Drews Co. v. Ledwith-Wolfe Associates, Inc.

371 S.E.2d 532, 296 S.C. 207, 1988 S.C. LEXIS 100
CourtSupreme Court of South Carolina
DecidedAugust 29, 1988
Docket22904
StatusPublished
Cited by6 cases

This text of 371 S.E.2d 532 (Drews Co. v. Ledwith-Wolfe Associates, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Drews Co. v. Ledwith-Wolfe Associates, Inc., 371 S.E.2d 532, 296 S.C. 207, 1988 S.C. LEXIS 100 (S.C. 1988).

Opinion

Harwell, Justice:

This case involves the breach of a construction contract. We affirm the trial court’s refusal to grant a new trial, but reverse the jury’s award of lost profits.

FACTS

The Drews Company, Inc. (“Contractor”) contracted to renovate a building owned by Ledwith-Wolfe Associates, Inc. (“Owner”). Owner intended to convert the building into a restaurant. From its inception, the project was plagued by construction delays, work change orders, and general disagreement over the quality of work performed. Contractor eventually pulled its workers off the project. Contractor later filed, then sued to foreclose, a mechanic’s lien for labor and materials used in renovating the building. Owner counterclaimed, alleging Contractor breached the contract and forced Owner to rework part of the job. Owner also claimed that Contractor’s delays in performance caused Owner to lose profits from the restaurant.

The jury returned an $18,000 verdict for Contractor on its complaint. The jury awarded Owner $22,895 on its counterclaim for re-doing and completing the work and $14,000 in lost profits caused by Contractor’s delays. The trial judge denied Contractor’s new trial motion and awarded Owner attorney’s fees and costs pursuant to S. C. Code Ann. §29-5-10 (Supp. 1987) (mechanics’ liens).

[209]*209A.

Contractor first argues that the trial court erred in admitting evidence of Owner’s “delay damages” because the contract contained no completion date or statement that “time was of the essence.” We disagree.

A contractor may be liable for delay damages regardless of whether time was of the essence of the contract. 17A C.J.S. Contracts § 502(4)(a) (1963). Where a contract sets no date for performance, time is not of the essence of the contract and it must be performed within a reasonable time. General Sprinkler Corp. v. Loris Industrial Developers, Inc., 271 F. Supp. 551, 557 (D.S.C. 1967); see Davis v. Cordell, 237 S. C. 88, 115 S. E. (2d) 649 (1960) (applying “reasonable time” rule to time for payment under contract); Cloniger v. Cloniger, 261 S. C. 603, 193 S. E. (2d) 647 (1973) (applying “reasonable time” rule to agreement to repurchase property within an unspecified time); Smith v. Spratt Machine Co., 46 S. C. 511, 24 S. E. 376 (1896) (where manufacturing contract specified no time for performance, “reasonable time” implied); see also 17A C.J.S. Contracts § 503(a)(1) (1983) (“reasonable time” for performance will be implied where no time therefor is fixed in building or construction contract). The timeliness of Contractor’s performance here was a disputed factual issue properly reserved for jury determination.

B.

Contractor’s next exception presents this Court with an opportunity to address a legal issue unsettled in South Carolina: Does the “new business rule” operate to automatically preclude the recovery of lost profits by a new business or enterprise? We hold that it does not.

1. Lost Profits In South Carolina

We begin our analysis of the lost profits issue by recognizing an elementary principle of contract law. The purpose of an award of damages for breach is “to give compensation, that is, to put the plaintiff in as good a position as he would have been in had the contract been performed.” 11 S. WILLISTON, A TREATISE ON THE [210]*210LAW OF CONTRACTS, §1338 (3d ed. 1968). The proper measure of that compensation, then, “is the loss actually-suffered by the contractee as the result of the breach.” South Carolina Finance Corp. v. West Side Finance Co., 236 S. C. 109, 122, 113 S. E. (2d) 329, 335 (1960).

