Dr. Mickey Lee Peshoff v. Kenneth R. Belanger

CourtLouisiana Court of Appeal
DecidedMarch 6, 2013
DocketCA-0012-1231
StatusUnknown

This text of Dr. Mickey Lee Peshoff v. Kenneth R. Belanger (Dr. Mickey Lee Peshoff v. Kenneth R. Belanger) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dr. Mickey Lee Peshoff v. Kenneth R. Belanger, (La. Ct. App. 2013).

Opinion

NOT DESIGNATED FOR PUBLICATION

STATE OF LOUISIANA COURT OF APPEAL, THIRD CIRCUIT

CA 12-1231

DR. MICKEY LEE PESHOFF, ET AL.

VERSUS

KENNETH R. BELANGER

**********

APPEAL FROM THE THIRTY-EIGHTH JUDICIAL DISTRICT COURT PARISH OF CAMERON, NO. 10-18759 HONORABLE PENELOPE QUINN RICHARD, DISTRICT JUDGE

JOHN E. CONERY JUDGE

Court composed of Marc T. Amy, Shannon J. Gremillion, and John E. Conery, Judges.

AFFIRMED. Winfred Thomas Barrett, III Attorney at Law 3401 Ryan Street, Suite 307 Lake Charles, Louisiana 70605 (337) 474-7311 COUNSEL FOR PLAINTIFFS/APPELLEES: Dr. Mickey Lee Peshoff Elizabeth Mae Peshoff

Larry Arlen Roach Jr. Attorney at Law 2917 Ryan Street Lake Charles, Louisiana 70601 (337) 433-8504 COUNSEL FOR DEFENDANT/APPELLANT: Kenneth R. Belanger CONERY, Judge.

Defendant, Kenneth R. Belanger (Belanger) appeals the trial court’s judgment

in favor of Plaintiffs, Dr. Mickey Lee Peshoff and Elizabeth Mae Peshoff (Peshoff).

For the following reasons, we affirm.

FACTS AND PROCEDURAL HISTORY

Plaintiff, Peshoff, entered into a series of written agreements (hereinafter

referred to collectively as the contract) with Defendant, Belanger, wherein Belanger

agreed to elevate and complete the construction of a prefabricated one story home for

Peshoff. The parties agree that Peshoff wanted the home completed by June 1, 2010.

The initial agreement was dated October 10, 2009, and was for the sum of $35,000. It

provided that Belanger would clear the property where the house was to be located

and another piece of property owned by Peshoff, do certain preparatory work

including concrete work and pilings, and assemble and complete the outer shell of the

home according to engineer-approved plans. The only materials provided by Belanger

under this portion of the contract were the pilings and concrete. The costs of all other

materials were to be the responsibility of Peshoff. The total amount of $35,000 under

this portion of the contract was paid in full by Peshoff at the time the contract was

executed. At trial, both parties testified that some of the trim work and some of the

soffit work were never completed under this portion of the contract, and that there was

a small crack in the concrete around one of the pilings.

The second written agreement required payment in the amount of $5,100,

which was paid in full on December 4, 2009, when the agreement was executed.

Peshoff testified that all work was performed under this portion of the contract.

The third written agreement was executed on January 21, 2010, and was in the

amount of $2,900. Peshoff paid the total amount under this agreement at the time he

1 executed this portion of the contract. It provided that Belanger would construct a

stairway from the ground level to the deck of the house at a cost of $2,500, and he

would construct an elevated platform for the HVAC system at a cost of $400. It also

provided that the materials would be purchased by Belanger and reimbursed by

Peshoff. On February 1, 2010, Peshoff paid Belanger $650 for the materials for the

stairway. Peshoff testified, and Belanger did not dispute, that although the stairway

was begun, it was never completed by Belanger. Peshoff testified that he paid

someone else $1,200 to build the stairway in order to access his home. The court

noted at the time of trial that the stairway was still not complete because it had no

railings. Belanger testified that he thought the cost to complete the stairway would be

about $700.

The fourth and final written agreement was for a total of $58,000 and included

all materials and labor. It was executed on March 9, 2010, and provided that the

contractor would complete the interior of the shell home and install a septic system.

