Doyle v. District Council No. 4 of Buffalo & Vicinity

105 F. Supp. 94, 30 L.R.R.M. (BNA) 2545, 1952 U.S. Dist. LEXIS 4621
CourtDistrict Court, W.D. New York
DecidedMay 19, 1952
DocketCiv. A. No. 4728
StatusPublished

This text of 105 F. Supp. 94 (Doyle v. District Council No. 4 of Buffalo & Vicinity) is published on Counsel Stack Legal Research, covering District Court, W.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Doyle v. District Council No. 4 of Buffalo & Vicinity, 105 F. Supp. 94, 30 L.R.R.M. (BNA) 2545, 1952 U.S. Dist. LEXIS 4621 (W.D.N.Y. 1952).

Opinion

KNIGHT, Chief Judge.

This is a motion for summary judgment in favor of the defendants. The notice of motion, returnable March 17, 1952, states “the plaintiff (sic) will move this Court for a summary judgment in favor of the defendants in the above entitled matter pursuant to the Rules of Civil Procedure”’ and such other relief as may be proper.

From the affidavits and the oral argument on this motion, the salient facts appear to be that plaintiff and the general [95]*95contractor entered into an agreement on December 12, 1947, under which plaintiff was to do .the painting of the Veterans’ Hospital at Buffalo, New York. Before entering into the agreement plaintiff claims to have had a confirmation by defendants that the rate of wages for painters on that job would be $1,871/4 an hour until and unless the government should issue a change order to take care of any increase in wages. The agreement between the Union Painting & Decorating Contractors of Buffalo, of which plaintiff was a party, and District Council No. 4 of Buffalo and Vicinity, Brotherhood of P’ainters, Decorators and Paperhangers of America, ■ among other things, contained provisions with respect to employment relating .to conditions, 'hours, wages and arbitration.

Between December 12, 1947, and the date when the general contractor requested plaintiff in December, 1948, to commence painting under the contract with plaintiff, the prevailing wage rate for local painters had been increased twenty-five cents an hour. The attitude of the Union members toward this hospital job was claimed to be such that plaintiff, on December 29, 1948, addressed a letter to Alford J. Farley, Secretary-Treasurer of District Council #4, as follows:

“December 29, 1948
“Mr. Alford J. Farley
Secretary & Treasurer, District Council #4
78 Philadelphia Street Buffalo 7, New York
Re: Joint Trade Board
“Dear Mr. Farley:
“In keeping with Article XI-Section 1 of our Working Agreement, we hereby appeal to your board to avoid a threatened dispute due to a direct violation of Article XII-Section F by the District Council.
“The District Council has allowed the posting of a sign at the ‘Day Room’ advising members of the Union to ‘Stay away’ from the E. J. Doyle Painting ■Company’s Veterans’ Hospital Job, as the job is a $1.87^4 hourly rate job.
“We are ready, willing and able to prove to the Joint Trade Board that the prevailing rate of wage established by law for Painters, to be used on the V eterans’ Administration Hospital, Buffalo, New York as determined by the Secretary of Labor, is $1.87j4 per hour.
“As we anticipate starting this job on January 3, 1949, we would like an immediate decision from the Joint Trade Board relative to the wages to be paid on the job.
“Very truly yours,
“E. J. Doyle Painting Company
“E. j. Doyle
“E. J. Doyle, President”

Following the request of the plaintiff the ' matter was thereupon submitted to 'the Joint Trade Board. Such Board is described in Article XI, §§ 1-6 of the agreement between the contractors arid the painters union above referred to, and its membership, purpose, conduct and powers are set down in detail. As to the matter so submitted, the Board found that the complaint by plaintiff was premature as there had been no work stoppage.

On January 25, 1949, after plaintiff claimed defendant had again breached the contract of employment, plaintiff wrote Alford J. Farley another letter as follows:

“January 25, 1949
“Alford J. Farley, Secretary
District Council #4
78 Philadelphia Street Buffalo 7, New York
“Dear Mr. Farley:
“This letter is in confirmation of our telephone conversation requesting a meeting of the Trade Board, as set up in our working agreement, for 8:00 P.M. Wednesday, January 26, 1949 at the Hotel Lafayette, Buffalo, New York.
“Very truly yours
“E. J. Doyle
“E. J. Doyle, Secretary
“U.P.D.C.B.”

Another meeting of the Joint Trade Board was thereby induced by plaintiff, which meeting was held January 26, 1949, pursuant to plaintiff’s request, to consider the matter then submitted by plaintiff. At the time plaintiff presented his matter to [96]*96the Board and while it was being considered by the Board, but prior to the formal determination of the matter by the Board, plaintiff withdrew his claim of breach by the defendants of the alleged employment agreement. The parties to this action, as a result of the Board meeting of January 26, 1949, then entered into a “Supplemental Agreement” dated January 27, 1949, which was stated therein to be “Amendatory and supplemental to a certain agreement * * made .as of the first day of May, 1948 (dated June 7, 1948; effective May 1, 1948) * * * which said agreement shall remain in full force and effect except as the same may be inconsistent with or modified and amended by this supplemental agreement.” This supplemental agreement was to remain in force until the painting of the Veterans’ Hospital should be completed. It also provided for the straight time hourly rate of $1.8714 to continue during the regular hours from 8 A.M. to 12 noon, and from 12:30 P.M. to 3:30 P.M., Monday through Friday, and double time for the 8th hour of work on those days and 121/2 cents for carfare and incidentals, making a total pay of $17 per day. Provision was also made in the supplemental agreement for compliance with the bid-contract for spraying lacquer and paint, for the hiring and discharging of painters and further provided against strikes, lockouts, slowdown, stoppage and other interference by any of the .parties pending the completion of the painting.

After the making of the supplemental agreement, prepared by plaintiff’s counsel, dated January 27, 1949, all went well and the painting was completed. The contract between the plaintiff and the general contractor appears to have been performed and completed on or about December 19, 1949.

Plaintiff, relying on the futility of the supplemental agreement, commenced this action by the service of the summons and complaint on November 17, 1950. 'Issue was joined by the.service of the answer on January 22, 1951. Except that the defendants admit being labor organizations under the Labor Management Relations Act of 1947, 29 U.S.C.A. § 141 et seq., having their principal places of business at Buffalo, New York, and that the plaintiff is a resident of Buffalo, New York, all of the allegations of the complaint are challenged. The answer further alleges thirteen affirmative defenses.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack