Dugas v. Pelican Construction Co.

481 F.2d 773, 1973 A.M.C. 1652
CourtCourt of Appeals for the Fifth Circuit
DecidedJune 11, 1973
DocketNo. 72-2546
StatusPublished
Cited by21 cases

This text of 481 F.2d 773 (Dugas v. Pelican Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dugas v. Pelican Construction Co., 481 F.2d 773, 1973 A.M.C. 1652 (5th Cir. 1973).

Opinion

AINSWORTH, Circuit Judge:

Lloyd Dugas, a roustabout employed by Pelican Construction Company, Inc., brought this suit for damages growing out of personal injury sustained aboard a submersible drilling barge, ROWAN NO. 1, owned by Rowan Drilling Company and located on navigable waters at Northeast Patterson Prospect Field, south of Morgan City, St. Martin Parish, Louisiana.

Union Oil Company of California had contracted with Rowan for the drilling of an oil and gas well at that location. The contract provided that Rowan furnish a drilling rig and barge and the necessary personnel to operate them. Union was required under the contract to furnish a tugboat and service barge to be used in connection with the operation. Contract depth was specified to be 13,500 feet, for which Rowan was to be paid a fixed rate per linear foot. Rowan was to provide the drilling pipe up to the contract depth. Beyond 13,500 feet the operations were to be conducted on a day-work basis agreement under which Union would furnish the drilling pipe to Rowan.

In addition to the contract with Rowan, Union had a service contract with Pelican for the furnishing of labor crews as requested by Union.

On September 8, 1964, Rowan was in the process of drilling the well for Union and was operating on day rate, having exceeded the contract depth. Kenneth Ditch, the foreman for Union and its only representative on the drilling barge, called Pelican’s office and requested that a crew of roustabouts be sent out to work aboard the drilling barge. Accordingly, a Pelican crew of two pushers, Edward George and Oris Cormier, and four roustabouts, including plaintiff Dugas, left Morgan City, Louisiana, by crewboat and proceeded to the drilling barge, where they arrived at approximately 10 a. m. George was informed by Ditch that the Pelican crew was to unload drilling pipe from a pipe barge onto the drilling barge. The pipe barge, owned by Union and loaded with 4j4-ineh drill pipe provided by Union, was lying alongside the drilling barge, unmanned. The drilling barge was equipped with a crane and air hoist for use in moving pipe from the pipe barge to the pipe rack aboard the ROWAN NO. 1, and thence to the V-door at the drilling floor when needed by Rowan to run the pipe into the well hole.

Upon arrival at the drilling site, the Pelican crew were assigned various jobs preparatory to unloading the pipe. Sometime in the afternoon the unloading operation began, with George, an experienced air hoist operator, operating the hoist and crane. At 7 p. m. Rowan be-gain putting the pipe into the hole.

The accident which precipitated this suit occurred at about 4:30 a. m., the following day. Dugas was then working at the far end of the pipe rack on the drilling barge. He and a Pelican co-worker had just attached a sling to a load of six joints of pipe. George then lifted the pipe but the load instead of moving to the V-door, swung back and hit Dugas, who had turned and was walking in the opposite direction, knocking him to the floor of the rig. When observing Dugas fall, George placed the hoist in neutral, left the controls and ran to a point on the upper deck where he could see Dugas, at which time the air hoist “bled off” allowing the load of pipe to settle on Dugas’ legs.

Dugas claimed damages from Pelican,1 his employer, Union and Rowan, asserting liability under the Jones Act, the general maritime law and maritime tort. His theory for Jones Act liability against Union and Rowan was based on the theory that he was the borrowed servant of these defendants.

