Dravo Corp. v. City of New York

198 Misc. 161, 98 N.Y.S.2d 682, 1947 N.Y. Misc. LEXIS 3853
CourtNew York Supreme Court
DecidedMay 16, 1947
StatusPublished

This text of 198 Misc. 161 (Dravo Corp. v. City of New York) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dravo Corp. v. City of New York, 198 Misc. 161, 98 N.Y.S.2d 682, 1947 N.Y. Misc. LEXIS 3853 (N.Y. Super. Ct. 1947).

Opinion

Miller, J.

TMs motion for summary judgment dismissing the complaint is granted. The contract between the parties provided that “ if the Contractor fails, neglects or refuses to accept the payment due him under the certificate of completion and acceptance * * * then no action shall lie or be maintained by the Contractor against the City upon any claim arising out of or based upon this contract * * ü unless such action shall be commenced within one year after the date of filing in the office of the Comptroller of the City of New York of the certificate of completion and acceptance.” The present action was not commenced within one year after the date of filing of the certificate of completion and acceptance. Plaintiff claims that the one-year provision did not commence to run because of the retention by the city of $28.22 out of $26,028.22 conceded by the city to be due herein. Although the $28.22 may not have been [162]*162tendered to the plaintiff by the city, there appears to be no question but that the plaintiff, had it so requested, could have obtained the $28.22 from the city, that amount being concededly due to plaintiff. In the circumstances, the case appears to be one where the contractor has failed or neglected to accept the payment due him under the certificate of completion and acceptance, and the action should therefore have been commenced within one year after the filing of that certificate. The fact that it may have been the intention of the deputy comptroller, as well as of the plaintiff, that plaintiff’s time be extended by the procedure adopted beyond the one-year period of limitation provided for in the contract, is immaterial. The procedure adopted was not sufficient, for the reason above indicated, to render inapplicable the condition of the one-year limitation, viz., that the contractor fail or neglect to accept the payment due him under the certificate of completion and acceptance. It is to be noted further that the deputy comptroller had no authority, in any event, to modify the provisions of the contract and extend the time for the commencement of suit (see Oakhill Contr. Co. v. City of New York, 262 App. Div. 530).

Settle order.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Oakhill Contracting Co. v. City of New York
262 A.D. 530 (Appellate Division of the Supreme Court of New York, 1941)