Duesenberg Motors Corp. v. United States

260 U.S. 115, 43 S. Ct. 19, 67 L. Ed. 162, 1922 U.S. LEXIS 2347, 58 Ct. Cl. 699
CourtSupreme Court of the United States
DecidedNovember 13, 1922
Docket80
StatusPublished
Cited by6 cases

This text of 260 U.S. 115 (Duesenberg Motors Corp. v. United States) is published on Counsel Stack Legal Research, covering Supreme Court of the United States primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Duesenberg Motors Corp. v. United States, 260 U.S. 115, 43 S. Ct. 19, 67 L. Ed. 162, 1922 U.S. LEXIS 2347, 58 Ct. Cl. 699 (1922).

Opinion

Mr. Justice McKenna

delivered the opinion of the Court.

Action in the Court of Claims against the United States for expenses in endeavoring to perform certain contracts with the' United States made during the war with Germany, or for anticipated profits.

The contracts were for aeronautical equipment for war purposes. There were a first and primary contract and seven other contracts called supplemental agreements. The latter contained modifications of the first or primary contract, and each agreement contained modifications of those which preceded.

The first or primary contract, dated November 20, 1917, provided for 500 United States standard twelve-cylinder engines, sometimes referred to as Liberty engines. By an agreement dated December 11, 1917, the number was increased to 1,000. By another agreement dated January 4, 1918, the type of motor was changed and a motor called "the Bugatti motor was substituted; and thelre were other agreements.

From this general statement it will be seen that the contract and agreements are determining elements in the claims sued upon. A full recital of them, however, would extend this opinion to an embarrassing length. Wé shall confine ourselves, therefore, to those which we regard of determining pertinence;

*120 Upon demurrer of the United States, the Court of Claims decided the contractor entitled to no relief and dismissed its petition. This action is contested; and it is earnestly insisted that the contracts made time their essence and required speed and dispatch from the contractor, and demanded in their performance precedence upon all other work, involving necessarily, sacrifice and expense up.on the part of the contractor. And time, it is contended, being of the essence of the contracts, this necessarily. implied that the United States must have done everything to permit the contractor to comply with its obligations. The Government, however, was delinquent; and it- is alleged that “ the drawings and specifications referred to in the contract (Exhibit A) as being attached thereto (but which were not in fact so attached) were furnished piece-meal from time to time but not so as to enable the claimant to enter into quantity production; and the only work which was practicable under said contract was in making extensive alterations in the plant of claimant company to adapt it to the uses of the Government for the purpose of carrying out the contract (Exhibit A), to assemble a competent engineering staff, and to make other-preparations for the performance of said contract, all of which the claimant did at great expense.”

And further delinquency is charged in not performing the agreement which substituted the Bugatti motors,-and Article I of the agreement is quoted as follows:

“ That, subject to all the provisions of-Article I in said contract No. 2318 contained, the Contractor shall make for the Government, instead of the articlés described in Article I of said contract, two thousand (2,000) Bugatti motors, and such spare parts for said motors as the Government may order from time to time during the period of the construction of said motors,- in accordance with specifications to follow.”

The -specifications were not turnished, it is said,; until September 25, 19X8; and that the delay was a breach-of *121 the contract; and the contractor is entitled to recover for the losses caused thereby.

To this the Court Of Claims answered that the contract contemplated a revision of' the schedule (times of delivery) ’ in regard to the engines.. The provision to which that purpose was attributed is, that in view of the present uncertain factors inherent in the articles, and in the establishment of the industry of producing them, it is understood that this schedule may require revision, . . The schedule designated June, 1918, as the month of . complete production.

Changes were provided for in another article, and by still another it was provided that if in the opinion of- the Chief Signal Officer of the United States the public interests so required, the Government might, upon thirty days’ notice, terminate the contract. And there was provision for settlement of disputes.

Dates are important to <be considered. The supplemental contract in which Article I appears, and' which adopts Article I of the first contract, is dated January 4, 1918. Another agreement which was supplementary to that agreement was dated January 15, 1918, and still another dated February 11, 1918.

In none of these agreements, continuing as they did the .obligations of the parties to them and the means of their performance, is there a word of complaint that the Government had been or was delinquent on account of not furnishing specifications or in any way. In the agreement of February 11, 1918, in Article II, it is provided that:

“ In the interest of both parties hereto and in order to expedite -the delivery of the said supplies, the Government will advance to the contractor under the Principal Agreement the sum of Four Hundred Thousand Dollars ($400,000) on the terms and security hereinafter mentioned, and will make payment directly to the contractor by check dated February 25, 1918.”

*122 There was another agreement, dated February 14, 1918, which continued in effect, except as modified, all that preceded. There was no protest or complaint of any kind, ho accusation of default or delay on the part of the Government.

There was a seventh agreement, made September 26, 1918, and another, made October 23, 1918, for advance payments to the contractor.

- The agreéments are of significant strength. Their legal effect and that of the contract cannot be determined by any one provision but the totality of them must be regarded and their relations and purposes.

A war of magnitude was waging. The Government was eager for efficient instrumentalities and the contractor was enticed by the sprofit of their manufacture. The matters were urgent, but they were beset with contingencies. The Government .could terminate the contract in the interest of the public, welfare; and the war might cease.' The latter did happen. However, before it happened and, before, it may be, there were signs of its happening, there were dealings and adjustments of preparation between the Government and the contractor. They took care of, and were intended to take care of, changing purposes, and no dissatisfaction was expressed. One of the changes was, as we have said, from the construction of 500 Liberty motors to 1,000, the completion and delivery of which was to be in June, 1918, and, as we have said, another change was the substitution of 2,000 Bugatti motors for the Liberty engines, and for such, spare parts as the Government might order from time to time; the motors to be delivered by September, 1918. By the supplemental-agreements which provided for those changes, it was also provided that their cost was to be paid by the Government, and the profit of the contractor was changed from $625 for each article to $750, and the Government agreed to advance the contractor $1,250,000, to be repaid with' interest at 6%.

*123

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ingram-Day Lumber Co. v. McLouth
275 U.S. 471 (Supreme Court, 1928)
Peterson v. Farmers' Grain & Milling Co.
255 P. 436 (Utah Supreme Court, 1927)
Ingram-Day Lumber Co. v. McLouth
13 F.2d 581 (Sixth Circuit, 1926)
Twin City Forge & Foundry Co. v. United States
60 Ct. Cl. 673 (Court of Claims, 1925)

Cite This Page — Counsel Stack

Bluebook (online)
260 U.S. 115, 43 S. Ct. 19, 67 L. Ed. 162, 1922 U.S. LEXIS 2347, 58 Ct. Cl. 699, Counsel Stack Legal Research, https://law.counselstack.com/opinion/duesenberg-motors-corp-v-united-states-scotus-1922.