Dudley v. Born

710 S.W.2d 638, 1986 Tex. App. LEXIS 7690
CourtCourt of Appeals of Texas
DecidedApril 10, 1986
DocketNo. 09-84-382 CV
StatusPublished
Cited by4 cases

This text of 710 S.W.2d 638 (Dudley v. Born) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dudley v. Born, 710 S.W.2d 638, 1986 Tex. App. LEXIS 7690 (Tex. Ct. App. 1986).

Opinion

OPINION

BROOKSHIRE, Justice.

Appeal from a suit for damages, alleging breach of a Construction Loan Agreement. The agreement was secured by a Promissory Note and Deed of Trust. The judgment below, after a bench trial, was awarded to Donald Born and wife, Celia Born, for damages, attorney’s fees and costs. Findings of Fact and Conclusions of Law were filed. At the bench trial, the court held that Dudley had breached the Construction Loan Agreement by an anticipatory breach by suggesting to the Borns to seek other sources of the final funding; secondly, by charging the Borns more interest than was agreed to under the governing instruments; and, thirdly, by refusing to fund the balance of the last one or two “Requests for Advance” under the loan agreement.

Obviously, the paramount issue in the case sub judice, and especially under the Construction Loan Agreement, was which party breached the agreement. Dudley contended the Borns breached the loan agreement. At the threshold, it should be pointed out that the Construction Loan Agreement contained certain “terms and conditions”. Both parties, during the negotiations leading to the loan agreement, were represented at all times by able, experienced attorneys. Both parties were represented and advised by their respective attorneys at the actual time of the signing of the documents. The documents were explained by the attorneys, in detail, to the parties. The final closing took place in the office of the attorneys for the Boms.

The construction was the building and completion of an airplane hangar, office building, and other improvements located at the Beaumont Municipal Airport. The Appellees had determined that they would need $175,000. to properly construct and complete all of the construction and improvements on the project. Therefore, the loan was so structured that Dudley would lend to the Borns a total of $175,000. This sum was to be advanced as the work progressed upon certain “Requests for Advance” as agreed to by the parties. The agreement called for a specific form of “Request for Advance” which provided for certain important recitations, certificates and representations of facts concerning completed work and owed bills.

Since the Construction Loan Agreement was definitely a contract of commitment to advance monies on certain “terms and conditions”, the agreement had to be strictly complied with by the “Borrowers” in order to enforce their right of advances from the “Lender”. Hohenberg Bros. Co. v. George E. Gibbons & Co., 537 S.W.2d 1 (Tex.1976); Republic of Texas Sav. v. Island Recreational, 680 S.W.2d 588 (Tex.App.—Beaumont 1984), affirmed, 28 Tex.Sup.Ct.J. 534 (July 3, 1985) (Motion for Rehearing pending).

The “Requests for Advance” were to include specific wording and were to list the sub-contractors, materialmen and other suppliers who had done work on the project. The “Requests” specified the degree of completion for each of these claimants’ work. The “advances” were to be used to pay the bills listed. It was unequivocally set forth as a “condition” that the completion date for the total, one hundred percent completion, of all improvements was to have been July 10,1981. The project was not completed by that date; nevertheless, Dudley did grant extensions of time to complete the improvements. The extensions of time did not change or reduce the force or efficaciousness of the other “terms and conditions” of the Construction Loan Agreement.

After the original deadline of July, 1981, on October 1,1981, the attorney for Dudley wrote a letter to the Boms, with a copy to [640]*640their attorney of record, or vice versa, stating the final construction completion deadline to be November 1, 1981. This same letter specified a number of important major items of construction still to be completed by Appellees. On October 1, 1981, about 3 months after the original completion date, the construction was only about eighty-five or ninety percent completed.

Later on, there was an attempt to complete parts of the improvements, including work on the hangar, work on the office building, and a taxiway. Then on November 9 and November 13, 1981, there were two separate “Requests for Advances” made, both of these “Requests for Advances” were numbered “No. 9”. The first “Request for Advance No. 9” was for $44,-111.48, being the total amount of the balance of the unfunded monies. However, on November 13, the Borns resubmitted a second “Request for Advance No. 9” in the reduced amount of $26,021.79.

THE COST OVERRUNS

It is glaringly clear in the record that there were large cost overruns. The amounts of these overruns, at different times, varied but they exceeded $12,000. Indeed, when the final disbursement on the construction project was made, on March 8, 1982, it was shown that a considerably larger sum than $12,000. was due, owing, and payable to various subcontractors, ma-terialmen and other claimants who were in a position to assert lien claims against the improvements at the Municipal Airport. The larger, disbursed sum was $67,413.57.

Dudley’s letter of October 1, 1981, required and demanded that the Borns deposit with Dudley such amounts of money as would be reasonably necessary for the payment of all of the outstanding bills and cost overruns. This demand undoubtedly was wise and reasonable; it was a “condition” of the loan agreement. At the final closing of this matter in March of 1982, the Neches Title Company showed outstanding mechanics’ and materialmen’s claims, in re the Boms’ construction project at Municipal Airport, to be in the total sum of $67,-413.57, which the title company, in accordance with the Borrowers’ (the Borns’) statement, actually disbursed. These are listed as follows:

[[Image here]]

The letter of November 13, 1981, is clear and unequivocal, stating:

“... Marvin Dudley will make several requirements relating to full payments of all bills for labor and materials.”

The requirement was a demand made by the Lender. A second time in the letter, a demand was made by the Lender. The letter, in a separate paragraph, read:

“Secondly, we will require that Mr. Bom deposit with Mr. Dudley the additional funds necessary to pay for all labor and material in connection with the construction, whether invoiced or not. As you know, there were some $35,-000.00 worth of other bills which were presented with the first request no. 9....” (Emphasis added)

We determine that the record conclusively shows that the $35,000.00 was a conservative figure in view of the $67,413.57 paid out at closing for mechanics’ and material-men’s claims by the Neches Title Company. The $67,413.57 was on the Borns’ settlement statement and agreed to by them.

The Construction Loan Agreement specifically provided for the right of Dudley to make this requirement. It was a “term and condition”.

Paragraph 10 of the loan agreement reads, in relevant part:

“10. Borrower’s Representations and Warranties.
“(a) Borrower shall pay to Lender, on demand, and whether or not any funds [641]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
710 S.W.2d 638, 1986 Tex. App. LEXIS 7690, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dudley-v-born-texapp-1986.