Downtown Texarkana, LLC v. Graylee Construction and Demolition, LLC; And City of Texarkana, Arkansas

2026 Ark. App. 75
CourtCourt of Appeals of Arkansas
DecidedFebruary 4, 2026
StatusPublished

This text of 2026 Ark. App. 75 (Downtown Texarkana, LLC v. Graylee Construction and Demolition, LLC; And City of Texarkana, Arkansas) is published on Counsel Stack Legal Research, covering Court of Appeals of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Downtown Texarkana, LLC v. Graylee Construction and Demolition, LLC; And City of Texarkana, Arkansas, 2026 Ark. App. 75 (Ark. Ct. App. 2026).

Opinion

Cite as 2026 Ark. App. 75 ARKANSAS COURT OF APPEALS DIVISION III No. CV-24-378

DOWNTOWN TEXARKANA, LLC Opinion Delivered February 4, 2026 APPELLANT APPEAL FROM THE MILLER COUNTY CIRCUIT COURT V. [NO. 46CV-20-403]

GRAYLEE CONSTRUCTION AND HONORABLE ROBERT BYNUM DEMOLITION, LLC; AND CITY OF GIBSON, JR., JUDGE TEXARKANA, ARKANSAS APPELLEES AFFIRMED

WAYMOND M. BROWN, Judge

Appellant Downtown Texarkana, LLC, appeals the January 13, 2024 judgment of the

Miller County Circuit Court in favor of appellee City of Texarkana (City) in the amount of

$223,000.1 The circuit court also granted appellant $35,000 in attorney’s fees for a total

judgment against the City in the amount of $258,000.2 Appellant argues on appeal that the

circuit court (1) erred by utilizing the wrong measure of damages for this contract case; (2)

erred in failing to direct a verdict as to damages for demolition and removal of debris; (3)

1 The circuit court awarded appellant $45,000 for the fair market value of appellant’s building destroyed by appellee Graylee Construction and Demolition, LLC (Graylee), and $178,000 for demolition costs. 2 The City had an agreement with Graylee whereby Graylee would indemnify the City. Graylee also was ordered to pay the City $26,073.10 in attorney’s fees. erred in refusing to award prejudgment interest from the date of the total loss to the date of

judgment; (4) abused its discretion in refusing to award the attorney’s fee provided for in the

contingent-fee contract between appellant and its attorney and thus failed to award appellant

a full damages award; (5) erred in refusing to award court costs to appellant as the prevailing

party; and (6) erred in failing to award the correct postjudgment interest rate upon the entire

judgment from the date of judgment entry until paid to appellant. We affirm.3

The City condemned Regency House, a four-story building taking up two lots at 110

East Broad Street in Texarkana, as a public hazard. The City contracted with Graylee on

May 26, 2020, to perform the demolition work for $310,000,4 and it entered an indemnity

contract with Graylee for any damage resulting from the demolition. The City also obtained

a temporary-working easement from appellant, the owner of a two-story building located on

a lot at 114 East Broad Street, allowing the City and its contractors to enter the property to

perform the demolition. The easement stated that appellees would provide “roof protection

to the building at 114 E. Broad St., parapet repairs, and repairs of any damage suffered to

114 E. Broad during construction activities.” It further stated that “[t]he City, in connection

with construction of the proposed improvements, shall restore Grantor’s property to a

condition substantially similar to its condition prior to construction[.]” Graylee started work

shortly after executing the contract. On June 30, a portion of Regency House’s wall collapsed

3 This appeal was orally argued before this court on January 14, 2026. 4 This amount was only for the demolition; it did not include haul off. The City stated that it expected to spend another $100,000 for disposal.

2 onto the roof of appellant’s building, causing a total loss. The City subsequently condemned

appellant’s building as unrepairable and as a health and safety hazard. The City paid Graylee

$176,272.50 for work already performed on Regency House and subsequently canceled its

contract with Graylee. After appellant’s efforts to resolve the problem with the City and

Graylee failed, it filed a complaint against them on November 12, 2020, seeking damages for

the loss of the building as well as demolition costs.

