Dun-Par Engineered Form Co. v. Vanum Construction Co.

310 P.3d 1072, 49 Kan. App. 2d 347, 2013 WL 4499124, 2013 Kan. App. LEXIS 75
CourtCourt of Appeals of Kansas
DecidedAugust 23, 2013
DocketNo. 108,841
StatusPublished

This text of 310 P.3d 1072 (Dun-Par Engineered Form Co. v. Vanum Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dun-Par Engineered Form Co. v. Vanum Construction Co., 310 P.3d 1072, 49 Kan. App. 2d 347, 2013 WL 4499124, 2013 Kan. App. LEXIS 75 (kanctapp 2013).

Opinion

Powell, J.:

The Hanover Insurance Co. (Hanover) appeals the denial of its own motion for summary judgment and the granting [348]*348of Dun-Par Engineered Form Company’s (Dun-Par) cross-motion for summary judgment. The district court granted Dun-Par’s claim to recover the unpaid balance due Dun-Par, a sub-sub-subcontractor, from the Subcontract Payment Bond bought from Hanover by the subcontractor, Vanum Construction Co., Inc. (Vanum). Hanover challenges the district court’s interpretation of tire definition of “Claimant” as set out in tire bond.

Because we find that Dun-Par does not meet the definition of “Claimant” as set out in the Subcontract Payment Bond, we reverse the district court and remand with instructions to enter judgment for Hanover.

Factual and Procedural History

The parties agree on the following uncontroverted facts. Fortis Construction Co., LLC (Fortis) hired Dun-Par as a subcontractor for a construction project in Fort Riley, Kansas. Dun-Par was the sub-sub-subcontractor on the project. The general contractor for the project was BE&K Federal Services, LLC (BE&K). BE&K hired Vanum to be a subcontractor. BE&K and Vanum entered into a Subcontract Payment Bond through Hanover naming Vanum as the principal and BE&K as the obligee. Under this bond, Vanum and Hanover agreed to “jointly and severally, bind themselves ... to [BE&K] to pay for labor, materials and equipment furnished for use in die performance of the Subcontract....” Vanum then hired Fortis to be its sub-subcontractor, which in turn hired Dun-Par, making Dun-Par a subcontractor to Fortis and a sub-sub-subcontractor to BE&K. Dun-Par admitted that it did not have a direct contract with Vanum.

Dun-Par performed and, on December 9,2011, filed suit against Fortis, Vanum, and Hanover for the unpaid balance due Dun-Par under its contract with Fortis. Dun-Par obtained default judgments against both Fortis and Vanum. Dun-Par and Hanover both filed cross-motions for summary judgment on the issue of whether Hanover’s Subcontract Payment Bond covered Dun-Par’s claim for payment.

The Subcontract Payment Bond required that Vanum “promptly make payment directly or indirectly to all Claimants as defined in [349]*349this bond, for all labor, material and equipment used in performance of the Subcontract.” The terms of the bond defined “Claimant” as:

“an individual or entity having a direct contract with tire Principal to furnish labor, materials or equipment for use in the performance of the Subcontract or any individual or entity having valid, lien rights which may be asserted in the jurisdiction where the Project is located.” (Emphasis added.)

The district court granted Dun-Par summary judgment while denying Hanover’s motion.

The district court found that Dun-Par was entitled to payment under the bond as a contract beneficiary and as a “claimant” with valid “lien rights.” It initially concluded that, on its face, the bond language appeared to preclude Dun-Par from payment for two reasons: first, Dun-Par did not fall into the first category of claimants because Dun-Par did not have a direct contract with Vanum; and second, Dun-Par did not fall into the second category of claimants because federal law prohibited Dun-Par from obtaining a lien on federal property.

