Driver Pipeline Company, Inc. v. Mustang Pipeline Company, Inc.

CourtCourt of Appeals of Texas
DecidedFebruary 13, 2002
Docket06-00-00053-CV
StatusPublished

This text of Driver Pipeline Company, Inc. v. Mustang Pipeline Company, Inc. (Driver Pipeline Company, Inc. v. Mustang Pipeline Company, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Driver Pipeline Company, Inc. v. Mustang Pipeline Company, Inc., (Tex. Ct. App. 2002).

Opinion



In The

Court of Appeals

Sixth Appellate District of Texas at Texarkana



______________________________



No. 06-00-00053-CV



DRIVER PIPELINE COMPANY, INC., Appellant



V.



MUSTANG PIPELINE COMPANY, INC., Appellee





On Appeal from the 124th Judicial District Court

Gregg County, Texas

Trial Court No. 97-617-B





Before Cornelius, C.J., Grant and Ross, JJ.

Opinion by Justice Grant



O P I N I O N



This is an appeal by Driver Pipeline Company, Inc. (Driver) and Mustang Pipeline Company, Inc. (Mustang) from a judgment in a lawsuit for breach of contract. Seaboard Surety Company, the insurer that provided a performance bond for Driver, is before this court as a cross-appellee.

Mustang wanted to build a gas pipeline from Longview to Diboll to Mount Belview (near Houston), a 200-mile stretch of pipeline. Mustang divided the work into the north spread and the south spread, each 100 miles long. After going through a bidding process, Mustang hired Driver to dig the trenches and lay the pipe for the north 100 miles of pipeline. Because Mustang wanted to finish the pipeline by a specific deadline, it prepared a contract stating that the prices were based on eleven hours per day and seven days a week to meet a fourteen-week schedule (ninety-eight construction days), and specifying that the final completion of the pipeline within that time was of "great importance to the Company." (1)

And then the rains came. At the end of fifty-eight days, Driver had finished only fifteen miles of the pipeline and had laid off some of its crews and suspended operations. Driver proposed that Mustang give it additional time and money to finish the project. Driver took the position that rain delayed its work and that all parties understood that his bid was based on no weather delays. The owner of the company, James Driver, testified by deposition that his bid took into account a fifteen percent contingency for rain days. At trial, however, Driver testified that this was a "best-time" contract with no rain days included and that he relied on a clause allowing (but not requiring) Mustang to give them extra time in the event of weather delays. There is evidence that the builder of the south portion of the line sought and received a thirty-day extension on its construction.

The contract does contain provisions explaining how the crews and welds were to be protected when working in the rain, which suggests that they expected Driver to work through at least some inclement weather rather than shutting down. Also, Driver was several days late in starting work and could have started earlier. The reasons are disputed.

When the rains came, there was testimony that Driver kept part of its crews working, but refused to move any operations to drier areas of the line to continue work. Driver offered testimony that such a move would have been a useless act because the entire length of the proposed pipeline was soaked. The evidence also shows that the rain in that time period of 1997 was above average, but within the five-year range for the area.

After several meetings, at which Driver's representatives and owner demanded more time and money because the pipeline could not be finished under the conditions of the contract, Mustang declared a breach.

Mustang had already been testing the waters with other construction companies, and after declaring a breach, it hired one of the original bidders, Sunland Construction. Mustang requested that Sunland finish as close to the original schedule as possible. Sunland hired a second crew, moved in, worked through the mud, and completed the remaining eighty-five miles of pipeline within eleven weeks.

Mustang sued Driver for breach of contract, seeking costs to complete the project, lost profits, and attorney's fees. Driver countersued for wrongful termination, seeking damages for termination, lost profits, and attorney's fees.

Mustang sought damages of $4,065,286 because it cost that much more than the original contract price with Driver to complete the pipeline. (2)

The Verdict

At the conclusion of an eight-day trial, the jury made the following findings:

  • Driver failed to comply with the contract;
  • Mustang was not justified in terminating its contract with Driver;


  • $2,104,601 would compensate Mustang for damages caused by Driver's failure to comply with the contract; and
  • $2,515,958 would compensate Driver for damages caused by Mustang's unjustified failure to comply with the contract. (3)

The Trial Court's Judgment Notwithstanding the Verdict

The trial court found that the verdict was for Driver and that there was "no evidence of probative force to sustain the jury's finding with respect to question No. 3" [the damages question for Mustang]. The court then rendered judgment in favor of Driver and Seaboard Surety against Mustang. The court awarded Driver actual damages of $3,146,728.33, plus attorney's fees, appellate attorney's fees, and ten-percent interest on the judgment.

