Doyle v. Fluor Corp.

400 S.W.3d 316, 2013 WL 150807, 2013 Mo. App. LEXIS 64
CourtMissouri Court of Appeals
DecidedJanuary 15, 2013
DocketNo. ED 98462
StatusPublished
Cited by3 cases

This text of 400 S.W.3d 316 (Doyle v. Fluor Corp.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Doyle v. Fluor Corp., 400 S.W.3d 316, 2013 WL 150807, 2013 Mo. App. LEXIS 64 (Mo. Ct. App. 2013).

Opinion

OPINION

CLIFFORD H. AHRENS, Presiding Judge.

Appellants appeal the trial court’s judgment approving a class action settlement in favor of Herculaneum residents whose real property was affected by the Doe Run lead smelter. We affirm.

Background

Appellants are 28 objectors in a class of over 700 Plaintiffs (collectively, the Class) who suffered nuisance and damage to their real property as a result of toxins emitted from Doe Run. The Class is represented by six named Plaintiffs (the Representa-fives). Defendants are entities and executives associated with the smelter.

The Doe Run smelter was established in 1892 and came under environmental scrutiny in the 1980s due to elevated levels of lead in the soil of residential neighborhoods near the facility. As relevant here, soil remediation (iereplacement) began in 1991 and accelerated beginning in 2001 pursuant to a consent decree between Defendants and the Environmental Protection Agency. By 2007, 524 properties in Herculaneum had been remediated. Concurrent with remediation, in 2002 Defendants agreed, in cooperation with the Missouri Department of Natural Resources, to offer to purchase all of the residential properties within approximately three-eighths of a mile of the smelter. Properties in the buy-out zone had been remedi-ated first, as they were closest to the smelter, and to date nearly all properties in Herculaneum have been remediated except for “a few” at the outskirts. Twenty-. four of the 28 Appellants are former property owners who sold their property to Defendants under the purchase program. The remaining four are current owners still residing in Herculaneum.

From the protracted procedural history of this case, highlights relevant to the issues on appeal here can be summarized as follows. The Representatives filed their petition July 9, 2001. At the time, all six Representatives owned real property in the area affected by Doe Run. In 2005, the Class was certified to include “all persons who own residential real property” in a defined geographic area of Herculaneum. The Class contained two sub-classes: owners whose property had been remediated and owners whose property had not been remediated. In 2006, two of the Representatives sold their property and moved. In February 2010, in its order approving notice to the Class, the trial court clarified [320]*320that the Class included not only current owners but also previous owners back to the date of the petition. In anticipation of an appeal of that order, the notice form in the court file was left blank where the opt-out date was to be indicated. Indeed, the order was appealed and ultimately upheld. State ex rel. Doe Run v. Van Amburg, ED 94282 (Mo.App. E.D. March 12, 2010). Notice was achieved by publication and by direct mail, posted March 23, 2010, to all Class members. That notice described the lawsuit, identified the Class and its Representatives, summarized Class members’ rights, explained members’ participation options, and provided instructions for opting out of the action. The direct mail notice specified an opt-out deadline of May 4, 2010, but the published notice did not specify a date. Three individuals opted out of the suit.

In February 2012, after over a decade of litigation, Representatives and Defendants (together here, Respondents) reached a settlement agreement whereby, in consideration for the Plaintiffs’ release of all property-related claims,1 Defendants would disburse $55 million, to be distributed to the Class pursuant to an allocation plan. Under that plan, after attorney fees and other set-asides,2 two-thirds of the fund was designated as nuisance compensation allocated to both past and present owners, calculated by function of their duration of ownership. The remaining one-third was allocated to current owners only, calculated in terms of the remediable surface area of their property.3 Each Representative submitted an affidavit to the trial court expressing approval of the settlement agreement and allocation plan and specifically confirming their belief that the arrangement was fair and in the best interests of the Class.

A month later, on the eve of judicial approval of the settlement — two years after notice of the action and 22 months after the opt-out deadline — Appellants4 moved to intervene and objected to the entire transaction, claiming that notice was inadequate and the allocation plan unfair. All parties appeared before the trial court for the final approval hearing March 15, 2012. In addition to evidence supporting approval of the settlement, the trial court also heard arguments on Appellants’ motions and objections. Ultimately, the trial court approved the settlement agreement and allocation plan over Appellants’ objections, and this appeal followed. Appellants claim that they were denied adequate notice of the action, specific representation of their interests, and meaningful discovery on the environmental rationale for the allocation plan. Additional facts are presented below as relevant to the particular issues.

I. Class Representation

For their first point,5 Appellants assert that the settlement is not “fair, [321]*321reasonable, and adequate” because the Representatives did not sufficiently represent the interests of the whole Class. As a threshold matter, Respondents counter that Appellants’ point is untimely because, despite their longstanding knowledge of the Representatives, they didn’t raise this issue until after the final approval hearing in March 2012. Appellants do not allege that they failed to receive notice of the action in 2010 (including identification of the Representatives and the Class); none of them elected to opt out at that time; and the record suggests that Appellants’ counsel was well aware of this case throughout its evolution.6 Yet Appellants never challenged the adequacy of representation at any time prior to 2012, or in the written objections accompanying their motion to intervene filed in February of that year, or in oral arguments thereon before the trial court on March 15. Rather, Appellants raise this issue for the first time in their post-hearing pleadings. Missouri law is clear that an appellate court will not convict a trial court of error on an issue that was not put before it to decide. Sheedy v. Missouri Highways and Transp. Com’n., 180 S.W.3d 66, 71 (Mo.App.2005). More specific to class repre sentation, while our research uncovered no Missouri case on point, Respondents offer well-reasoned authority from other jurisdictions holding that belated objections are deemed waived. See Joel A. v. Giuliani, 218 F.3d 132 (2nd Cir.2000) (objectors challenging adequacy of representation should have done so at time of certification); In re Cendant Corp. Litigation, 264 F.3d 201 (3rd Cir.2001) (objectors’ challenge to adequacy of representation, raised at settlement approval stage, was untimely and hence waived). Given the factual and procedural history of this case spanning over a decade, Appellants’ tardiness is unjustified and their point is untimely.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fallon R. Nestle v. Brandon E. Johns
452 S.W.3d 753 (Missouri Court of Appeals, 2015)
Patrick Blanks v. Fluor Corporation
450 S.W.3d 308 (Missouri Court of Appeals, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
400 S.W.3d 316, 2013 WL 150807, 2013 Mo. App. LEXIS 64, Counsel Stack Legal Research, https://law.counselstack.com/opinion/doyle-v-fluor-corp-moctapp-2013.