Drut Technologies Inc v. Microsoft Corporation Inc

District Court, W.D. Washington·Decided June 15, 2022·No. 2:21-cv-01653·Unknown

Opinion

WESTERN DISTRICT OF WASHINGTON

No. 2:21-cv-01653-BJR Plaintiff, v. ORDER GRANTING IN PART AND DENYING IN PART DEFENDANT MICROSOFT CORPORATION, MICROSOFT’S MOTION TO DISMISS

Defendants.

Before the Court is Defendant Microsoft Corporation’s (“Microsoft”) motion to partially dismiss Plaintiff’s Complaint (“Motion” or “Mot.,” Dkt. 16) pursuant to Rule 12(b)(6) of the Federal Rules of Civil Procedure. Plaintiff Drut Technologies, Inc. (“Drut”) opposes the Motion. Having reviewed the pleadings, the record of the case, and the relevant legal authorities, the Court GRANTS the Motion in part, and DENIES it in part. The Court’s reasoning is set forth below. II. FACTUAL BACKGROUND1 This dispute arises from a supplier agreement between Microsoft and Drut, a company that had, prior to the events at issue in this case, developed certain technology for use in cloud-based servers.2 Compl. ¶¶ 3-5. On November 20, 2019, Drut and Microsoft entered into a Master

1 The facts recited below are taken from Plaintiff’s Complaint (“Compl.,” Dkt 1). For the purposes of the present motion, the Court takes the factual allegations in the Complaint as true. 2 Drut designed a set of computer algorithms, and a configuration of software and hardware components, that allows cloud-based resources to be disaggregated so to improve servers’ efficiency. Compl. ¶¶ 3-5. ORDER - 1 Supplier Services Agreement (“MSSA”), pursuant to which Microsoft engaged Drut in a project in which Drut was to refine its developed technology and apply it to Microsoft’s Azure server network (the “Project”). Id. ¶¶ 15, 47; Declaration of Brian Tuttle (“Tuttle Decl.,” Dkt. 1), Ex. B (MSSA). Under the MSSA, Drut was to provide Microsoft several deliverables that were defined in a separate Statement of Work (“SOW”). Tuttle Decl., Ex C (SOW). The SOW divides the deliverables into five separate “milestones” and, for each milestone, provides for a specific delivery date and payment amount. Compl. ¶¶ 62-63; SOW at 2-7. Section 3 of the MSSA provides that “[e]ach party will own and retain all rights to its pre- existing IP and any IP developed independently of Services performed under this Agreement.” Compl. ¶ 58; MSSA at 6 § 3(a). Section 3 also contains a provision granting Microsoft a license to materials incorporated into Drut’s deliverables. It provides: If Supplier Materials are incorporated into Deliverables or are necessary for the use or distribution of Deliverables by Microsoft or any third-party, then Supplier will continue to own the Supplier Materials, including any Supplier IP therein (“Retained IP”). Unless the parties agree on written license terms, Supplier grants Microsoft and its Affiliates a worldwide, nonexclusive, perpetual, irrevocable, royalty-free, fully paid-up right and license, under all current and future Retained IP, to a. make, use, reproduce, format, modify, and create derivative works of the applicable Supplier Materials, b. publicly perform or display, import, broadcast, transmit, distribute, license, offer to sell and sell, rent, lease, or lend copies of the applicable Supplier Materials and derivative works thereof, c. combine the Supplier Materials and derivative works thereof with any software, firmware, hardware, or services, … MSSA at 7-8 § 3(c)(2) (emphasis added). Finally, Microsoft and Drut had entered into a Non-Disclosure Agreement (the “NDA”) in April 2019, prior to executing the MSSA. Compl. ¶ 98; Tuttle Decl., Ex. A (NDA). That agreement is incorporated into the MSSA, which provides that “[i]nformation shared under the ORDER - 2 [MSSA] is Confidential Information and subject to the NDA.” MSSA at 10 § 6(a)(1). The MSSA further requires the parties to “hold in strictest confidence and not use or disclose to any third- party any Confidential Information of the other party.” Compl. ¶¶ 61, 110; MSSA at 10 § 6. Drut alleges that, from February to April 2020, following its completion of Milestone 1, Microsoft imposed additional and costly requirements for the deliverables that delayed and hindered Drut’s completion of the milestones. Compl. ¶¶ 70-88. Despite Drut’s completion of Milestone 2 in late April 2020, Microsoft, which had by then adopted a “hostile” and “noncooperative” approach to the Project, refused to pay for those deliverables unless the parties amended the SOW. Id. ¶¶ 68-69, 94-96. The parties did so by executing a Change Order on April 24, 2020 that modified the work required for Milestones 2 through 5, and also required Drut to provide Microsoft with access to its source code and other proprietary technology. Id. ¶¶ 97-98, 100; Tuttle Decl., Ex. 4 (Change Order).3 To that end, Drut sent Microsoft a physical device that demonstrated Drut’s developed software and hardware configuration. Compl. ¶ 115. According to Drut, it eventually completed the remaining milestones by June 2020. Compl. ¶ 103. Microsoft, however, despite having previously represented that it would make payment for them, notified Drut on July 17, 2020 that it would not do so because Drut had missed milestone deadlines and failed to provide completed deliverables. Id. ¶¶ 104-05. Drut alleges that Microsoft, having received Drut’s proprietary information pursuant to the Change Order (Compl. ¶¶ 112-15), began to develop its own server using Drut’s technology. Id. ¶ 117. In September 2020, Microsoft posted a video onto YouTube that showed Microsoft’s Chief 3 Copies of the MSSA, the NDA, the SOW, and the Change Order were submitted by Microsoft with its Motion. Given the extent to which the Complaint and the claims asserted therein rely on those documents, and in the absence of any dispute as to their authenticity, the Court deems them incorporated by reference into the Complaint. See Marder v. Lopez, 450 F.3d 445, 448 (9th Cir. 2006).

