Dunleavy v. YATES CONST. CO., INC.

416 S.E.2d 193, 106 N.C. App. 146, 1992 N.C. App. LEXIS 446
CourtCourt of Appeals of North Carolina
DecidedMay 5, 1992
Docket9018SC333
StatusPublished
Cited by27 cases

This text of 416 S.E.2d 193 (Dunleavy v. YATES CONST. CO., INC.) is published on Counsel Stack Legal Research, covering Court of Appeals of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dunleavy v. YATES CONST. CO., INC., 416 S.E.2d 193, 106 N.C. App. 146, 1992 N.C. App. LEXIS 446 (N.C. Ct. App. 1992).

Opinion

GREENE, Judge.

Plaintiffs appeal from an order entered 8 November 1989 granting summary judgment for Yates Construction Company (Company), Robert Yátes, Douglas Yates, and Donald Baynes (Baynes). Plaintiffs also appeal from an order entered 9 November 1989 dismissing the plaintiffs’ complaint as to Springfield Properties (Springfield) for failure to state a claim upon which relief can be granted.

In October, 1985, Company, an independent contractor, contracted with Springfield to construct, among other things, sewer lines within the Raven Ridge Subdivision located in Guilford County, North Carolina. Springfield owned the property on which the subdivision was being built. At this time, Johnny Glenn Cobb, II (Cobb) worked for Company as a member of a “new and inexperienced pipe crew.” Cobb had no prior experience on a pipe crew. On 17 October 1985, Cobb and the other members of the crew arrived with their equipment‘at the Raven Ridge work site to begin installing the sewer lines. Before 17 October 1985, the pipe crew had been digging trenches to lay water lines at a location different than the Raven Ridge work site. They did not begin any trench work that day because Baynes, the crew foreman, did not plan to make much progress with such a new and inexperienced crew.

On the morning of 18 October 1985, the pipe crew began the first leg of the trench work at the Raven Ridge work site. The soil at the work site was “firm and stable.” At no time that morning did the depth of the trench exceed five feet. Douglas Yates, vice *150 president of Company, “requested that trench boxes owned by the company be transferred from another construction site for use during the progress of the construction work at the Raven Ridge subdivision . . . .” By the afternoon, the pipe crew had begun the second leg of the trench work. In the early stages of this second leg, the trench was not to exceed five feet in depth. Baynes was called away to another side of the project, and while he was gone, the operator of the backhoe made more progress than Baynes had expected. In fact, the operator of the backhoe was digging well ahead on the pipe laying crew. When Baynes left, the trench did not exceed five feet in depth. While Baynes was gone, however, the digging increased at such a rate that before Baynes could return to the trench, the trench exceeded five feet in depth in certain parts. According to Robert Yates, president of Company, “it was the policy of the Company to use trench boxes or slope the sides of a trench when conditions warranted such action, including whenever the depth of a trench exceeded five feet . . . .” It is undisputed that Occupational Safety and Health Act (OSHA) regulations in effect at the time required trenches of more than five feet in depth to be properly supported. This trench, however, was approximately 150 feet long, the walls of the trench were vertical and had not been shored, sloped, braced, or otherwise supported to prevent a collapse, and the trench boxes which Douglas Yates had requested had not yet arrived. While Cobb was in a portion of the trench where the depth exceeded five feet, a small portion of one side of the trench collapsed and struck Cobb in the head resulting in his death. Cobb, contrary to OSHA regulations, had not been provided a hard helmet and consequently was not wearing such protective equipment at the time of his death. Baynes was not present when the trench collapsed.

The plaintiffs, in addition to filing a claim for workers’ compensation benefits, filed a complaint against Company, Robert Yates, Douglas Yates, Baynes, and Springfield. As to Company, Robert Yates, Douglas Yates, and Baynes, the plaintiffs alleged that Cobb’s death was the result of a deliberate and intentional assault and willful, wanton, and reckless negligence. As against Springfield, the plaintiffs alleged that Springfield was liable to the plaintiffs on the theories of inherently dangerous activity, negligent selection of Company, and negligent retention of Company. On 17 July 1989, Springfield filed a motion to dismiss under N.C.G.S. § 1A-1, Rule 12(b)(6) (Rule 12(b)(6)). On 27 July 1989, the remaining defendants *151 jointly filed an answer, and on 18 August 1989, they filed a motion to dismiss under Rule 12(b)(6), and in the alternative, for summary judgment under N.C.G.S. § 1A-1, Rule 56 (Rule 56). On 26 October 1989, the plaintiffs made a motion to stay all proceedings pending the North Carolina Supreme Court’s resolution of Woodson v. Rowland, 92 N.C. App. 38, 373 S.E.2d 674 (1988), disc. rev. allowed, 324 N.C. 117, 377 S.E.2d 247 (1989). On 8 November 1989, the trial court denied the plaintiffs’ motion to stay and granted summary judgment for Company, Robert Yates, Douglas Yates, and Baynes. The next day, the trial court granted Springfield’s motion to dismiss the plaintiffs’ complaint. The plaintiffs appealed to this Court which, in an unpublished opinion, affirmed the trial court’s orders based on Woodson, 92 N.C. App. 38, 373 S.E.2d 674. Dunleavy v. Yates Constr. Co., 103 N.C. App. 804, 407 S.E.2d 905 (1991). The plaintiffs then petitioned the North Carolina Supreme Court for discretionary review of this Court’s decision, and on 6 November 1991, the North Carolina Supreme Court allowed the plaintiffs’ petition for discretionary review “for the limited purpose of entering the following order: the case is remanded to the Court of Appeals for reconsideration in light of” Woodson v. Rowland, 329 N.C. 330, 407 S.E.2d 222 (1991). Dunleavy v. Yates Constr. Co., 330 N.C. 194, 412 S.E.2d 54 (1991).

