Dravo Corp. v. United States

93 Ct. Cl. 270, 1941 U.S. Ct. Cl. LEXIS 137, 1941 WL 4610
CourtUnited States Court of Claims
DecidedMarch 3, 1941
DocketNo. 45147
StatusPublished
Cited by1 cases

This text of 93 Ct. Cl. 270 (Dravo Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dravo Corp. v. United States, 93 Ct. Cl. 270, 1941 U.S. Ct. Cl. LEXIS 137, 1941 WL 4610 (cc 1941).

Opinions

Littleton, Judge,

delivered the opinion of the court:

December 21, 1933, The Dravo Contracting Company, a Pennsylvania corporation, entered into a contract with the defendant through the Corps of Engineers of the War Department for the construction of two parallel locks and appurtenant works at the Gallipolis Locks and Dam on the1 Ohio Eiver, near Gallipolis, Ohio. The contract and specifications, portions of which are hereinafter set forth, are attached to the original petition herein, and are made a part hereof by reference.

December 31,1936, plaintiff succeeded by operation of law to the entire business, assets and liabilities, including the claim here involved, of The Dravo Contracting Company. No question as to the right of plaintiff to maintain and prosecute this suit is involved and, for convenience, The Dravo Contracting Company and the Dravo Corporation will hereinafter be referred to as “plaintiff.”

Plaintiff constructed a cofferdam and the two parallel locks and appurtenant works in strict accordance with the terms of the contract and all modifications thereof, and did and performed all things which it undertook to do and perform,' as directed by the officers and employees of the defendant. Art. 1 of the contract provided that “The contractor shall furnish all labor and materials, and perform all work required for constructing two parallel locks, including guide and guard walls, gates and gate operating machinery, valves and valve operating machinery, and piping at the Gallipolis Lock and Dam, Ohio Eiver, near Gallipolis, Ohio, for the consideration of a sum based on designations and unit prices specified in schedule appended hereto in strict accordance with the specifications, schedules, and drawings, all of which are made a part hereof * * This article further provided as follows:

The work shall be commenced within ten (10) calendar days after the date of receipt by the contractor of notice to proceed, and shall be completed within 650 calendar days after the date of receipt by the contractor of the aforesaid notice to proceed.
[272]*272An amount of time equal to that lost as a result of the flooding of cofferdam built to the required height caused by rises in the Ohio River (see par. 9 of specifications) will be allowed in addition to the 650 calendar days specified for the completion of the work, provided it is clearly established that this time is not due to any negligence on the part of the contractor.

Par. 1-02 of Section 1 of the Detail Specifications, made a part of the contract and entitled “Cofferdams, Excavation, Foundations and Fill,” provides as follows:

Cofferdam,.
(a) The entire work shall be constructed within a cofferdam as indicated on sheet 19/1. The cofferdam shall consist of connected circular cells of interlocked steel sheet piling driven to refusal in rock. The cells shall be filled with suitable material and capped with a 6-inch layer of concrete. The cofferdam shall be built to elevation 530.0 which is 18 feet above the normal pool above Dam No. 27, Ohio River. The base width of the cofferdam shall be at least equal to its height unless equal stability is otherwise provided.

Par. 9 of the specifications referred to in the last above-quoted provision of Art. 1 of the contract provides as follows:

(a) In the event that work remains to be done and is actually in progress within the cofferdam constructed to the height specified in Section 1, and a rise in the Ohio River overtops the cofferdam where built and maintained to the full height specified in paragraph 1-02, an allowance of $5,000 will be made to the contractor upon full resumption of work within the cofferdam, subject to the following: Only one allowance will be made for a rise, allowances for overtopping of the cofferdam will be made only during the period allowed for completion of the work under paragraph 6 of these specifications, and such extension thereof as • may be allowed under Articles 3 and 9 of the contract.
(b) No allowance will be made in case the cofferdam is flooded through failure of the cofferdam. In case the contractor floods the cofferdam during a rise prior to natural flooding due to overtopping the cofferdam, the flooding will be considered grounds for the allowance provided the rise actually overtops the cofferdam where built to the full height specified.

[273]*273Plaintiff prepared and submitted plans and blue prints to the defendant for a cofferdam showing a height to elevation •530, as required by the specifications, and such plans were approved by the contracting officer. The plaintiff thereupon constructed the cofferdam to elevation 530 as called for by the specifications and in accordance with plans and blue prints submitted to and approved by the contracting officer. In addition to the construction of such cofferdam to elevation 530, the plaintiff of its own volition and without request or direction by the contracting officer, either orally or in writing, but with the knowledge and acquiescence of defendant’s officers and employees having charge of the work called for by the contract, added, at its own expense and with its materials, two feet to the height of the cofferdam as called for by the contract and specifications, thereby bringing the height of the cofferdam to elevation 532 feet. This voluntary increase in the contract height of the cofferdam was made by plaintiff as a precaution against flooding of the cofferdam and resulting interference with the work to be constructed and performed therein, in the event the waters •of the Ohio Eiver in the pool above the dam should reach a stage above elevation 530 but lower than 532. The petition alleges that “the cost of this extra 2 feet of construction work together with the expense of removal of machinery and other extraordinary outlays caused by floods on the two occasions when the water exceeded 530 feet, but did not exceed 532 feet, was in excess of $10,000.00.”

April 8, 1934, while work called for by the contract was actually in progress within the cofferdam, and while other such work remained to be done, a rise in the Ohio Eiver occurred which exceeded elevation 530 at the place where the cofferdam was constructed and maintained, but the rise did not reach elevation 532. During this rise plaintiff discontinued operations but as soon as practicable, and within a day or two thereafter and while there remained work to be done within the cofferdam, plaintiff resumed work. The cofferdam was not overtopped or flooded. On February 28, 1935, while work was actually in progress within the cofferdam and while other such work remained to be done under the contract, another rise in the Ohio Eiver occurred during [274]*274which the water in the pool above the dam, on which the cofferdam was constructed, exceeded elevation 530 at the place where the coiferdam had been constructed and was maintained but did not reach an elevation of 532. The water did not overtop the coiferdam and it was not flooded. As soon as practicable, and within a day or two after this rise the waters subsided, and while there remained work to be performed within the cofferdam, the plaintiff fully resumed such work.

At some time subsequent to the two rises in the waters of the Ohio River on April 8, 1934, and February 28, 1935, the exact date not being stated, plaintiff demanded of defendant payment of $10,000 which plaintiff claimed was due it under par.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
93 Ct. Cl. 270, 1941 U.S. Ct. Cl. LEXIS 137, 1941 WL 4610, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dravo-corp-v-united-states-cc-1941.