Dunbar & Sullivan Dredging Co. v. John R. Jurgensen Co.

44 F.R.D. 467, 13 Fed. R. Serv. 2d 133
CourtDistrict Court, S.D. Ohio
DecidedSeptember 14, 1967
DocketNo. 6026
StatusPublished
Cited by14 cases

This text of 44 F.R.D. 467 (Dunbar & Sullivan Dredging Co. v. John R. Jurgensen Co.) is published on Counsel Stack Legal Research, covering District Court, S.D. Ohio primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dunbar & Sullivan Dredging Co. v. John R. Jurgensen Co., 44 F.R.D. 467, 13 Fed. R. Serv. 2d 133 (S.D. Ohio 1967).

Opinion

MEMORANDUM OPINION

PORTER, District Judge.

This case started out as one involving a contract between a subcontractor and his general. The plaintiff, Dunbar & Sullivan Dredging Co. (which will be called Dunbar), is the subcontractor. The defendant, John R. Jurgensen Co., is the general contractor and the defendant, American Insurance Company is Jurgensen’s surety.

Jurgensen and American not only answered and counterclaimed but cross-claimed against another subcontractor, McGovney, without first obtaining leave to make him a defendant. McGovney nevertheless answered, and Jurgensen then moved to strike portions of Mc-Govney’s answer alleging no jurisdiction for failure to obtain leave, no diversity and no federal question. In the alternative, Jurgensen moved for an order making McGovney a defendant nunc pro tunc. American joins in Jurgensen’s motions, and they present for decision questions about third party practice which merit a full statement of facts and discussion of the applicable rules and authorities.

The facts are these: On May 6, 1963 Dunbar entered into a contract with Jurgensen to supply and place material in embankments on Ohio State Highway Project No. 736 in Clermont and Hamilton Counties. This was to be performed as part of Jurgensen’s contract (No. 1726) with the Ohio State Highway Department. Pertinent portions of the contract state: “If Dunbar & Sullivan misplace material contrary to Jurgensen’sdirection, it shall be Dunbar & Sullivan’s responsibility to move it, if moving is necessary.” And, “Dunbar & Sullivan will save harmless Jurgensen from any [471]*471and all claims and demands of every nature, arising from or out of the operations of Dunbar & Sullivan in carrying out the provisions of this agreement and will further indemnify and save harmless Jurgensen for any damage directly or indirectly caused to said project by errors or omissions of its personnel or for damage caused by the operation of any of its equipment.”

Dunbar alleges that it caused its forces to be on the project ready for work May 6, 1963, as ordered and directed by Jurgensen, but was unable to commence work until May 24, 1963, due to delays caused by Jurgensen; that after it entered upon its work, it duly prosecuted the work with diligence and in a workmanlike manner, and that it satisfactorily performed all conditions of the contract between it and Jurgensen. Dunbar further alleges that, under the contract, there became due $778,745.66, and that by acts of omission and commission by Jurgensen, contrary and beyond the contemplation of the contract, the performance of Dunbar was made more expensive and increased in the amount of $45,486.61. Dunbar claims that as a result there became due, exclusive of interest, $894,870.23, and that there was paid on account $676,536.41, leaving a balance of $218,333.82, plus 6% interest on all sums not paid by Jurgensen at the times when they became due under the contract.

Dunbar further alleges that by reason ■of the foregoing, the conditions of the bond of American were broken and the ■obligation of American as surety matured in favor of Dunbar. Dunbar alleges a demand, and a refusal of that ■demand, and, on July 21, 1965, within a period of 90 days after acceptance of the Ohio State Highway Project by the ■State of Ohio, Dunbar furnished American with a statement of the amount due it under its contract with Jurgensen, pursuant to Ohio Rev.Code § 153.56.

Dunbar brings suit in this Court for •$218,333.12, alleging diversity of citizenship. Dunbar is a New York corporation, with its principal place of business in Detroit, Michigan, and Jurgensen is an Ohio corporation, with its principal place of business in Cincinnati, Ohio. American is a New Jersey corporation. Therefore, there is present the requisite diverse citizenship.

In the answer of Jurgensen and American, the defendants claim that the total contract price is $747,632,70, and that Dunbar has been paid $676,536.41, which leaves a difference of only $71,096.29. They say this sum is not due because Dunbar placed excessive fill on various sections of the project, and that Jurgensen was, therefore, required to spend sums in excess of the amount due to remove this.

The defendants Jurgensen and American also counterclaim for damages due them by Dunbar as a result of the expenditure made in removing the fill, relying on those portions of the contract set out above. Jurgensen and American claim that Jurgensen spent $25,000 in moving the excess fill, and that Jurgensen also had a contract with McGovney, under which McGovney was to spread and place such fill, and to slope the embankment. McGovney made a claim against Jurgensen by way of mechanic’s lien for $145,890.00 for moving and disposing of the excess fill. Jurgensen and American allege that this claim is the responsibility of Dunbar because of its breach of the contract between Jurgensen and Dunbar and ask for a declaratory judgment to establish the rights of the parties.

In their answer, Jurgensen and American also set out a crossclaim against McGovney praying for a declaratory judgment and an order stating that Jurgensen’s obligation to McGovney arises out of Dunbar’s breach of contract, and to the extent Jurgensen is liable to McGovney, Dunbar should indemnify Jurgensen.

McGovney answered (after being served, but before being made a party) [472]*472alleging that this Court has no jurisdiction for the reason that Jurgensen failed to comply with Rule 13(h) of the Federal Rules of Civil Procedure by failing to apply for an order of this Court permitting Jurgensen to make McGovney a party to this action or for leave to file the crossclaim against Mc-Govney, and for the further reason that McGovney is a citizen of Ohio, and, therefore, there is no diversity of citizenship between Jurgensen and McGovney. McGovney also claims that, if this Court has jurisdiction, there is due him from Jurgensen and American the sum of $122,028.02, plus $12,786.76 for unpaid invoices for services, materials, supplies and equipment, along with $145,890.00 for work completed, and prays for judgment in his favor in the amount of $280,704.78.

The questions before this Court arise from Jurgensen and American’s motion to strike Paragraph 4 of McGovney’s answer, which states that Jurgensen and American failed to apply for or obtain an order of this Court permitting them to make this defendant (McGovney) a party to this action, or for leave to file their crossclaim against McGovney, and from the motion to strike paragraph 5 of McGovney’s answer, which states that there is no federal question herein presented, and from the motion to strike Paragraph 6 of McGovney’s answer, which denies jurisdiction of this Court by virtue of the crossclaim of Jurgensen and American. By way of alternative motion, Jurgensen and American move to have McGovney made a party-defendant to this action nunc pro tunc pursuant to Rule 13(h) of the Federal Rules of Civil Procedure, as the Rule existed at the time of Jurgensen and American’s crossclaim, and before its amendment in July, 1966. They also move, in the alternative, to have Mc-Govney made a party-defendant pursuto Rule 13(h) of the

Related

Cite This Page — Counsel Stack

Bluebook (online)
44 F.R.D. 467, 13 Fed. R. Serv. 2d 133, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dunbar-sullivan-dredging-co-v-john-r-jurgensen-co-ohsd-1967.