Dowling v. John P. Cruz Construction Co.

21 Mass. L. Rptr. 637
CourtMassachusetts Superior Court
DecidedSeptember 22, 2006
DocketNo. SUCV200501247
StatusPublished

This text of 21 Mass. L. Rptr. 637 (Dowling v. John P. Cruz Construction Co.) is published on Counsel Stack Legal Research, covering Massachusetts Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dowling v. John P. Cruz Construction Co., 21 Mass. L. Rptr. 637 (Mass. Ct. App. 2006).

Opinion

Troy, Paul E., J.

This action arises from a private construction project on which defendant, John B. Cruz Construction Co., Inc. (“Cruz”), acted as the general contractor and plaintiff, Brendan Dowling d/b/a B. Dowling Construction Co. (“Dowling”), acted as a subcontractor. Dowling filed a complaint seeking to enforce a subcontract agreement with Cruz. Dowling has since filed an amended complaint seeking to enforce a lien bond executed by Cruz and defendant surety, Hartford Casualty Ins. Co. (“Hartford”). Hartford now moves to dismiss the amended complaint. For the reasons stated herein, the Defendant, Hartford Casualty Insurance Company’s Motion to Dismiss Plaintiffs Amended Complaint is DENIED.

BACKGROUND

On August 16, 2002, Dowling entered into a subcontract agreement with Cruz. Cruz was the general contractor on a private construction project for the building of a church on Blue Hill Avenue in Boston. Thereafter, Dowling commenced working on the contract. Dowling submitted a number of claims for change orders, which the owner did not approve. In March 2004, Dowling, asserting that it had not been paid all sums due, terminated its work on the project.

On February 9, 2004, Dowling filed a notice of contract with the Registry of Deeds in Suffolk County, thereby creating a mechanic’s lien on the project owner’s property. On May 25, 2004, Dowling filed a statement of account with the Registry. On March 31, 2005, Dowling filed a complaint seeking to enforce the lien and alleging breach of contract.

Meanwhile, on April 8,2004, Cruz and Hartford had executed a lien bond, which purportedly dissolved Dowling’s previously filed mechanic’s lien. On April 9, Cruz’s attorney sent a letter to Dowling’s attorney, Ann B. McGuigan, which notified her that the lien bond, which was enclosed, “has been filed in conformity with Chapter 254, Section 14.” On April 12, 2004, Cruz and Hartford filed the lien bond with the Registry.

On April 21, 2006, the court allowed Dowling to amend its complaint to include an action against Hartford to enforce the lien bond.

MOTION TO DISMISS STANDARD

This court may dismiss a complaint that fails “to state a claim upon which relief can be granted.” Mass.R.Civ.P. 12(b)(6). In considering a motion to dismiss, “the allegations of the complaint, as well as such inferences as may be drawn therefrom in the plaintiffs favor, are to be taken as true.” Nader v. Citron, 372 Mass. 96, 98 (1977), citing Balsavich v. Local 170, International Brotherhood of Teamsters, 371 Mass. 283 (1976). Further, “a complaint should not be dismissed for failure to state a claim unless it appears beyond doubt that the plaintiff can prove no set of facts in support of his claim which would entitle him to relief.” Nader, 372 Mass. at 98, quoting Conley v. Gibson, 355 U.S. 41, 45-46 (1957). Moreover, “a complaint is sufficient against a motion to dismiss if it appears that the plaintiff may be entitled to any form of relief, even though the particular relief he has demanded and the theory on which he seems to rely may not be appropriate.” Nader, 372 Mass. at 98, citing Janke Constr. Co. v. Vulcan Materials Co., 527 F.2d 772 (7th Cir. 1976). Therefore, a plaintiff “must prevail over the motion [to dismiss] unless it appears with certainty that he is entitled to no relief under any combination of facts that could be proved in support of his claims.” Brum v. Town of Dartmouth, 44 Mass.App.Ct. 318, 322 (1998), citing Flattery v. Gregory, 397 Mass. 143, 145-46 (1986). The court is “not to consider the unlikelihood of the plaintiffs ability to produce evidence to support otherwise legally sufficient complaint allegations.” Brum, 44 Mass.App.Ct. at 322, citing Mmoe v. Commonwealth, 393 Mass. 617, 619-20 (1985).