Driver's Appeal

Driver filed the first Notice of Appeal and is labeled as the appellant. Driver contends that the trial court erred by not granting its motion to impose a statutory mineral lien in support of its victory in the trial court.

This issue has not been adequately preserved for review. When brought to the trial court's attention, the trial court stated that it would not grant the motion at that time, but that it would be willing to consider it later if Driver so desired. No further mention of the motion was made, and the trial court never denied the request. In such a situation, we cannot conclude that the trial court committed error.

Further, the stated purpose for the relief was to enforce the judgment. Since that time, Mustang has filed a supersedeas bond that is sufficient to cover the entirety of the judgment against it. Even if the court had denied the lien, and even if that were error, any right to recover on the judgment is now protected by the bond, and imposition of such a lien at this point would be duplicitous and improper. Driver is not entitled to have its right to recover on the judgment protected twice.

The Appeal by Mustang

Cross-Appellant Mustang raises five issues in which it contends that the trial court erred by disregarding the jury's answer to its damage issue; that because the jury found that Driver was in breach, the court erred by refusing to disregard the jury's answer finding that it had wrongfully terminated Driver; and that there was legally and factually insufficient evidence to support the finding of wrongful termination.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

English v. Fischer
649 S.W.2d 83 (Court of Appeals of Texas, 1982)
Mancorp, Inc. v. CULPEPPEER
802 S.W.2d 226 (Texas Supreme Court, 1990)
Exxon Corp. v. Quinn
726 S.W.2d 17 (Texas Supreme Court, 1987)
Merrell Dow Pharmaceuticals, Inc. v. Havner
953 S.W.2d 706 (Texas Supreme Court, 1997)
Roth v. Law
579 S.W.2d 949 (Court of Appeals of Texas, 1979)
Maritime Overseas Corp. v. Ellis
971 S.W.2d 402 (Texas Supreme Court, 1998)
Ashley v. Bizzell
694 S.W.2d 349 (Court of Appeals of Texas, 1985)
Osterberg v. Peca
12 S.W.3d 31 (Texas Supreme Court, 2000)
Crescendo Investments, Inc. v. Brice
61 S.W.3d 465 (Court of Appeals of Texas, 2001)
Dallas Railway & Terminal Company v. Gossett
294 S.W.2d 377 (Texas Supreme Court, 1956)
Liptak v. Pensabene
736 S.W.2d 953 (Court of Appeals of Texas, 1987)
Corso v. Carr
634 S.W.2d 804 (Court of Appeals of Texas, 1982)
Ron Craft Chevrolet, Inc. v. Davis
836 S.W.2d 672 (Court of Appeals of Texas, 1992)
County of Tarrant v. Butcher & Sweeney Construction Co.
443 S.W.2d 302 (Court of Appeals of Texas, 1969)
English v. Fischer
660 S.W.2d 521 (Texas Supreme Court, 1983)
Graco Robotics, Inc. v. Oaklawn Bank
914 S.W.2d 633 (Court of Appeals of Texas, 1996)
Lazy M Ranch, Ltd. v. TXI OPERATIONS, LP
978 S.W.2d 678 (Court of Appeals of Texas, 1998)
Weitzul Construction, Inc. v. Outdoor Environs
849 S.W.2d 359 (Court of Appeals of Texas, 1993)
Merchants Fast Motor Lines, Inc. v. State
917 S.W.2d 518 (Court of Appeals of Texas, 1996)
Atlantic Richfield Co. v. Long Trusts
860 S.W.2d 439 (Court of Appeals of Texas, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
Driver Pipeline Company, Inc. v. Mustang Pipeline Company, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/driver-pipeline-company-inc-v-mustang-pipeline-com-texapp-2002.