Durkee Lumber Co. v. Department of Conservation & Natural Resources

903 A.2d 593, 2006 Pa. Commw. LEXIS 386
CourtCommonwealth Court of Pennsylvania
DecidedJuly 13, 2006
StatusPublished
Cited by7 cases

This text of 903 A.2d 593 (Durkee Lumber Co. v. Department of Conservation & Natural Resources) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Durkee Lumber Co. v. Department of Conservation & Natural Resources, 903 A.2d 593, 2006 Pa. Commw. LEXIS 386 (Pa. Ct. App. 2006).

Opinion

OPINION BY

Judge PELLEGRINI.

Durkee Lumber Co., Inc. (Protestant) appeals a determination of the Secretary of the Department of Conservation and Natural Resources (Purchasing Agency) denying its bid protest and affirming the Purchasing Agency’s decision to reject its bid because it had a record of non-compliance in state forest timber sales.

Because it had defaulted on contracts that it had entered into with the Commonwealth, Protestant had been placed in the Contractor Responsibility Program which, according to a Governor’s Management Directive, would “provide evidence of your non-responsibility.” 1 On August 17, 2005, the Purchasing Agency solicited bids for timber sale No. 15-2005BC03 (Pokeweed Timber Sale) located in Susquehannock State Forest, Abbot Township, Potter County, Pennsylvania. Protestant was the highest bidder with a bid price of $467,000, which was $79,232 higher than the next highest bid price. By letter mailed September 2, 2005, the Purchasing Agency notified Protestant that, among other things, it was the highest bidder but not the highest responsible bidder because of its non-performance on previous state forest timber sales. 2

Protestant then submitted a bid protest 3 asserting that the Pokeweed Timber *595 Sale contract should properly have been awarded to it on the grounds that:

1. [Protestant] was the highest responsive 4 and responsible bidder 5 and its bid complied in all material respects with the bid instructions and [Purchasing Agency] regulations concerning timber sales contracts.
2. It is untrue that [Protestant] has “a record of non-compliance on previous State Forest timber sales.” To the contrary, with the exception of a prior default completely outside the responsibility or control of [Protestant], [it] has faithfully performed all timber sales contracts awarded to it by the Commonwealth of Pennsylvania. Your [Purchasing Agency] previously wrongfully terminated two timber sale contracts awarded to [Protestant] in 2004. However, [Protestant] filed a timely statement of claim as to the wrongful termination of those contracts and the [Purchasing Agency] has not responded to that claim. [Protestant] intends to file an appropriate action with the Board of Claims as a result of the [Purchasing Agency’s] failure to respond to [its] statement of claim previously filed with the [Purchasing Agency] on those contracts. 6 The [Purchasing Agency] had no legitimate basis for the termination of the two contracts.
3. The action of the [Purchasing Agency] in rejecting [Protestant’s] bid on the present timber sale contract constitutes an attempt to debar or suspend [it] from consideration for the award of contracts without reasonable notice or reasonable opportunity to be heard and without a basis in substantial evidence, all as required under 62 Pa.C.S. § 531. 7
4. The rejection of the bid of [Protestant] would deprive the Commonwealth and its taxpayers of the benefit of *596 awarding the timber sales contract to the highest responsible bidder as required under the competitive bidding law.

(Respondent’s Reproduced Certified Record at P5.) Protestant included a request for a hearing in its bid protest letter.

On October 18, 2005, the Secretary invited Protestant and the Purchasing Agency to submit documents and information to aid in his determination on the bid protest. 8 Both parties made submissions and were given the opportunity to examine and comment on each other’s submissions. The parties neither responded nor objected to any submission made by the other party. The Purchasing Agency’s submissions included information on Protestant’s involvement in the only four timber sales of record, which stated:

1) In February of 1997, Protestant executed the contract for timber sale 11-94BC01 and started the first phase of work on June 24, 1997, but stopped working on June 30, 1997, due to financial problems. After the Purchasing Agency gave Protestant numerous extensions and expressions of willingness to provide assistance, the Assistant State Forester terminated the contract in July of 1999.
2) Protestant was the only bidder on timber sale 11-2000BC01 with a bid price of $65,300, which had an acceptable minimum bid of $20,607. However, Protestant withdrew its accepted bid and the Purchasing Agency had to reinstate the bidding process.
3)Protestant also bid on timber sales 15-2003BC11 and 15-2003BC01. Because the Purchasing Agency had experience with Protestant not completing sales, it requested that Protestant provide start and finish dates for the haul roads and timbering. These dates were incorporated into the contracts and failure to meet them was cause for termination. Road construction for timber sale 15-2003BC11 was to be completed on August 1, 2004, and for timber sale 15-2003BC01 on September 1, 2004; however, by September 7, 2004, neither road had been started. Furthermore, the Purchasing Agency was notified that Protestant was harassing the supervisory foresters. By notice dated November 10, 2004, the Purchasing Agency terminated both timber sale contracts for failure to comply with the contract terms.

After reviewing the submissions made by both parties, the Secretary found that no material dispute regarding the facts existed to necessitate the holding of a hearing. Based on those submissions, the Secretary determined that Protestant had a record of non-compliance on timber sales; did not qualify as a responsible bidder because it was wanting in the “good faith performance” aspect of that status; and there was no evidence of record that the Purchasing Agency either attempted to bypass or put the procedures for debarment in motion, and denied Protestant’s bid protest. Protestant filed this appeal contending that the Secretary was required to provide it with a due process *597 hearing before deciding that its bid was properly rejected. 9

Pursuant to 62 Pa.C.S. § 1711.1(e), the Secretary has “sole discretion” to decide whether a hearing is necessary to decide a bid protest. His decision not to hold a hearing can only be reversed if he exercised his discretion with bad faith, fraud, capricious action or abuse of power. Cardiac Science, Inc. v. Department of General Services, 808 A.2d 1029 (Pa.Cmwlth.2002). 10 Where there are of record sufficient unchallenged facts necessary to make the required determination, no hearing is required. Glasgow, Inc. v. Department of Transportation,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sidelines Tree Service, LLC v. DOT
Commonwealth Court of Pennsylvania, 2022
Ascend Mgmt. Innovations LLC v. DHS
Commonwealth Court of Pennsylvania, 2018
UnitedHealthcare of Pennsylvania, Inc. v. Department of Human Services
172 A.3d 98 (Commonwealth Court of Pennsylvania, 2017)
Centurylink Public Communications, Inc. v. Department of Corrections
109 A.3d 820 (Commonwealth Court of Pennsylvania, 2015)
JPay, Inc. v. Department of Corrections
89 A.3d 756 (Commonwealth Court of Pennsylvania, 2014)
Stanton-Negley Drug Co. v. Department of Public Welfare
943 A.2d 377 (Commonwealth Court of Pennsylvania, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
903 A.2d 593, 2006 Pa. Commw. LEXIS 386, Counsel Stack Legal Research, https://law.counselstack.com/opinion/durkee-lumber-co-v-department-of-conservation-natural-resources-pacommwct-2006.