DISCUSSION

Upon the filing of Cruz and Hartford’s lien bond, Dowling’s Mechanic’s Lien dissolved. G.L.c. 254, §14. Accordingly, Dowling may not seek enforcement of the mechanic’s lien, but may only seek relief against Cruz and/or Hartford pursuant to the lien bond. In order to enforce the lien bond against Hartford, Dowling had to file its complaint seeking enforcement “within ninety days after the later of the filing of the [statement of account] or receipt of notice of recording of the bond.” G.L.c. 254, §14. Hartford alleges that Dowling received notice of the lien bond when its attorney received the April 9, 2004 letter from Cruz’s attorney. On May 25, 2004, Dowling filed its statement of account. The amended complaint relates back to the date the original complaint was filed.2 Mass.R.Civ.P. 15(c). Dowling challenges the defendants’ assertion that he received notice as required under the applicable statute, G.L.c. 254, §14.

Dowling raises “three problems” with the alleged notice provided by the April 9, 2004 letter: (1) the letter should not even be considered by the court at this procedural stage as it constitutes “extraneous materials” supporting a motion to dismiss; (2) the letter did not provide notice to the “claimant,” Dowling, as re[639]*639quired by G.L.c. 254, §14; and (3) the letter cannot provide “notice of the recording,” as required by G.L.c. 254, §14, because the letter was mailed three days before the lien bond was actually recorded. Even if the court reviews the “extraneous materials” and further assumes that the April 9 letter substantively constitutes a proper “notice of the recording,” the defendants’ failure to notify the claimant, Dowling, of the lien bond, mandates the denial of Hartford’s motion. The Court need not address the first and third issues raised by Dowling, as Section Fourteen requires that “(n)otice of the recording shall be given to the claimant by serving on the claimant a copy of the notice of recording together with a copy of the bond by an officer qualified to serve civil process or by delivering same to the claimant."

Here, notice of the recording3 and a copy of the bond were delivered to the attorney for the claimant, but were not delivered directly to the claimant. Although Hartford is seeking to employ a time limitations defense related to a lien bond, the requirement of strict compliance with the mechanic’s lien statute still applies, as the lien bond is also a creation of the statute. See e.g. Golden v. General Builders Supply LLC, 441 Mass. 652, 654-55 (2004) (requiring strict compliance with statutorily created mechanic’s lien in order to “create, perfect, and enforce such a lien”); see also Mullen Lumber Co. v. Lore, 404 Mass. 750, 752 (1989). A plain reading of the statute necessitates that notice be provided directly to the claimant and not merely a representative of the claimant, such as his attorney. See Schulman v. Attorney General, 447 Mass. 189, 191 (2006) (describing plain meaning of statutory language as the “principle source of insight into legislative purpose”); see also Phillips v. Pembroke Real Estate, Inc., 443 Mass. 110, 114 (2004) (interpreting statute by applying “the ordinary and approved usage of the language”).

The legislature’s use of the phrase “serving on the claimant” adds context to the requirement of delivering notice. G.L.c. 254, §14. Proper service is administered in this Commonwealth by serving the individual defendant, or an officer or agent of a defendant corporation. Mass.R.Civ.P.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Conley v. Gibson
355 U.S. 41 (Supreme Court, 1957)
Mmoe v. Commonwealth
473 N.E.2d 169 (Massachusetts Supreme Judicial Court, 1985)
Mullen Lumber Co. v. Lore
537 N.E.2d 123 (Massachusetts Supreme Judicial Court, 1989)
Flattery v. Gregory
489 N.E.2d 1257 (Massachusetts Supreme Judicial Court, 1986)
Nader v. Citron
360 N.E.2d 870 (Massachusetts Supreme Judicial Court, 1977)
Rosenblum v. Ginis
9 N.E.2d 525 (Massachusetts Supreme Judicial Court, 1937)
Balsavich v. Local Union 170 of the International Brotherhood of Teamsters
356 N.E.2d 1217 (Massachusetts Supreme Judicial Court, 1976)
Golden v. General Builders Supply LLC
807 N.E.2d 822 (Massachusetts Supreme Judicial Court, 2004)
Phillips v. Pembroke Real Estate, Inc.
819 N.E.2d 579 (Massachusetts Supreme Judicial Court, 2004)
Schulman v. Attorney General
447 Mass. 189 (Massachusetts Supreme Judicial Court, 2006)
Brum v. Town of Dartmouth
44 Mass. App. Ct. 318 (Massachusetts Appeals Court, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
21 Mass. L. Rptr. 637, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dowling-v-john-p-cruz-construction-co-masssuperct-2006.