DRS Global Enterprise Solutions, Inc.

CourtArmed Services Board of Contract Appeals
DecidedAugust 30, 2018
DocketASBCA No. 61368
StatusPublished

This text of DRS Global Enterprise Solutions, Inc. (DRS Global Enterprise Solutions, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
DRS Global Enterprise Solutions, Inc., (asbca 2018).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) DRS Global Enterprise Solutions, Inc. ) ASBCA No. 61368 ) Under Contract No. DAAB07-03-D-B013 et al.)

APPEARANCES FOR THE APPELLANT: David Z. Bodenheimer, Esq. Skye Mathieson, Esq. Crowell & Moring LLP Washington, DC

APPEARANCES FOR THE GOVERNMENT: Arthur M. Taylor, Esq. DCMA Deputy Chief Trial Attorney Michael T. Patterson, Esq. Trial Attorney Defense Contract Management Agency Chantilly, VA

OPINION BY ADMINISTRATIVE JUDGE O'CONNELL ON APPELLANT'S MOTION FOR SUMMARY JUDGMENT

This appeal involves a government demand for repayment of more than $8.6 million. Appellant, DRS Global Enterprise Solutions, Inc. (DRS), contends that the government's claim is untimely and has moved for summary judgment. We deny the motion.

STATEMENT OFF ACTS FOR PURPOSES OF THE MOTION

The following facts are undisputed or uncontroverted.

On various dates, the government awarded contracts to DRS's predecessor (for simplicity, also referred to as DRS). The Defense Contract Management Agency (DCMA) administered these contracts for the government. Two of the contracts are in the record, both of which provide that DRS would be paid on a time-and-materials basis. (R4, tab 1 at G-2, tab 11 at G-255)

Appellant submitted the vouchers at issue between December 2005 and May 2006. The government paid all of these vouchers by December 15, 2006. (Appellant's Statement of Undisputed Material Facts (ASUMF) and Government's Response to ASUMF (gov't resp.) ,r,r 4-5; compl. and answer ,r 9) The vouchers are not in the record. On February 28, 2008, DRS submitted its fiscal year (FY) 2006 incurred cost proposal (ICP) for the period from November 1, 2005 to January 31, 2006, to the government. On March 31, 2008, DRS submitted its FY 2006A ICP for the period from February 1, 2006, to March 31, 2006. (ASUMF and gov't resp. ,r,r 7-8; R4, tabs 16-17)

On July 17, 2009, the Defense Contract Audit Agency (DCAA) conducted an entrance conference with DRS concerning the FY 2006 and 2006A ICPs (ASUMF and gov't resp. ,r 13; compl. and answer ,r 17).

Almost three years later, on April 3, 2012, DCAA informed DRS that its FY 2006 and FY 2006A ICPs were inadequate, contending that the schedules included with the submission lacked various information (ASUMF and gov't resp. ,r,r 18-19; app. supp. R4, tabs 24-25).

DRS thereafter submitted additional information and on June 22, 2012, DCAA informed DRS that it had provided sufficient information for DCAA to perform the audits (ASUMF and gov't resp. ,r,r 20, 23; app. supp. R4, tabs 27-28).

In September 2013, DCAA requested additional documentation from DRS, which it did not provide. On November 7, 2013, DCAA wTote to DRS to inform it that it had been denied access to data/documentation for labor transactions, direct material transactions and the other direct cost transactions. (Government proposed findings of fact ,r,r 9-11 1; ex. G-3 at G-14)

On December 30, 2013, DCAA issued an audit report in which it questioned more than $54 million in costs for the fiscal years at issue (ASUMF and gov't resp. ,r 24; R4, tab 8 at G-168).

More than three years later, on September 11, 2017, a DCMA contracting officer issued a final decision demanding repayment of $8,607,879.23. Of this amount, the vast majority, $8,416,435.16, was for "other direct costs" that the contracting officer contended were unallowable. The final decision listed the purportedly unallowable costs and identified various reasons for the disallowance, including the lack of an invoice for the costs, proof of payment, or a signed purchase order. The remainder of the amount sought arose from the difference between DRS's billing rates and the indirect cost rates established in the final decision. (ASUMF and gov't resp. ,r,r 27-29; R4, tab 10 at 239-45)

DRS filed a timely appeal with the Board on October 16, 2017.

1 DRS has not disputed these facts. Thus, we find them to be undisputed. Board Rule 7(c)(2). 2 DECISION

Summary judgment is appropriate when there is no genuine issue of material fact and the moving party is entitled to judgment as a matter of law. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 247-48 (1986). When considering a motion for summary judgment, the Board's function is not to weigh the evidence and determine the tmth of the matter but to determine whether there is a genuine issue for trial. Id at 249. We are required to view the record in the light most favorable to the nonmoving party, in this case the government. Matsushita Elec. Indus. Co. v. Zenith Radio Corp., 475 U.S. 574, 587 (1986).

The Contract Disputes Act (CDA) provides that "each claim by the Federal Government against a contractor relating to a contract shall be submitted within 6 years after the accrual of the claim.'' 41 U.S.C. § 7103(a)(4)(A). A claim accmes, "when all events, that fix the alleged liability of. .. the contractor and permit assertion of the claim, were known or should have been known.'' Federal Acquisition Regulation (FAR) 33.201. 2 The events fixing liability "should have been known" when they occurred unless they were either concealed or inherently unknowable at the time. Alion Sci. & Tech. Corp., ASBCA No. 58992, 15-1 BCA ,T 36,168 at 176,489 (citing Raytheon Missile Sys., ASBCA No. 58011, 13 BCA ,T 35,241 at 173,017). Only facts that could not reasonably be known by the claimant postpone claim accrual. Id. (citing United States v. Commodities Export Co., 972 F.2d 1266, 1272 (Fed. Cir. 1992)).

Failure to meet a statute of limitations is an affirmative defense, for which DRS bears the burden of proof. Kellogg Brown & Root Servs., Inc., ASBCA No. 58175, 15-1 BCA ,T 35,988 at 175,823 (citing FED. R. CIV. P. 8(c); Bridgestone Firestone Research, Inc. v. Automobile Club de L 'Quest de la France, 245 F.3d 1359, 1361 (Fed. Cir. 2001)).

DRS contends it is entitled to summary judgment because the government's claim accrued more than six years before the September 11, 2017 final decision, or, in

I other words, before September 11, 2011. DRS identifies three alternative accrual dates. First, it contends, that for direct costs, the government's claim accmed no later than December 15, 2006, when it paid the last of the invoices at issue. (App. mot. at 1) Second, for the indirect costs, DRS identifies February 28, 2008, the submission date for the FY 2006 ICP and March 31, 2008, the submission date for the 2006A ICP (id. at 2), as the accrual dates. It also contends that the claim for direct costs began to accme on these dates if it did not accrue in 2006 (id. at 23 ). Third, DRS contends that the claim accrued no later than the July 17, 2009 DCAA entrance conference by which

2 We quote from the current version of the regulation but the version in the 2002 FAR (the year of the earlier of the two contracts in the record (R4, tab 1)) is the same or very similar in material respects. 3 point DRS contends that the auditor should have been aware "that the costs in the vouchers and ICPs were not sufficiently substantiated" (id. at 26).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
DRS Global Enterprise Solutions, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/drs-global-enterprise-solutions-inc-asbca-2018.