D.R. Horton v. Campus Housing Company
This text of D.R. Horton v. Campus Housing Company (D.R. Horton v. Campus Housing Company) is published on Counsel Stack Legal Research, covering Court of Appeals of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
THIS OPINION HAS NO PRECEDENTIAL VALUE. IT SHOULD NOT BE CITED OR RELIED ON AS PRECEDENT IN ANY PROCEEDING EXCEPT AS PROVIDED BY RULE 239(d)(2), SCACR.
THE STATE OF SOUTH CAROLINA
In The Court of Appeals
D.R. Horton, Inc., Respondent,
v.
Campus Housing Company, LLC, Appellant.
Appeal From Beaufort County
Curtis Coltrane, Special Circuit Court
Judge
Unpublished Opinion No. 2008-UP-335
Heard May 8, 2008 Filed July 1, 2008
AFFIRMED
Barry Johnson and Jason Ward, both of Okatie, for Appellant.
James Herring and G. Hamlin OKelley, both of Bluffton, for Respondent.
PER CURIAM: Campus Housing Company, LLC (Campus Housing) appeals the trial courts order denying its claims for reformation and specific performance of a land sale contract entered into with D.R. Horton, Inc. (Horton). We affirm.
FACTS
On January 29, 2003, Horton and Campus Housing entered into a contract for the purchase of real estate in Beaufort County. Pursuant to the contract, Campus Housing was obligated to make deposits into escrow in four separate amounts at specific times.[1] The contract also provided the Seller will have reasonable ARB [Architectural Review Board] approval over the product that will be built by the Purchaser, with said ARB guidelines being provided to the Purchaser by the Seller during the Due Diligence Period.
On November 19, 2003, the parties amended the original contract with an Addendum to Purchase Agreement (Addendum). In the Addendum, Campus Housing had until April 25, 2004 to complete its due diligence study on the property to determine the suitability of the property for its intended use. Campus Housing could then choose to either terminate the agreement or make the final deposit into escrow.
On April 2, 2004, Horton and Campus Housing entered into a new contract for the purchase and sale of additional property in Beaufort County. The new contract also gave Campus Housing until April 25, 2004 to complete its due diligence study to determine if it wanted to make the final deposit into escrow.
By letter dated April 21, 2004, Campus Housing informed Horton that pursuant to the contract, it believed the deadline for delivering its ARB guidelines (guidelines) to Campus Housing was April 7, 2003, more than a year prior to the date of the letter. Therefore, Campus Housing argued the due diligence period should be extended for a period equal to the time between the due date and the date Horton would be providing the guidelines to Campus Housing. In a second letter, Campus Housing further claimed it was not required to close until Horton provided the guidelines, even though the original contract set the closing for fifteen days after the end of the due diligence period. Horton rejected Campus Housings argument, claiming the delivery of the guidelines was not a condition precedent to Campus Housings obligation to make the escrow deposits.
As of April 26, 2004, Campus Housing had not made the final deposits into escrow or terminated either contract. On April 26, Campus Housing sent notices to Horton alleging Horton was in default under the terms of both contracts. Specifically, Campus Housing claimed Horton failed to timely provide the guidelines because Horton was obligated under the contracts to provide the guidelines to Campus Housing during the time period Campus Housing was required to complete its due diligence studies. The following day, Horton sent a notice of default to Campus Housing for failure to make the escrow payments. According to the original contract, each party was entitled to written notice of default and would have fifteen days from the receipt of the notice to cure the alleged defect.
On April 30, 2004, Horton wrote to Campus Housing providing the guidelines Horton intended to impose on the land:
[T]he only [guidelines] which Horton will impose on [the land] . . . would be Hortons prior written approval of the design and exterior color of any improvements [to the land] within 100 of the properties common boundary line with property owned by [Horton] and within 150 of the intersection of any right of way at the point where such right of way crosses from property owned by [Horton] into properties owned by Campus Housing.
The letter further stated if [Campus Housing] purchases all properties . . . currently under contract to purchase from [Horton] there will be no [guidelines] imposed by [Horton].
On May 3, 2004, Campus Housing wrote to Horton asking for clarification as to what guidelines Horton planned to employ. In response, Horton wrote Campus Housing the next day addressing Campus Housings questions. However, Campus Housing contended Hortons letters did not sufficiently provide the architectural guidelines required by the contract. Neither the original contract nor the Addendum defines what the parties intended by the term guidelines.
Subsequently, Horton wrote to Campus Housing informing them Horton was willing to enter into negotiations to revive the January 29 contract because Horton considered the contracts to be terminated due to Campus Housings failure to timely make their payments. The same day, Campus Housing wrote to Horton contending Horton had not provided the guidelines as required and rejecting Hortons assertion the contracts had been terminated.
On May 26, 2004, Horton filed a declaratory judgment action against Campus Housing for breach of contract. On June 2, Campus Housing filed its answer and counterclaims for reformation and special performance. After a trial without a jury, the trial court issued its order denying both parties claims. Both parties filed Rule 59(e), SCRCP, motions to alter or amend, which the court denied on February 8, 2007. This appeal followed.
STANDARD OF REVIEW
A suit for declaratory judgment is neither legal nor equitable, but is determined by the nature of the underlying issue. Gordon v. Colonial Ins. Co. of Cal., 342 S.C. 152, 155, 536 S.E.2d 376, 378 (Ct. App. 2000).[2] Reformation of a contract and an action for specific performance are actions in equity. Glasscock, Inc. v. U.S. Fidelity & Guar. Co., 348 S.C. 76, 81, 557 S.E.2d 689, 691 (Ct. App. 2001); Ingram v. Kaseys Assocs., 340 S.C. 98, 531 S.E.2d 287 (2000); see Godfrey v. E.P. Burton Lumber Co., 88 S.C. 132, 133, 70 S.E. 396, 397 (1910). In an action in equity, tried by the judge alone, the appellate court has jurisdiction to find facts in accordance with its views of the preponderance of the evidence. Townes Assocs., Ltd. v. City of Greenville, 266 S.C. 81, 86, 221 S.E.2d 773
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
D.R. Horton v. Campus Housing Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dr-horton-v-campus-housing-company-scctapp-2008.