The issues are whether (I) the North Carolina Supreme Court’s decision in Woodson operates retroactively; (II) (A) the plaintiffs sufficiently alleged a cause of action for breach of the nondelegable duty of care arising from an alleged inherently dangerous activity, and (B) North Carolina law recognizes claims of an injured employee of an independent contractor for negligent selection and retention of the independent contractor; and (III) (A) this Court should remand the trial court’s order of summary judgment for Company, Robert Yates, and Douglas Yates, and (B) Baynes’ conduct towards Cobb was willful, wanton, and reckless.

I

The plaintiffs argue, and Springfield disagrees, that this Court should apply the North Carolina Supreme Court’s decision in Woodson retroactively to cases like this one arising before 14 August 1991, the date Woodson was filed.

Under the well-established judicial policy in North Carolina, decisions of the North Carolina Supreme Court “are generally *152 presumed to operate retroactively.” State v. Rivens, 299 N.C. 385, 390, 261 S.E.2d 867, 870 (1980). Furthermore, decisions of the North Carolina Supreme Court overruling former decisions are also presumed to operate retroactively. Cox v. Haworth, 304 N.C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Baker v. Reinhardt
Court of Appeals of North Carolina, 2023
Blue v. Mountaire Farms, Inc.
786 S.E.2d 393 (Court of Appeals of North Carolina, 2016)
Vaughn v. Transdev Services, Inc.
179 F. Supp. 3d 559 (E.D. North Carolina, 2016)
Burnham v. S&L Sawmill, Inc.
749 S.E.2d 75 (Court of Appeals of North Carolina, 2013)
Trivette v. Yount
735 S.E.2d 306 (Supreme Court of North Carolina, 2012)
Trivette v. Yount
720 S.E.2d 732 (Court of Appeals of North Carolina, 2011)
Dorton v. HENDRICK MOTORSPORTS, INC.
792 F. Supp. 2d 870 (M.D. North Carolina, 2011)
Blitz v. Agean, Inc.
677 S.E.2d 1 (Court of Appeals of North Carolina, 2009)
Wells v. Cumberland County Hospital System, Inc.
640 S.E.2d 400 (Court of Appeals of North Carolina, 2007)
Maraman v. Cooper Steel Fabricators
555 S.E.2d 309 (Court of Appeals of North Carolina, 2001)
Kinsey v. Spann
533 S.E.2d 487 (Court of Appeals of North Carolina, 2000)
Brice v. Sheraton Inn
527 S.E.2d 323 (Court of Appeals of North Carolina, 2000)
Lilley v. Blue Ridge Electric Membership Corp.
515 S.E.2d 483 (Court of Appeals of North Carolina, 1999)
Barrientos v. Taylor
917 F. Supp. 375 (E.D. North Carolina, 1996)
Jones v. Willamette Industries, Inc.
463 S.E.2d 294 (Court of Appeals of North Carolina, 1995)
Echols v. Zarn, Inc.
448 S.E.2d 289 (Court of Appeals of North Carolina, 1994)
Pinckney v. Van Damme
447 S.E.2d 825 (Court of Appeals of North Carolina, 1994)
McCorkle v. Aeroglide Corp.
446 S.E.2d 145 (Court of Appeals of North Carolina, 1994)
Dunleavy v. Yates Construction Co.
442 S.E.2d 53 (Court of Appeals of North Carolina, 1994)
Owens v. W. K. Deal Printing, Inc.
433 S.E.2d 793 (Court of Appeals of North Carolina, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
416 S.E.2d 193, 106 N.C. App. 146, 1992 N.C. App. LEXIS 446, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dunleavy-v-yates-const-co-inc-ncctapp-1992.