case entitling her to have the temporary injunction continued. The consent of the commissioner of highways of the town of Eastchester was given on the 12th day of May, 1896, and was accepted by the North Mount Vernon Railway Company, the predecessor of- the defendant, on the twenty-seventh day of the same month. It was provided in the 12th clause of such consent as follows : That if such branches or extensions of said road aré not completed and in running order by the first day of January, eighteen hundred and ninety-seven, then this franchise shall be forfeited, and the rights and privileges granted by-it shall cease and determine without any action or proceeding in law or otherwise.” By the 13th clause of the consent it was provided that such franchise should become binding upon the town of Eastchester upon the acceptance by said company within thirty days of the obligations and conditions thereof, and that upon such acceptance the franchise granted thereby should constitute the contract and be the measure of the rights‘and liabilities [269]*269of the town and of. the company, its successors and assigns. It is conceded in the record that compliance with the conditions of this franchise was not made by the North Mount Vernon Railway Company nor by the defendant. If, therefore, this condition be suchas the highway, commissioner of the town had the right to' impose, and if compliance therewith has not been waived, and if there exist no facts upon which non-compliance by the railroad company can be excused, then it follows that this defendant has no right in the street and no franchise to construct and operate its railroad thereon. So far as is disclosed by the papers in opposition to this motion, no excuse whatever is made or attempted to be made for the non-compliance with the condition thus imposed as matter of fact. The defendant rests its claim solely upon the ground that the condition imposed-is void ; and it must stand or fall, so far as the present right to an injunction is concerned, upon its ability to maintain this proposition.

The determination below in favor of the defendant proceeded upon the ground that the consent vested in the defendant an absolute franchise, which, having been once vested, could not be divested by a condition subsequent, and that a breach of such condition did not’ work a forfeiture of the franchise. This holding proceeded upon the general doctrine that the breach of a condition subsequent, which is malum prohibitum, only, does not defeat the vesting of an estate, as it is in its nature repugnant to the estate which has been granted ;. and this doctrine is undoubtedly the law as stated by the learned court below. ' It does not follow, however, as is recognized by the learned court, that executory conditions which the party has be the right to impose upon the right or estate which it grants, may not enforced, 'or that upon failure to perform such conditions the grantee does not become divested of the estate which he has received. The ■ court held, however, that the condition which we have heretofore quoted was not within the power of the highway commissioner of the town to impose; that for that reason the condition was void, and the consent vested in the railroad company an absolute franchise. This ruling proceeds upon the ground that by virtue of the provisions of sections 93 and 99 of the Railroad Law (Laws of 1890, chap. 565) the railroad is to be constructed within three years after the consents therefor have been granted, arid the conclusion is reached that the statute itself furnishes the only limitation as to [270]*270time of construction which may be lawfully imposed. Section 93 of the Railroad Law (Laws of 1890, chap. 565, as amd. by Laws of 1893, chap. 434) provides : “ The local authorities may, in their disr cretion, make their consent to depend upon any further conditions respecting other or further security or deposit, suitable to secure the construction, completion and operation of the railroad within anytime not exceeding the period prescribed in this article,”. etc. Section 99 provides that if a railroad shall not complete the construction of its railroad within three years after obtaining the necessary consents, “ its right, privileges and franchises shall cease and determine.” We understand the rule to be that where the Legislature, in the exercise of its sovereign power, has regulated the subject-matter, it is not competent for other persons charged with the duty of giving consent to -the performance of a particular act to impose other or different conditions, as such conditions will be' deemed opposed to a sound public policy. (Beekmam v. Third Avenue R. R. Co., 153 N. Y. 144.)

The question which confronts us is whether the Legislature in,the exercise of its authority, has imposed an absolute rule of limitation as to the time within which a railroad shall be constructed after it has obtained the consent of the proper authorities for its’ construction,. or whether the persons or body authorized to give the-consent may impose a condition that it shall be constructed within a shorter time. It is to be observed in construing this statute that by its terms a forfeiture may be worked unless the railroad constructs within the period limited thereby. There is nothing in the statute which places any limitation whatever on the time when the construction must be made. Its provision is,-that unless within the given period it does construct, such failure may work a forfeiture. If the persons or body possessed of the power to give consent may not impose any condition, then such persons or body are limited in authority to grant or deny. But such is evidently not the purpose of the statute, for therein is reserved the right. to secure the -construction, completion and operation of the railroad within anytime not exceeding the period prescribed by the statute, and also upon such further' conditions as will be for the public interest. It would seem as if, by the very language of the statute, a condition might be imposed by the persons or body giving the consent in respect to [271]*271the particular matter of construction, the only limitation thereon being that they would not be authorized to extend the time beyond three years, the period prescribed by the statute; and such seems to.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bohl v. City of Schenectady
128 Misc. 863 (New York Supreme Court, 1927)
Farnsworth v. . Boro Oil Gas Co.
109 N.E. 860 (New York Court of Appeals, 1915)
Manton v. South Shore Traction Co.
104 N.Y.S. 612 (New York Supreme Court, 1907)
South Shore Traction Co. v. Town of Brookhaven
116 A.D. 749 (Appellate Division of the Supreme Court of New York, 1907)
Adee v. Nassau Electric Railroad
65 A.D. 529 (Appellate Division of the Supreme Court of New York, 1901)

Cite This Page — Counsel Stack

Bluebook (online)
46 A.D. 267, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dusenberry-v-westchester-and-connecticut-traction-co-nyappdiv-1899.