According to this portion of the contract, Peshoff was to pay $29,000 at the time the

fourth written agreement was executed, $16,000 when approximately 50% of the

work was complete, and $13,000 as a final payment. Peshoff paid the initial payment

of $29,000 and paid an additional $9,000 on May 19, 2010, for a total of $38,000.

There was no testimony as to why the $9,000 payment was paid before it was due

under the contract. Both parties agree that Belanger only installed sub-flooring and a

vapor barrier under the agreement. According to Belanger’s testimony, when he left

the job, he had completed about 10% of the work on this portion of the contract with

an estimated cost of about $5,000.

On Friday, June 11, 2010, Belanger went to Peshoff’s office after business

hours and presented various receipts to him for reimbursement. The receipts are dated

2 April 15, 2010, May 20, 2010, May 22 2010, May 23, 2010, May 24, 2010, May 25,

2010, May 26, 2010, June 3, 2010, June 8, 2010, and June 10, 2010, and totaled

$1,466.02. According to Belanger’s testimony, these receipts represented materials

purchased under the first agreement, which was executed in October 2009, and under

the third agreement, which was executed on January 21, 2010, and were due from

Peshoff upon presentation. The trial court found that Peshoff had previously

reimbursed Belanger for materials under both of these agreements in the amount of

$10,824.47.

According to Peshoff, when Belanger presented these receipts, Peshoff was

frustrated with the progress on his home and questioned the invoices. The home was

to have been completed by June 1, 2011, and on June 11, 2011, when Belanger

appeared at his office to demand payment on these relatively minor invoices, the

home was nowhere near complete. Peshoff requested an accounting and wanted

Belanger to meet with his attorney. Belanger testified that Peshoff refused to

reimburse him for these invoices totaling $1,466.02. According to Belanger, Peshoff

said that he was contacting an attorney and placing the home up for sale. Belanger

testified that, after hearing Peshoff’s threat, he contacted his attorney and, acting on

his attorney’s advice, Belanger immediately removed his tools from the job site.

Belanger testified that his attorney advised him to present the receipts to Peshoff again

on Monday, June 14, 2010, and, if Peshoff failed to pay, then Belanger should file a

lien on Peshoff’s property. According to Belanger, when the receipts were presented

again on June 14, 2010, Peshoff continued to refuse to pay him. Belanger filed his lien

the same day, and his attorney sent Peshoff a demand letter. Thereafter, on June 22,

2010, just eleven days later, Peshoff paid Belanger $1,506.02, $40.00 more than the

3 amount of the invoices.1 Belanger claimed that Peshoff was in breach of the contract

for failure to pay the invoices upon presentation and refused to return to the job site.

The parties and their respective attorneys met on or about July 27, 2010, to

attempt to amicably resolve this matter. At that meeting, Belanger presented Peshoff

with two additional invoices, and demanded payment prior to his return to the job site.

Both invoices are dated July 27, 2010. Neither invoice/change order was signed by

Peshoff as required under the initial contract. One, in the amount of $600, was for a

temporary utility pole that Belanger installed at Peshoff’s request. On August 1, 2010,

Peshoff wrote Belanger a check in the amount of $437, the actual cost of the pole,

without compensating him for his labor to install the pole. Because Peshoff

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Evangeline Parish Sch. Bd. v. ENERGY CONTR. SERVICES, INC.
617 So. 2d 1259 (Louisiana Court of Appeal, 1993)
Borden, Inc. v. Gulf States Utilities Co.
543 So. 2d 924 (Louisiana Court of Appeal, 1989)
Hays v. Christus Schumpert Northern Louisiana
72 So. 3d 955 (Louisiana Court of Appeal, 2011)
Burns v. Couvillion
53 So. 3d 540 (Louisiana Court of Appeal, 2010)
Caldwell ex rel. State v. Janssen Pharmaceutical, Inc.
100 So. 3d 865 (Louisiana Court of Appeal, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
Dr. Mickey Lee Peshoff v. Kenneth R. Belanger, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dr-mickey-lee-peshoff-v-kenneth-r-belanger-lactapp-2013.