Dozier v. Commissioner

1967 T.C. Memo. 97, 26 T.C.M. 467, 1967 Tax Ct. Memo LEXIS 163
CourtUnited States Tax Court
DecidedMay 5, 1967
DocketDocket No. 880-64.
StatusUnpublished

This text of 1967 T.C. Memo. 97 (Dozier v. Commissioner) is published on Counsel Stack Legal Research, covering United States Tax Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dozier v. Commissioner, 1967 T.C. Memo. 97, 26 T.C.M. 467, 1967 Tax Ct. Memo LEXIS 163 (tax 1967).

Opinion

George A. Dozier and Dixie G. Dozier v. Commissioner.
Dozier v. Commissioner
Docket No. 880-64.
United States Tax Court
T.C. Memo 1967-97; 1967 Tax Ct. Memo LEXIS 163; 26 T.C.M. (CCH) 467; T.C.M. (RIA) 67097;
May 5, 1967

*163 Petitioner's subcontractor on two highway construction projects became unable to meet payments for taxes, labor, supplies, materials and for equipment and, in order to avoid any interruption on the projects, petitioner undertook to make the necessary payments until work was completed. As collateral for his expenditures, petitioner took back a second mortgage on the subcontractor's home and on certain road construction equipment. The subcontractor also assigned corporate stock and policies of life insurance to petitioner. Records were kept by both parties showing the amounts received and expended by petitioner on the subcontractor's behalf. In June 1962, the parties executed a settlement agreement to settle matters between them.

Petitioner used the completed contract method of accounting for income realized from his highway construction contracts. In August 1961 work was completed on the Shelby County job. However, there was substantial difference between the amount claimed by petitioner for the work done and the admitted liability of the State Highway Department. A recheck was made and in 1962 the State Highway Department made payments to petitioner greatly in excess of its admitted*164 liability in 1961.

Held, under these facts the parties intended a debtor-creditor relationship in connection with the expenditures made by petitioner on the subcontractor's behalf and the outstanding obligations of the subcontractor to petitioner did not become worthless to any extent prior to 1962.

Held, further, in view of the dispute existing in 1961 over the entire amount payable on the Shelby County job, the contract was properly closed into income in 1962.

Harold I. Apolinsky and Joseph S. Bluestein, for the petitioners. Homer F. Benson, for the respondent.

MULRONEY

Memorandum Findings of Fact and Opinion

MULRONEY, Judge: Respondent determined deficiencies in petitioners' income tax for the years 1958, 1959, 1960 and 1961 in the respective amounts of $6,971.97, $3,490.88, *165 $108.80 and $61,332.47. The years 1958 and 1959 are involved because of the disallowance of a net operating loss carryback. Petitioner concedes the 1960 deficiency in the sum of $108.80.

The issues are (1) whether certain payments made by petitioner George A. Dozier during the course of highway construction jobs should be characterized as costs incurred by Dozier on such construction jobs or whether such payments were in fact loans made to a subcontractor, and (2) whether, under the completed-contract method of accounting, the income from a highway construction job was properly includable in petitioners' income in 1961 or 1962.

Findings of Fact

Some of the facts were stipulated and they are so found.

George A. Dozier and Dixie G. Dozier, husband and wife, are residents of Montgomery, Alabama. They filed a joint Federal income tax return for 1961 with the district director of internal revenue, Birmingham, Alabama.

Since 1946 and during the years here involved, petitioner George A. Dozier was engaged in highway construction work either as a prime contractor or as a subcontractor. He used the completed-contract method of accounting and reporting taxable income realized from*166 contracts for highway construction.

In 1948 petitioner and Jack R. Bryant began working together on road contracting jobs. Petitioner supplied the bonding power, without which the contracts could not have been obtained, and Bryant was his unbonded subcontractor who did the work with his men and equipment. In general, petitioner retained an agreed percentage of the estimate payments received as the work progressed and turned the balance over to Bryant. Petitioner did have some equipment which was used on some of the jobs.

On December 28, 1958, petitioner was awarded a contract by the Alabama State Highway Department to build 6.689 miles of Interstate Highway No. 65 in Shelby County, Alabama. On January 5, 1960, the petitioner, as prime contractor on the Shelby County project, subcontracted a portion of the project to J. R. Bryant (doing business as J. R. Bryant Contracting Co.) to the extent of $2,382,850.46 and also subcontracted a portion of the project to Montgomery Construction Company to the extent of $186,085.23. The subcontract with Bryant provided, in part, as follows:

Article XIII(a) Should Sub-contractor at any time breach this agreement or fail to prosecute the said*167 work with promptness, diligence and efficiency, or fail to perform any of the requirements hereof, Contractor may without notice (or, if notice be required by law, then after twenty-four hours written notice either by registered mail addressed to Sub-contractor at 1103 Bell Building, Montgomery, Alabama or by posting in some conspicuous pace on the job) proceed as follows:

1. Provide such materials, supplies, equipment and labor as may be necessary to complete said work, pay for same and deduct the amount so paid from any money then or thereafter due Sub-contractor, or

2. Terminate the employment of Subcontractor, enter upon the premises and take possession, for use in completing the work, of all the materials, supplies, tools, equipment and appliances of the Subcontractor thereon and complete the work, or have same completed by others, and be liable to Sub-contractor for no further payment under the agreement until final payment is due and then only if and to the extent that the unpaid balance of the amount to be paid under this Sub-contract exceeds the expense of the Contractor in finishing the work.

(b) If the amount expended by Contractor under 1, above or the cost of completing*168 the work under 2, above exceeds the unpaid balance of Sub-contract price herein stated, Sub-contractor shall pay Contractor such excess.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

V & M Homes, Inc. v. Commissioner
28 T.C. 1121 (U.S. Tax Court, 1957)

Cite This Page — Counsel Stack

Bluebook (online)
1967 T.C. Memo. 97, 26 T.C.M. 467, 1967 Tax Ct. Memo LEXIS 163, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dozier-v-commissioner-tax-1967.