Duluth-Superior Dredging Co. v. United States

81 Ct. Cl. 912, 1935 U.S. Ct. Cl. LEXIS 195, 1935 WL 2273
CourtUnited States Court of Claims
DecidedNovember 4, 1935
DocketNo. 42465
StatusPublished

This text of 81 Ct. Cl. 912 (Duluth-Superior Dredging Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Duluth-Superior Dredging Co. v. United States, 81 Ct. Cl. 912, 1935 U.S. Ct. Cl. LEXIS 195, 1935 WL 2273 (cc 1935).

Opinion

Booth, Chief Justice,

delivered the opinion of the court:

On March 29, 1926, a written contract was executed by the Duluth-Superior Dredging Company, plaintiff, and Lieut. Col. E. J. Dent, Corps of Engineers of the Army, representing the United States. The work to be performed under the contract was the dredging of Maumee Bay and River channels, Ohio.

The case involves a single isstie. The plaintiff excavated 2,383,374 cubic yards of material and was paid for excavating 2,245,822 cubic yards, leaving, as is claimed in this suit; a balance due it of $28,885.92; i. e., for excavating 137,552 cubic yards of material at the contract price of twenty-one .cents per cubic yard, which was not paid.

The defendant rests the defense on certain provisions of the contract, insisting that the method of ascertaining cubic yards of material excavated by the plaintiff limits payments t herefor to the sum ]3aid the plaintiff, and recovery for the [917]*917sum is precluded, it not being disputed that the plaintiff did actually excavate 2,383,374 cubic yards .of material, and that the 137,552 cubic yards for which no payment was made were “shoalings” which occurred in the .areas involved subsequent to .the completion of excavation •therein.

Paragraph 34 of the specifications vested in the contracting officer plenary authority to' direct the conduct of the work, and paragraph 19 of the same document detailed the -work to be done and the manner of doing it. The channel •to be dredged was about 30,000 feet in length, the depth to be obtained was- “21 feet below low-water datum (elevation .570.8 feet) in those portions where a less depth than twenty-one feet exists, and shall have a total bottom width of 400 ■feet.” The channel was divided into four distinct sections, .and the plaintiff was required by the contracting officer to dredge the south one-lialf of the width of the channel of sections 1 and 2 and the greater portion of section 3 before beginning to dredge the north half of said area.

The plaintiff in the year 1926 completed performance of its contract work in accord with the specifications and did dredge the south half of sections 1 and 2 and a portion of section 3, and was engaged in dredging the north half of section 1 when on or about December 4, 1926, winter weather and ice conditions caused a cessation of work. In 1926, as dredging work under the contract proceeded, contract officials made soundings or sweepings immediately before dredging operations commenced, and followed this up by a similar procedure when the excavation in the areas was completed, and, upon the data thus obtained, monthly estimates of the yardage of excavation shown therein disclosed that plaintiff had met the exact requirements of the contract ■ ;as to depth and width, and that none of the dredging “so shown fell outside the limits provided in the sepecifications.”

In July 1927 the. contracting officials made final soundings and sweepings of section 1 of the work area, and by making a comparison of the data thus obtained with the data of. the soundings and sweepings obtained coincident with the performance of the work in 1926, it was discovered that [918]*918sboalings to the extent of 88,764 cubic yards bad taken place in said section, and by employing a similar procedure in August 1927, shoaling to the extent of 48,788 cubic yards was disclosed to have occurred in that qiortion of section 2 which plaintiff had dredged in 1926.

The plaintiff was not required' to remove any poi’tion of' the shoalings from the areas dredged. The defendant tendered it, in final settlement for the work done, a payment, predicated upon a measurement of the area dredged, as stated above, taken before the work commenced, and the cubic contents of the same area when the work was completed, thereby deducting from the actual amount of material dredged by the plaintiff the quantity of material which found its way into the dredged area, i. e., shoaling, long after the plaintiff had completed its work therein.

The defendant justifies the reduced sum paid the plaintiff for the quantity of material actually dredged, by a construction of certain paragraphs of the contract and specifications to which we refer later. It is first essential to set out the provisions of the contract and specifications which we think stipulate the sum to be paid the contractor for performance of the contract work in accord with the provisions of the same. It is not disputed that under article 1 the contractor was to “receive payment at the rate o? twenty-one (21) cents per cubic yard, place measurement.”'

Paragraph 30', entitled “Method of measurement”, is as follows:

“The material will be measured by the cubic yard in place by means of soundings or sweepings taken before and after-dredging. The maps already prepared (par. 21) are believed to represent approximately the existing condition; but they will be replaced by other maps showing soundings taken shortly before dredging is begun in any locality. Soundings or sweeping will be made behind the dredge as the work progresses, and so far as practicable, the contractor will be advised of the result before anchors are shifted. Monthly deductions for excessive overdepth or side-slope dredging (par. 26) and monthly payments for approximate net results will be based upon these surveys.”-

Paragraph 17, entitled “Payments”, is as follows:

“Payments will be made monthly on estimates of such, material as has been excavated and deposited in accordance [919]*919with the specifications and not included in any prior estimate, except that 10 percent of the amount of each estimate will be retained until the work is 50 percent completed; and thereafter with each monthly payment there will be-paid such portion of the amount so retained as is in excess of 10 percent of the estimated cost of completing the work, remaining to be done, until the amount retained is reduced to $10,000, after which it will remain unchanged until the full completion of the work.”

The character of the work involved necessitated the paragraphs quoted. Soundings and sweepings depicted the quantity of material dredged, and the additional fact as to-whether the dredging operations coincided with the area specified to be dredged for which the contractor was only to be paid. The language of paragraph 30 obligates the defendant, unless some other provision of the contract precludes it, to pay the contractor at the contract rate for allí material actually excavated within the limits of the contract area. That payments were to be made in accord therewith is obvious from paragraph 17. They were to be made monthly “on estimates of such material as has been excavated and deposited in accordance with the specifications” less certain retained percentages.

The defendant insists that paragraph 31 of the specifications provides expressly for a method of measurement and therefore a basis of payment which limits the quantity of' dredged material to be paid for to measurements taken before dredging operations and those taken when the contract work was completed, a contention which in effect nullifies paragraph 30 and places upon the contractor the-assumption of all risks which may through no fault of it materially reduce the quantity of material admittedly-dredged in compliance with the contract and specifications, and for which estimates had been made, approved, and payments made therefor under paragraph 17.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
81 Ct. Cl. 912, 1935 U.S. Ct. Cl. LEXIS 195, 1935 WL 2273, Counsel Stack Legal Research, https://law.counselstack.com/opinion/duluth-superior-dredging-co-v-united-states-cc-1935.