[776]*776Thereafter a progression of cross-claims between defendants followed, with the parties asserting every known theory of maritime indemnity — tort, contractual (express and implied) and third-party beneficiaries to rights of others under contracts. Virtually everyone claimed over against virtually everyone else.2 As a result of these numerous claims and long, protracted pretrial procedures, including the taking of depositions, interrogatories and the utilization of other discovery devices, the case did not proceed to trial until almost five years after the initial complaint was filed and approximately six years following the accident, a period much longer than the memory span of most of the testifying witnesses. Consequently, the evidence was in many instances sketchy or conflicting. Nevertheless, the district judge, sitting without a jury found that the sole proximate cause of the injury was the negligence of Union in allowing the Pelican crew to become fatigued and overworked on an undermanned vessel which thus became unseaworthy. In this regard the district judge made the following pertinent findings:

“All of the Pelican crew testified that they were very tired. Cormier requested relief at ten o’clock p. m. and again at about two o’clock a. m. Mr. Ditch, the Union superintendent, and the man in charge, had retired for the night. None of the Rowan men had authority to order a relief crew to come out. Mr. Bevills, Rowan’s tool-pusher, stated that no one requested relief of him that he can remember; but if they had, he would have taken the matter up with Mr. Ditch. Under these circumstances, Union’s failure to exercise reasonable care for the safety of the men furnished to it by Pelican was negligence, and its failure to provide a sufficient number of men to do the work that had to be done resulted in an unseaworthy, undermanned ship, which rendered the vessel itself not reasonably fit for her intended use and dangerous to the well being of those aboard her. . . .We find that the inattention of George in allowing the load to swing toward Du-gas, as well as the fact that Dugas has turned his back to the load and failed to watch it, as he should have, were the result of their fatigue, a condition that could and should have been foreseen by Union. No effort was made to allow these men to even have a few minutes rest after they began running pipe, or to provide them with food although there was food available. They came aboard, went about their appointed tasks as directed by Mr. Ditch and were thereafter completely neglected. We hold that this failure on the part of Union and the resulting unseaworthiness of the ship was the sole proximate cause of the accident.”

The district court further found that the dereliction of George and Dugas, if any, was caused by fatigue due to the unrelieved long hours and sustained heavy labor, and did not under the circumstances constitute negligence on their part which was a contributing cause of the accident. The district court concluded that Dugas was a Jones Act seaman of Union under the borrowed servant theory. Damages were assessed in the sum of $45,000 against Union and Rowan as joint tort-feasors — Union, because of its negligence, and Rowan, because of the unseaworthiness of the ROWAN no. 1 caused by Union’s negligence. Judgment was also rendered in favor of Union on its cross-claim against Rowan for contribution in the sum of $22,500. Judgment was then rendered in favor of Union on its cross-claim against Pelican for one half the amount of the award, under the terms of the contract between the parties, which the district court construed as requiring indemnification for injuries to Pelican’s employees regardless of causal negligence by Union. All [777]*777of the other cross-claims and a counterclaim by Pelican against Market Insurance Company, its public liability insurance carrier, were denied. In short', Rowan and Pelican were each liable for one half the amount of judgment, or $22,500 each, under the district court’s decree.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Robertson v. W & T OFFSHORE, INC.
712 F. Supp. 2d 515 (W.D. Louisiana, 2010)
Carmichael v. Kellogg, Brown & Root Services, Inc.
572 F.3d 1271 (Eleventh Circuit, 2009)
Kidder v. Miller-Davis Co.
564 N.W.2d 872 (Michigan Supreme Court, 1997)
Brown v. Union Oil Company Of California
984 F.2d 674 (Fifth Circuit, 1993)
Brown v. Union Oil Co. of California
984 F.2d 674 (Fifth Circuit, 1993)
Thornton v. PAKTANK FLA., INC.
409 So. 2d 31 (District Court of Appeal of Florida, 1981)
Gaudet v. Exxon Corp.
562 F.2d 351 (Fifth Circuit, 1977)
City of Plantation v. Roberts
342 So. 2d 69 (Supreme Court of Florida, 1976)
Burgess v. M/V Tamano
373 F. Supp. 839 (D. Maine, 1974)
Lloyd Dugas v. Pelican Construction Company, Inc.
481 F.2d 773 (Third Circuit, 1973)

Cite This Page — Counsel Stack

Bluebook (online)
481 F.2d 773, 1973 A.M.C. 1652, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dugas-v-pelican-construction-co-ca5-1973.