SHELBY, Circuit Judge.

L. C. Dulaney, the appellant, made a written contract with an officer representing the United States, binding himself to construct certain levees. He agreed to furnish the labor and material, and to complete them in a manner satisfactory to the government. Dulaney was insolvent, and unable to carry out Ms agreement without assistance. On the 31st of March, 1894, to get the money and supplies to do the work, he made a contract with Scudder & Co. This contract is in writing, and by its terms Dulaney was to repay Scudder & Co. for the advances made to him, out of money he was to receive from the government for the work on the levees. With the contract:, Dulaney executed a power of attorney to Scudder & Co. authorizing them to collect and receipt for all money to become due on Dulaney’s, contract with the government. The agreement referred to the power of attorney executed at the same time in these words: ‘Tn case the power of attorney executed by the said Dulaney shall not be satisfactory to the United States authorities, he agrees to execute such oilier or others as may be necessary to conform to the requirements of said authorities.” The poiver of attorney was submitted to the government, and accepted as satisfactory, after requiring a change in the acknowledgment. The estimates, when due, while Dulaney liad charge of the work, were paid to Scudder & Co. under this contract and power of attorney. In May, 1895, it became known to Scudder & Co. that Dulaney had failed to comply with the terms of his contract with the government, and that the government was about to annul the contract. Scudder & Co. had already made large advances to Dulaney. To avoid the loss of advances already made, Scudder & Co., on the 27th day of May, 1895, made another agreement with Dulaney. By this agreement Dulaney transferred’ certain personal property to Scudder & Co., and also assigned to them “all his rights and interest” in the contract which he had made with the government; Scudder & Co. agreeing to finish the work which Dulaney had, in the first instance, agreed to do. Scudder & Co. proceeded to finish the work, taking entire charge of it. As the work progressed, payments were made to them upon estimates made pursuant to the original contract between Dulaney and the gov[8]*8ernment. When the work was finished, it was accepted by the government, and the estimate for the final payment was made; but, before it could be paid to Scudder & Co., Dulaney gave the government written notice that he had revoked his power of attorney, and objected to this final payment being made to Scudder & Co. The amount then due from the government on the work was about $7,715, and Dulaney was, on account of these transactions, indebted to Scudder & Co. in a much larger sum. Dulaney continues insolvent, and the substantial subject of this litigation is the right to the money due for the work, and now held by the government. On the 27th of May, 1896,'Scudder & Co. filed their bill in chancery against Dulaney, alleging the facts that we have briefly stated, and praying for general relief, and specially that Dulaney be perpetually enjoined from collecting or receiving the money due for this work. The circuit court overruled a demurrer to the bill, and on the final hearing enjoined Dulaney as prayed for; and also rendered a decree against Dulaney for the amount found to be due Scudder & Co. The cause is brought here by appeal, and it is urged that there is no equity in the bill, that the United States was a necessary party to the suit, and that sections 3477 and 3737 of the Revised Statutes of the United States make the dealings between the parties illegal, and that, therefore, the contracts between Dulaney and Scudder & Go. are against public policy, and void.

1. It is not necessary to examine the questions whether the bill contains equity as a bill for an accounting or as one to1 prevent a'multiplicity of suits. Scudder & Co. had earned, and are certainly the equitable owners of, the fund in controversy, which is withheld by the government. The contract under which the work was done was originally with Dulaney. He is now claiming the fund, and has given notice to the government of the revocation of the power of attorney under which it was to have been paid to Scudder & Co. Dulaney is insolvent. Unless the government is bound by its dealings with Scudder & Co., — a question not necessary to be decided,— it has the right to either recognize or reject the power of attorney of Dulaney and his contract with Scudder & Co. If Dulaney should receive the money, Scudder & Co. would be without remedy. The jurisdiction of equity for the protection of contract rights is not limited to the original parties to the agreement, but is often exercised in favor of their assignees. Under the circumstances of this case, the necessity of protecting the assignee by the writ of injunction is sufficient of itself to give equity jurisdiction. 2 High, Inj. (3d Ed.) § 1113. In Milnor v. Metz, 16 Pet. 221, the fund in controversy was in the treasury. The secretary refused to recognize the claim of either party, and waited for the conflicting claims to be' adjusted by the courts. Metz filed his bill enjoining Milnor from receiving the money, and had a decree of perpetual injunction, which was affirmed by the supreme court.- The case of Phelps v. McDonald, 99 U. S. 298-307, was a con-, test in equity as to the ownership of money which was not within the jurisdiction of the court. The court said, “Whether the money be here or abroad, the assignee is entitled to have the question finally Settled whether he or McDonald has the better right.” The allegations of the bill make a case within the jurisdiction of equity to enjoin [9]*9Dulaney, and to settle, as between the parties, which has the better right to the fund in controversy.

2. In this suit it was not necessary that the United States be made a party defendant. The United States cannot be sued except by their consent. The position could not be sustained that the complainants would be deprived of their equitable remedy by injunction against Dulaney, because the United States did not consent to be sued. In the case of Milnor v. Metz, supra, the United States was not made a party defendant; and in Phelps v. McDonald, supra, the court granted relief by a decree in personam, although the property involved was not in its territorial jurisdiction. The purpose of this suit was to settle the controversy between the parties to it, and the decree rendered is not binding on the United States, but would protect the government in disregarding the notice of Dulaney that he had revoked the ¡lower of attorney given to Scudder & Co.

3. There5 are two sections of the Revised Statutes that bear upon the defense's made, and they should be examined together. Section 3477 is as follows:

“All transfers and assignments made of any claim upon the United States, or of any part or share thereof, or interest therein, whether absolute or conditional, and whatever may be the consideration therefor, and all powers of attorney, orders, or other authorities for receiving payment of any such claim, or of any part or share thereof, shall be absolutely null and void, unless they are freely made and executed In the presence of at. least two attesting witnesses. after ihe allowance of such a claim, the ascertainment of the amount due and the issuing of a warrant for the payment thereof. * * *”

This sod ion, it will be observed, relates to the transfers of auy “claim” against the United States.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Frost v. County of San Diego
S.D. California, 2022
Jaekel v. Aytu BioScience, Inc.
N.D. California, 2022
American Dock Co. v. City of New York
174 Misc. 813 (New York Supreme Court, 1940)
Mullen & Junkin v. Byrd & Clopton
122 So. 485 (Mississippi Supreme Court, 1929)
Behre v. Anchor Ins.
297 F. 986 (Second Circuit, 1924)
United States v. A. Bentley & Sons Co.
293 F. 229 (S.D. Ohio, 1923)
Hegness v. Chilberg
224 F. 28 (Ninth Circuit, 1915)
Chidberg v. Hegness
5 Alaska 168 (D. Alaska, 1914)
Lewis Pub. Co. v. Wyman
182 F. 13 (Eighth Circuit, 1910)
Scott v. United States Fidelity & Guaranty Co.
169 F. 211 (U.S. Circuit Court for the District of Oregon, 1909)

Cite This Page — Counsel Stack

Bluebook (online)
94 F. 6, 36 C.C.A. 52, 1899 U.S. App. LEXIS 2323, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dulaney-v-scudder-ca5-1899.