However, Vanum supplied a generic form for the bond with Hanover which, unlike Hanover’s usual bond agreement form, did not provide coverage for subcontracts two levels down from Vanum. The district court interpreted the word “jurisdiction” as used in the bond’s definition of a claimant as referring to die jurisdiction of Kansas, not the jurisdiction of the federal government. With that interpretation, the district court reasoned that Dun-Par would have had the right to assert a mechanic’s lien on the project under Kansas law, but federal law prohibited the remedy. Despite the lack of remedy, Dun-Par still retained the right of a mechanic’s lien under Kansas law. The district court explained that the lien laws of Kansas were designed to protect contractors who are denied justly earned compensation, which promotes fairness in the construction industry. Though Dun-Par could not issue a mechanic’s lien on the Fort Riley project, Dun-Par still had the right to a mechanic’s lien under state law; therefore, Dun-Par qualified as a claimant under the terms of the bond.

The second theory relied upon by the district court provided Dun-Par with the right to collect from Hanover because Dun-Par [350]*350was a third-party beneficiary of the contract. The district court interpreted Wichita Sheet Metal Supply, Inc. v. Dahlstrom & Ferrell Constr. Co., 246 Kan. 557, 561, 792 P.2d 1043 (1990), as holding that “[cjlaims under Kansas little Miller Act statutes must look down two levels.” Following this conclusion, the district court reasoned that if this bond had been a public works bond under K.S.A. 60-1111, then Dun-Par would be within two levels of Vanum and Hanover’s bond would cover payment to Dun-Par. The legislature’s enactment of K.S.A. 60-1111 demonstrated the State’s public policy in favor of protecting subcontractors from nonpayment through the use of bonds.

The district court found that Hanover’s risk was so limited under the terms of the bond that it appeared as an “inadvertent windfall to Hanover from the fortuitous caprices of using someone else’s supplied form.” The district court also discussed the background of the bond by concluding that there was no evidence of a meeting of the minds on the terms of the bond. “The facts of this case are an anomaly that lead, under defendant’s position to a result inconsistent with the usual bond coverage of Kansas workers and contractors.” The court concluded that the “weight of the law in this court’s opinion is that the contractor two levels down from Vanum and five levels down on the whole project is and should be covered by Hanover’s bond.”

Hanover timely appeals.

Did the District Court Err in Finding that Dun-Par Had the Right to Payment by Hanover Under the Subcontract Payment Bond?

Hanover relies upon the plain language of the bond to argue that Dun-Par clearly does not fit into either of the two categories of claimants given in the bond because Dun-Par had neither a direct contract with Vanum nor the right to impose a lien upon the property owned by the federal government. Hanover argues that the Subcontract Payment Bond is a contract and is therefore subject to the rules governing contract interpretation. See Tradesmen Int'l, Inc. v. Wal-Mart Real Estate Business Trust, 35 Kan. App. 2d 146, 163, 129 P.3d 102 (giving the ordinary meaning to clear and un[351]*351ambiguous language in a payment bond), rev. denied 281 Kan. 1382 (2006).

Dun-Par cites to two cases, Local No. 1179 v. Merchants Mutual Bonding Co., 228 Kan. 226, 229, 613 P.2d 944

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Martin v. Hanschu
738 P.2d 96 (Supreme Court of Kansas, 1987)
Wittig v. Westar Energy, Inc.
235 P.3d 535 (Court of Appeals of Kansas, 2010)
Warner v. Stover
153 P.3d 1245 (Supreme Court of Kansas, 2007)
Tradesmen International, Inc. v. Wal-Mart Real Estate Business Trust
129 P.3d 102 (Court of Appeals of Kansas, 2006)
Haynes Hardware Co. v. Western Casualty & Surety Co.
133 P.2d 574 (Supreme Court of Kansas, 1943)
In re the Conservatorship of Huerta
41 P.3d 814 (Supreme Court of Kansas, 2002)
Law v. Law Co. Building Associates
289 P.3d 1066 (Supreme Court of Kansas, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
310 P.3d 1072, 49 Kan. App. 2d 347, 2013 WL 4499124, 2013 Kan. App. LEXIS 75, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dun-par-engineered-form-co-v-vanum-construction-co-kanctapp-2013.