A jury trial took place on October 12–14, 2023. The circuit court directed a verdict

in appellant’s favor against the City on the issue of liability and allowed the issue of damages

to be submitted to the jury. The circuit court also directed a verdict in Graylee’s favor in

appellant’s action against it. The evidence adduced at trial showed that appellant had

purchased the property in question for $15,000 in August 2015. The property was last

assessed by the Miller County Assessor for $45,000 before the damage.5 At some point,

appellant listed the property for sale for $125,000, but it did not sell. Graylee described the

property as being in bad condition6 before its collapse. Graylee walked through appellant’s

property to get an idea of the condition of Regency House because Graylee was not allowed

inside Regency House due to safety issues. After litigation had begun, appellant had a hard

5 Appellant proffered an architect’s report showing that a reconstruction of the collapsed building would cost approximately $4,069,735 (rate of $387.59 per square foot). 6 Upstairs, there was a crack in the wall at least six feet long, the floors were spongy, the walls were unfinished, and the roof had exposed rafters. Downstairs, there were exposed wires, some drywall had been installed, and there were plumbing issues. There were no utilities at the property.

3 time finding a company willing to take on the demolition project. Appellant entered into a

contract with Stan Excavating in April 2021 for demolition and removal for $401,938. Stan

Excavating understood that appellant did not have the money at that time to pay for the

work; however, appellant was to pay Stan Excavating with money received from its claims

against appellees. At the time of the trial, Stan Excavating had completed the work for

appellant. The City also contracted with Stan Excavating in early 2023 and paid $453,000

to complete the Regency House demolition and disposal. In the end, the City spent a total

of $629,272.50 for the Regency House demolition and disposal. After being presented with

this evidence,7 the jury returned a verdict for appellant in the amount of $178,000 for

demolition. The jury also awarded appellant $45,000 for the loss of its building. Appellant

filed a timely notice of appeal as well as posttrial motions, which were either outright denied

or denied by operation of law. This timely appeal followed.

Appellant argues as its first point on appeal that the circuit court erred by utilizing

the wrong measure of damages for this contract case when it instructed the jury. A party is

entitled to a jury instruction when it is a correct statement of the law, and there is some basis

in the evidence to support giving the instruction. 8 We review the circuit court’s failure to

give a specific instruction under an abuse-of-discretion standard.9 Abuse of discretion is a

7 The jury also viewed in person the vacant lots where Regency House and appellant’s building once stood.

8 Old Dominion Freight Line, Inc. v. McMillion, 2025 Ark. App. 400, 715 S.W.3d 490.

9 See id.

4 high threshold that does not simply require error in the circuit court’s decision but requires

that the court act improvidently, thoughtlessly, or without due consideration. 10 The circuit

court granted Graylee’s motion in limine to prevent appellant from presenting evidence

reflecting the cost of new construction; however, appellant was allowed to proffer the report

by architect W. Mark Bailey reflecting that the cost to reconstruct appellant’s collapsed

building would be $4,069,735. At the conclusion of the evidence, the circuit court

instructed the jury that it should grant appellant the fair market value of its building at the

time of the accident. Appellant argues that this was erroneous. We disagree. Arkansas

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Reynolds Health Care Services, Inc. v. HMNH, Inc.
217 S.W.3d 797 (Supreme Court of Arkansas, 2005)
Barnes v. Young
382 S.W.2d 580 (Supreme Court of Arkansas, 1964)
Daniel v. Arkansas Department of Human Services
2017 Ark. 206 (Supreme Court of Arkansas, 2017)
Mitchell v. Fells
376 S.W.3d 543 (Court of Appeals of Arkansas, 2010)
Missouri Pacific Railroad v. Clements
281 S.W.2d 936 (Supreme Court of Arkansas, 1955)
King v. Barton
2023 Ark. App. 388 (Court of Appeals of Arkansas, 2023)
Vivek Dicholkar v. Blake McMillon
2024 Ark. App. 155 (Court of Appeals of Arkansas, 2024)
Crain v. Crain
2025 Ark. App. 122 (Court of Appeals of Arkansas, 2025)

Cite This Page — Counsel Stack

Bluebook (online)
2026 Ark. App. 75, Counsel Stack Legal Research, https://law.counselstack.com/opinion/downtown-texarkana-llc-v-graylee-construction-and-demolition-llc-and-arkctapp-2026.