“Profits” have been defined as “the net pecuniary gain from a transaction, the gross pecuniary gains diminished by the cost of obtaining them.” Restatement of Contracts § 331, Comment B (1932); see Mali v. Odom, 295 S. C. 78, 367 S. E. (2d) 166 (Ct. App. 1988) (defining “profits” as the net of income over expenditures during a given period). Profits lost by a business as the result of a contractual breach have long been recognized as a species of recoverable consequential damage in this state. Hollingsworth on Wheels, Inc., v. Arkon Corp., 279 S. C. 183, 305 S. E. (2d) 71 (1983); South Carolina Finance Corp. v. West Side Finance Co., supra. The issue is more difficult, however, when a new or unestablished business is the aggrieved party seeking projected lost profits as damages.

The new business rule as a per se rule of nonrecoverability of lost profits was firmly established in this state in Standard Supply Co. v. Carter & Harris, 81 S. C. 181, 187, 62 S. E. 150, 152 (1907): “When a business is in contemplation, but not established or not in actual operation, profit merely hoped for is too uncertain and conjectural to be considered.” McMeekin v. Southern Ry. Co., 82 S. C. 468, 64 S. E. 413 (1909), like Standard Supply Co., involved profits allegedly lost when a carrier failed to deliver machinery necessary for a new mill enterprise. The Court adhered to a strict application of the rule, stating that “[t]he plaintiff’s business had not been launched, and therefore he could not-recover profits he expected to make.” Id. at 473, 64 S. E. at 415; cited in Currie v. Davis, 130 S. C. 408, 126 S. E. 119 (1923) (new business rule applied to prelude recovery of lost profits where carrier’s tort against passenger delayed production by passenger’s cotton gin “not yet in active operation”).

Modern' cases, however, reflect the willingness of this Court and our Court of Appeals to view the new business rule as a rule of evidentiary sufficiency rather than an automatic bar to recovery of lost profits by a new business. See Hollingsworth on Wheels, Inc. v. Arkon Corp., supra [211]*211(holding that while aggrieved buyer’s projections of lost profits from new business enterprise introduced unreasonable amount of uncertainty into damages computation, evidence sufficient to permit Court itself to reach reasonable figure for profits lost); Bryson v. Arcadian Shores, Inc., 273 S. C. 471, 257 S. E. (2d) 233 (1979) (evidence of room revenues allegedly lost by hotel as result of construction delay held speculative and insufficient to allow recovery); Mali v. Odom, supra (attorney malpractice action — estimates of anticipated monthly income from new school held speculative and without reasonable basis where offered without reference to operational history or standard method for estimations); Petty v. Weyerhaeuser Co., 288 S. C. 349, 342 S. E. (2d) 611 (Ct. App. 1986) (tort action — three month period business operated prior to debilitating effect of tort afforded basis for fairly and reasonably approximating lost profits). These cases have so eroded the new business rule as an absolute bar to recovery of lost profits that the rigid Standard Supply Co., rule is no longer good law.

2. A Multi-Jurisdictional Trend

South Carolina has not been alone in developing its evi-dentiary view of the new business rule. Numerous authorities and commentators have tracked a similar trend nationwide: “Courts are now taking the position that the distinction between established businesses and new ones is a distinction that goes to the weight of the evidence and not a rule that automatically precludes recovery of profits by a new business.” D. Dobbs, HANDBOOK ON THE LAW OF REMEDIES, § 3.3, at 155 (1973). See R.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Vanwyk Textile Systems, B v. v. Zimmer MacHinery America, Inc.
994 F. Supp. 350 (W.D. North Carolina, 1997)
South Carolina Federal Savings Bank v. Thornton-Crosby Development Co.
399 S.E.2d 8 (Court of Appeals of South Carolina, 1990)
Beck v. Clarkson
387 S.E.2d 681 (Court of Appeals of South Carolina, 1989)
Drews Co., Inc. v. LEDWITH-WOLFE ASSOC., INC.
371 S.E.2d 532 (Supreme Court of South Carolina, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
371 S.E.2d 532, 296 S.C. 207, 1988 S.C. LEXIS 100, Counsel Stack Legal Research, https://law.counselstack.com/opinion/drews-co-v-ledwith-wolfe-associates-inc-sc-1988.