DSME Construction Co., Ltd.

Armed Services Board of Contract Appeals·Decided April 17, 2026·No. 63878·Published

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of - )

)

DSME Construction Co., Ltd. ) ASBCA No. 63878 )

Under Contract No. W91QVN-23-D-0038 )

APPEARANCE FOR THE APPELLANT: Yong Eui Song, Esq.

Central IP & Law Seoul, Korea

APPEARANCES FOR THE GOVERNMENT: Dana J. Chase, Esq.

Army Chief Trial Attorney LTC Bruce A. Nessler, JA CPT Natalie W. McKiernan, JA MAJ Katharine M. Calderon, JA Trial Attorneys

OPINION BY ADMINISTRATIVE JUDGE MCILMAIL

The parties contracted for appellant, DSME Construction Co., Ltd., to provide maintenance and repair services at Camp Humphries and Camp Yongin, in the Republic of Korea. The contracting officer terminated the contract for default. A month later, rather than appealing to this Board from the termination for default, DSME presented to the contracting officer a claim for (1) conversion of the termination to one for the convenience of the government, and (2) payment of approximately $2 million, including an amount for work performed prior to the termination. Ninety-seven days after the termination of the contract for default, the contracting officer denied DSME’s claim for conversion and money. DSME appeals from that decision. Among the government’s positions is its affirmative defense that the contract is void ab initio, for fraud and material misrepresentation. 1 The parties elected to proceed without a live hearing, pursuant to Board Rule 11. 2

1 Amend. ans. at 102-03.

2 We have not considered DSME’s surreply in arriving at this opinion, as a sanction in response to the preparation of that brief. DSME Constr. Co., Ltd., ASBCA No. 63878, 26-1 BCA ¶ 39,026 at 190,053.

FINDINGS OF FACT

The parties entered the contract on April 13, 2023, for DSME to “[p]rovide preventive maintenance in the critical facilities and dining facilities at Camp Humphreys and Camp Yongin [in accordance with the Performance Work Statement (PWS)], for 3,358,244,779 South Korean Won (KRW) ($2,270,495.86),” 3 through a base period ending December 31, 2023. 4 The contract incorporates by reference Federal Acquisition Regulation (FAR) 52.212-4, Contract Terms and Conditions - Commercial Products and Commercial Services (NOV 2021), which provides at paragraph (m), Termination for cause:

The Government may terminate this contract, or any part hereof, for cause in the event of any default by the Contractor, or if the Contractor fails to comply with any contract terms and conditions . . . . 5

FAR 52.212-4 further provides, at paragraph (f), Excusable delays:

The Contractor shall be liable for default unless nonperformance is caused by an occurrence beyond the reasonable control of the Contractor and without its fault or negligence . . . .

According to ¶¶ 1.0 and 1.1 of the PWS, the government needed an “enhanced maintenance program in the specific areas of heating, ventilating, and air-conditioning (HVAC) system, electrical systems, and built-in food service equipment of [] selected buildings,” and the contractor was to “provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and nonpersonal services necessary to provide maintenance and repair services for thirty-three (33) critical facilities” at the two camps. 6 The government says that the contract’s “full performance period” began on July 1, 2023; 7 DSME says that “contract commencement” began on July 3, 2023. 8

The PWS provides, in ¶ 9.2.2, Cooling Towers, that “[d]ue to absence of necessary water treatment system of the supply water flowing into the cooling towers, the Contractor shall . . . remove sludge on . . . inside/outside of the cooling towers

3 As of April 16, 2026. 4 See R4, tab 1 at 1-3 (alteration added). 5 R4, tab 1 at 23 (emphasis added). 6 R4, tab 1a at 1-2. 7 Gov’t br. at 2. 8 App. br. at 5.

every other week or more frequently.” 9 Ultimately, DSME was responsible for removing sludge at that rate from 29 cooling towers. 10 However, DSME performed sludge removal only three times: once each from only three cooling towers. 11

On May 8, 2023, the parties modified the contract to require that DSME inventory all equipment and submit an inventory report to the government no later than 70 days (from an original 85 days) “once Phase-In is started.” 12 We find that the phase-in period started on April 13, 2023, when the contract was awarded, and ended 70 days later, on June 22, 2023. 13 On August 8, 2023, the government issued a stop work order, effective August 9, 2023. 14 DSME did not provide a complete inventory until August 31, 2023. 15

On October 17, 2023, the contracting officer terminated the contract for default. 16 Among the reasons that the contracting officer identified for the termination of the contract are that DSME had not timely provided an accurate inventory list, and had not adequately removed sludge from cooling towers. 17

On November 16, 2023, DSME submitted to the contracting officer a certified claim asserting that “the government wrongfully and improperly terminated the Contract,” and requesting conversion of the termination to one for the convenience of the government and payment of 3,050,892,883 KRW ($2,062,696.47), 18 “for the work DSME performed prior to the termination and loss and damages incurred by DSME thereafter due to the wrongful and improper termination.” 19 On January 22, 2024, the contracting officer issued a decision stating that:

9 R4, tab 1a at 42 § 9.2.2 (emphasis added). 10 Gov’t br. at 18 ¶ 39; app. br. at 23-24 ¶ 81. 11 Gov’t br. at 18 ¶ 39; see app. br. at 14-15 ¶¶ 37-39. 12 See R4, tab 2 at 1-3. 13 DSME agrees. App. br. at 29 ¶ 102. The government says that the phase-in period began on April 17, 2023, and ended on June 30, 2023. Gov’t br. at 10 ¶ 22, 33, 35. That discrepancy is immaterial, because DSME did not provide a complete inventory until August 31, 2023. App br. at 24-25 ¶¶ 84, 86.

14 R4, tab 4; gov’t br. at 23 ¶ 57; app. br. at 5 ¶ 4. 15 App br. at 24-25 ¶¶ 84, 86. 16 R4, tabs 5b, 5c. 17 See R4, tab 5c at 1, 4. 18 As of April 16, 2026. 19 R4, tab 56 at 2-3, 201, 203, tab 56zn. In its complaint at page 1, DSME alleges that it “made the claim” on November 16, 2023. At page 3 of its answer, the government alleges that the contracting officer received the “complete claim” on November 20, 2023, citing page 1 of the contracting officer’s decision. But the contracting officer’s decision states that DSME’s claim is “dated

the Contracting Officer has determined not to convert the termination from [a termination for default] to [a termination for convenience]. The Government will pay for performance provided by DSME from 17 April 2023 thru 8 August 2023 (the stop work order date) [in accordance with] the contract. The contracting officer has repeatedly requested an invoice based on this amount and does not recognize the amount as part of this claim, as it has not been properly invoiced as of this time. 20

DSME noticed this appeal 85 days later, on April 16, 2024.

DECISION

I. Jurisdiction

Given that the contracting officer’s January 22, 2024 decision was issued seven days after the expiration of the 90-day period within which DSME could have timely appealed the contracting officer’s October 17, 2023 termination of the contract for default, we invited the parties to brief the issue of our jurisdiction. DSME says that we possess jurisdiction; the government disagrees. We find jurisdiction to entertain the appeal.

Free access — add to your briefcase to read the full text and ask questions with AI

DSME Construction Co., Ltd., (asbca 2026).

DSME Construction Co., Ltd. (DSME Construction Co., Ltd.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related