Free access — add to your briefcase to read the full text and ask questions with AI

Drut Technologies Inc v. Microsoft Corporation Inc, (W.D. Wash. 2022).

Drut Technologies Inc v. Microsoft Corporation Inc (Drut Technologies Inc v. Microsoft Corporation Inc) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Nano-Proprietary, Inc. v. Canon, Inc.
537 F.3d 394 (Fifth Circuit, 2008)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Marder v. Lopez
450 F.3d 445 (Ninth Circuit, 2006)
Anderson v. Valley Quality Homes, Inc.
928 P.2d 1143 (Court of Appeals of Washington, 1997)
Berg v. Hudesman
801 P.2d 222 (Washington Supreme Court, 1990)
Hall v. Security Planning Service, Inc.
371 F. Supp. 7 (D. Arizona, 1974)
Birkholm v. Washington Mutual Bank, F.A.
447 F. Supp. 2d 1158 (W.D. Washington, 2006)
Millican of Washington, Inc. v. Wienker Carpet Service, Inc.
722 P.2d 861 (Court of Appeals of Washington, 1986)
Panag v. Farmers Ins. Co. of Washington
204 P.3d 885 (Washington Supreme Court, 2009)
Interpipe Contracting, Inc. v. Xavier Becerra
898 F.3d 879 (Ninth Circuit, 2018)
Wilkinson v. Chiwawa Communities Ass'n
327 P.3d 614 (Washington Supreme Court, 2014)
Olney v. McNair
177 P. 641 (Washington Supreme Court, 1919)
Garcia v. Department of Transportation
161 Wash. App. 1 (Court of Appeals of Washington, 2011)
Johnson v. Yousoofian
930 P.2d 921 (Court of Appeals of Washington, 1996)
Smith v. West Coast Marine Cleaning, Inc.
98 Wash. App. 1057 (Court of Appeals of Washington, 2000)
Cushing v. City of Chicago
3 F.3d 1156 (Seventh Circuit, 1993)