Dover Watch Timeshare Project

CourtVermont Superior Court
DecidedApril 29, 2007
Docket103-05-06 Vtec
StatusPublished

This text of Dover Watch Timeshare Project (Dover Watch Timeshare Project) is published on Counsel Stack Legal Research, covering Vermont Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dover Watch Timeshare Project, (Vt. Ct. App. 2007).

Opinion

STATE OF VERMONT

ENVIRONMENTAL COURT

} In re: Dover Watch Timeshare Project } Docket No. 103-5-06 Vtec (Appeal of Dover Watch Owners Association) } }

Decision and Order on Cross-Motions for Summary Judgment

Appellant Dover Watch Owners Association, Inc., (Appellant Association) appealed

from a decision of the Development Review Board (DRB) of the Town of Dover dated April

20, 2006, upholding the Zoning Administrator’s decision that a municipal zoning permit

is required for the work Appellant Association wishes to complete on the time share

(interval ownership) project known as Dover Watch. Appellant Association, involving

more than 300 purchasers of time shares in the project, is represented by Eric J. Anderson,

Esq.; the Town is represented by Joseph S. McLean, Esq.

Both parties have moved for summary judgment. The following facts are

undisputed1 unless otherwise noted.

Appellant Association seeks to complete construction on one partially-completed

building and to construct additional2 four-unit buildings in a time share (interval

1 It has been unduly difficult for the Court to determine the present scope of the project itself, as well as to determine the scope of the project that had been approved as of the adoption of zoning in Dover in 1988, because the parties have provided only the most recent of the many Act 250 permits or permit amendments applicable to this project, and have provided none of the permit applications. The one Act 250 permit decision supplied by the parties, the District 2 Environmental Commission’s Memorandum of Decision in #2W0543-R1N(Altered), issued on January 5, 2006, attached to the parties’ Stipulated Facts as Exhibit D, assumes knowledge of the prior history of the permit and the underlying facts not provided to this Court. 2 The Court cannot determine from the materials supplied whether Appellant Association wishes to construct a total of 52 units in 13 four-unit residential buildings,

1 ownership) project now known as Dover Watch, on property located northerly of Country

Club Road in West Dover. The project was started by Appellant Association’s predecessor-

in-interest, Eugene Ettlinger, and/or by corporations in which he had an interest. It appears

that Appellant Dover Watch Owners Association is in continued litigation3 with one of

those corporations,“Dover Watch at Mt. Snow, Ltd.,” over ownership of all or part of the

project property.

The parties have not provided any of the Act 2504 decisions or permits applicable

to the property other than the most recent one issued in January 2006, ruling on a motion

to alter regarding the scope of the –R1N decision which had been issued in November of

2005. Accordingly, any of the permit history of this project as described in this decision

derives from that decision or from the one Environmental Board decision on the project5

available from the Natural Resources Board website.

Mr. Eugene Ettlinger first applied to the District Commission in early 1982 for an Act

250 permit to construct 96 two-bedroom residential units on 16.2 acres of land. After test

wells had been dug on an adjacent 53.8-acre parcel, which were planned to provide a water

including the existing buildings, or to construct a total of 88 units in 22 four-unit residential buildings, including the existing buildings, nor which non-residential buildings (such as a pool building and an administration building) are included in Appellant Association’s concept of the project. 3 The Court recognizes the parties’ frustration stemming from the delays in the Dover Watch time share project that may be related to this litigation; however, all that is before this Court in this appeal is the municipal zoning status of the project. 4 The Act 250 permit status of the project is relevant to the provisions of the Zoning Bylaw related to whether and when a project may be grandfathered. 5 In re: Eugene Ettlinger (Tara Interval), Land Use Permit #2W0543-EB, Findings of Fact, Concl. of Law and Order (Vt. Envtl. Bd., Dec. 8, 1982), available at http://www.nrb.state.vt.us/lup/decisions.htm

2 supply for the proposed project, a Vermont corporation controlled by Mr. Ettlinger

(Environmental Consultants, Inc.) purchased the adjacent 53.8-acre parcel. However,

neither the public notice of the Act 250 permit proceedings nor the permit application was

amended to include the additional involved land. In September of 1982, the District

Commission issued Act 250 Permit #2W0543 to Mr. Ettlinger to construct the 52 two-

bedroom units in 13 buildings, and gave “conceptual” approval for the entire project,

described as 88 two-bedroom units in 22 buildings. However, due to the lack of notice of

the additional 53.8-acre parcel of “involved land,” a neighboring landowner appealed to

the Environmental Board, which vacated the permit and remanded the application due to

that lack of notice.

Thus, the first valid Act 250 Permit for the project was #2W0543–R1, issued by the

District Commission in early 1983 (the 1983 Act 250 Permit) for the construction of 13 four-

unit buildings containing 52 two-bedroom units, as well as the conversion of what seems

to have been an existing 40' by 40' building on the property for use as an “administration

building.” The parties have not supplied sufficient information to determine whether this

original Act 250 Permit contemplated the buildings on a 16.2-acre parcel, with some

provision for water supply on the adjacent parcel of involved land, or whether the project

property ever merged to consist of a 70-acre parcel of land. Nor can the Court determine

from the documents that have been supplied whether the 1983 Act 250 Permit discussed

“conceptual” approval for any additional buildings beyond the initial thirteen.

By some time in the 1980s, three of the thirteen four-unit buildings authorized by

Act 250 Permit #2W0543–R1 were completed. The parties have not provided any of the

applications to or decisions of the District Commission prior to the –R1N decision issued

in January of 2006; that decision outlines the permitting history of the project as it pertained

to the issues in the then-motion to alter, and does not mention the –R1B, –R1C, –R1D,

–R1G, or –R1I amendments. However, it appears from the description of the Act 250

3 permitting history in that decision that on November 10, 1988, the –R1E Act 250 Permit

extended the construction completion date to October 1, 1990 for the entire project, the last

extension decision that addressed the entire project as originally permitted. On May 31,

1988,6 the – R1F Act 250 Permit first approved the construction of the pool building; it was

to be completed by October 15, 1989.

When the project obtained the 1983 Act 250 Permit, the Town of Dover had not yet

adopted a zoning bylaw. It may have adopted an interim bylaw in April7 of 1988; in any

event it adopted a zoning bylaw effective on November 8, 1988 (the 1998 Zoning Bylaw8).

The project property appears to be located9 in the Valley Walls (District C) zoning district.

In this district, under the 1988 Zoning Bylaw, a multiple-unit residential project was a

permitted use if applied for as a Planned Residential Development (PRD) subject to the

requirements of Article 6 of the Zoning Bylaw. §330. However, for any Planned

Residential Development, §620(B) limited its overall density to the number of residential

units that would be permitted if the land were subdivided into lots in accordance with the

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Jolley Associates
2006 VT 132 (Supreme Court of Vermont, 2006)
In Re Appeal of Taft Corners Associates, Inc.
758 A.2d 804 (Supreme Court of Vermont, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
Dover Watch Timeshare Project, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dover-watch-timeshare-project-vtsuperct-2007.