Droemer v. Transit Mix Concrete of Gonzales, Inc.

457 S.W.2d 332, 1970 Tex. App. LEXIS 1926
CourtCourt of Appeals of Texas
DecidedJuly 23, 1970
Docket537
StatusPublished
Cited by8 cases

This text of 457 S.W.2d 332 (Droemer v. Transit Mix Concrete of Gonzales, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Droemer v. Transit Mix Concrete of Gonzales, Inc., 457 S.W.2d 332, 1970 Tex. App. LEXIS 1926 (Tex. Ct. App. 1970).

Opinion

OPINION

NYE, Justice.

This is a suit brought by the plaintiff Transit Mix Concrete of Gonzales, Inc. on a verified account for amounts allegedly due and payable under a contract to supply ready-mix concrete to the defendant Walter Droemer. The case was tried before the court without a jury. Judgment was rendered against Droemer and the Fidelity and Deposit Company of Maryland (surety on defendant’s payment bond) for the unpaid balance found to be due. The defendants have perfected this appeal.

The basic question is what was the agreed price that was to be paid for the concrete furnished by plaintiff Transit Mix Concrete of Gonzales, Inc. to defendant Walter Droe-mer. The parties will be referred to hereafter as they were in the trial court.

Defendant was the successful bidder to construct a new high school building in Gonzales, Texas. The plaintiff was a subcontractor and supplier of the ready-mix concrete that went into the job. The facts are relatively undisputed and the evidence supports the findings of fact and conclusions of law supplied by the trial court. We therefore affirm the judgment accordingly.

Many duplicate plans and specifications for the building were left in the office of the school superintendent for interested bidders and subcontractors. The plaintiff obtained a copy of the plans and specifications as they related to the concrete and thereafter furnished the defendant with a written bid on August 30, 1966. The original bid was as follows:

“I am pleased to quote the following prices for the materials listed on the new Gonzales High School Building.
5 Sack 3,000 lb. Concrete - $13.50 per yd.
Admixtures - ¼ lb. #8 Pozzolith per sack - .50 per yd.
1½" Washed Gravel - 2.94 per ton
Mortar Sand 4.85 per yd.”

The prime contract provided that the contractor shall furnish all materials shown on the drawings and specifications. Certain designs were to be determined and tests were to be performed before the concrete would be acceptable. The relevant provisions are:

“(1) Proportions of the concrete design shall be determined by an independent testing laboratory selected by the Architect. The design furnished will be such as to produce the 28 day compressive strength called for in the structural drawings. Design and preliminary (7) seven day compressive tests will be made sufficiently in advance of the work to obtain approval from the Engineer. The Contractor shall furnish all tests and designs.”
“(3) The results of all concrete tests will confirm that the concrete meets the design strengths specified and called for in the plans. All materials and concrete design are subject to the Engineer’s approval prior to commencement of work.”

*334 Under “Concrete Quality & Strength” there appear the following relevant provisions :

“CONCRETE QUALITY & STRENGTH:
“(1) Concrete shall develop a compressive strength as designated by the Engineer and as shown on the structural drawings * *
“(2) The proportions of concrete materials will follow the design mix specified above * *
* * * * * *
«(4) * * *. One quarter pound (¼) of #8 Pozzolith per sack of cement shall be included in the design of all concrete.”
The structural drawings contain the following provision:
“All concrete shall be proportioned to develop a min. of 3000 P.S.I. in compression within 28 days.”

On or about the 9th day of September 1966 defendant learned that he was awarded the contract. While the defendant was in Gonzales, he met with the plaintiff at his plant. While defendant was visiting with the plaintiff and looking over the plant, the two engaged in a conversation relative to furnishing concrete for the job. Defendant told the plaintiff that ever since he had been in Gonzales, he had been bombarded by people because of arrangements that he had made previously to buy his concrete from an out of town supplier. He told plaintiff that he would like very much for him to supply the job, and would in fact prefer to do business with a local business rather than with an outsider. However, he said that he had a lower price that he had based his successful bid upon. The plaintiff asked him how much lower. He said: “twenty-five cents.” Plaintiff then said: “Well, that would make the concrete thirteen twenty-five plus the admixtures.” The defendant said “Yes”, and plaintiff said: "Well, we will do it for that”, and defendant said : “Okay. Fine. What kind of cement can we use ? ” They agreed upon the type to be used, shook hands and wished each other well and left, (emphasis supplied)

The contention made by defendant is that plaintiff’s original bid which called for five sacks at $13.50, when reduced by a ½ sack to 41/2 sacks of concrete as the final specifications called for, should have also reflected a reduction in the price of 50⅜ to $12.75, plus the additives. The defendant contended that local practice was that the price of concrete would vary up or down by 50‡ for each half sack of cement used.

The plaintiff argues that the parties made a new specific oral deal for the concrete at $13.25; that he was required to furnish the concrete to the defendant so that it met the design specifications at this agreed price; and that the 50‡ per half sack variance as contended by defendant did not form any part of the agreement. We agree that the evidence is sufficient to support plaintiff’s contentions.

The record shows that during plaintiff’s conversation with defendant, nothing was said about the cement content for a yard of concrete. Defendant testified that he “had a lower bid” and asked the plaintiff to lower his price by 25‡. He did not mention any cement content by sacks, nor any price by the yard based on the content of cement. He did not testify specifically as to any other proposal that he had “in his pocket” that showed a sack content or a price by the yard based on a specific number of sacks. Defendant did not give any details of his lower bid, or the name of the lower bidder.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Intl Insurance Co v. RSR Corporation
426 F.3d 281 (Fifth Circuit, 2005)
International Ins. Co. v. RSR Corp.
426 F.3d 281 (Fifth Circuit, 2005)
Universe Life Insurance Co. v. Giles
881 S.W.2d 44 (Court of Appeals of Texas, 1994)
Sonne v. Federal Deposit Insurance Corp.
881 S.W.2d 789 (Court of Appeals of Texas, 1994)
Gilbert v. Pettiette
838 S.W.2d 890 (Court of Appeals of Texas, 1992)
Gillman v. Phillips Petroleum Co.
601 S.W.2d 513 (Court of Appeals of Texas, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
457 S.W.2d 332, 1970 Tex. App. LEXIS 1926, Counsel Stack Legal Research, https://law.counselstack.com/opinion/droemer-v-transit-mix-concrete-of-gonzales-inc-texapp-1970.