Douglas H. Wheelock and Starscape Holdings, LLC v. Trim Electric, Inc

CourtCourt of Appeals of Texas
DecidedJune 25, 2013
Docket01-12-00475-CV
StatusPublished

This text of Douglas H. Wheelock and Starscape Holdings, LLC v. Trim Electric, Inc (Douglas H. Wheelock and Starscape Holdings, LLC v. Trim Electric, Inc) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Douglas H. Wheelock and Starscape Holdings, LLC v. Trim Electric, Inc, (Tex. Ct. App. 2013).

Opinion

Opinion issued June 25, 2013.

In The

Court of Appeals For The

First District of Texas ———————————— NO. 01-12-00475-CV ——————————— DOUGLAS H. WHEELOCK AND STARSCAPE HOLDINGS, LLC, Appellants V. TRIM ELECTRIC, INC, Appellee

On Appeal from the 215th District Court Harris County, Texas Trial Court Case No. 2010-39973

MEMORANDUM OPINION

In this appeal from a bench trial arising out of a construction dispute,

Douglas H. Wheelock and Starscape Holdings, LLC challenge the legal and factual

sufficiency of the evidence supporting the trial court’s judgment against them and

in favor of Trim Electric, Inc. We affirm. Background

David and Kim Swartz hired Trim to do electrical work for the opening of a

wine bar and a cocktail bar in an area of downtown Houston known as “The

Pavillions.” Wheelock, who is Starscape’s principal member, invested in the bars.

The project fell apart when Swartz defaulted on the lease with The Pavillions.

Because it had not been paid for $47,093.68 in electrical improvements at the time

Swartz defaulted, Trim filed a lien on the property.

Wheelock wanted to complete the project through Starscape, but The

Pavillions would not allow Starscape to assume the property leases until Trim

released its lien. Wheelock reached an agreement with Trim’s owner, Joe Palumbo.

Palumbo agreed to release the lien if Starscape agreed to pay the amount owed to

Trim and Wheelock personally guaranteed Starscape’s obligations. Trim filed this

lawsuit when Starscape stopped making the payments due under the parties’

agreement, asserting claims for breach of contract, promissory estoppel, and

attorney’s fees. Wheelock and Starscape answered the lawsuit, and Starscape

counterclaimed for unjust enrichment and attorney’s fees on the ground that Trim

had been paid more than it was owed for the work actually performed.

Only two witnesses testified at trial: Palumbo and Wheelock. Palumbo

testified to the circumstances giving rise to Trim’s contract claim. Palumbo stated

that Wheelock delivered a written contract to Trim’s office, which Wheelock

2 represented had been signed and notarized. A few days later, Palumbo noticed that

Wheelock had signed the personal guaranty but had not signed the agreement for

Starscape. Palumbo telephoned Wheelock, who was out of the country, and

inquired how to proceed. According to Palumbo, Wheelock instructed him to take

the agreement to Alan Michael, a man whom Wheelock had previously introduced

to Palumbo as being in charge of the project, for his signature on Starscape’s

behalf. Palumbo did as instructed.

At the bench trial, Trim offered a written agreement signed by (1) Palumbo

for Trim and (2) Michael for Starscape and (3) guaranteed by Wheelock in his

individual capacity. The agreement set forth Starscape’s obligation to pay Trim

“the sum of $47,093.68 for the electrical work already performed by Trim at the

property; $1128.00 for legal expenses and $6574.00 for work that will be

completed[.]” The agreement structured the payments as follows:

• $13,000 within five days of Starscape signing a new lease with The Pavillions; and

• Twelve equal monthly installments of $3,482.97 due on the first day of the month until the entire contract amount was paid.

Palumbo testified that Starscape made an initial payment of $13,500 and three

monthly payments. Starscape did not make any further payments under the

agreement for the work already performed, though it did pay Trim for additional

work performed pursuant to purchase orders signed by Michael.

3 During his testimony, Wheelock disputed that he told Palumbo to have

Michael sign the agreement on Starscape’s behalf. According to Wheelock,

Michael was only a general contractor on the project and had no authority to bind

Starscape. And, although Wheelock acknowledged his promise that Starscape

would make Trim whole for the work performed for Swartz, he testified to

different agreement terms. Wheelock stated that he agreed to pay Trim out of the

tenant assessment money that would be released by The Pavillions upon

completion of the work at the properties. Any payments Starscape made to Trim

before the work was completed were made in good faith but were not contractually

obligated. The wine bar failed almost immediately after its opening, the tenant

assessment money was never released, and thus, according to Wheelock, Starscape

was not obligated to pay Trim any amount outstanding for the work already

performed. Starscape and Wheelock did not offer any alternative writing as

evidence of the agreement alleged by Wheelock.

After considering the evidence presented at trial and the arguments of

counsel, the trial court issued the following findings of fact and conclusions of law:

Findings of Fact

4. [Wheelock and Starscape] desired to assume the leasehold free and clear of any liens, and entered into a valid contract with Trim. The terms of the contract are that Doug Wheelock would be held personally liable for the terms of the contract and that Starscape would pay Trim the following amounts:

4 a. $47,093.68 for electrical work already performed by Trim at the property;

b. $1,128.00 for legal expenses; and

c. $6,574.00 for additional work to be performed on the properties. This work was never performed.

5. In consideration, Trim would release [its] lien on the properties upon receipt of an initial $13,000.00, as well as resume and complete the remaining electrical work.

....

8. [Wheelock and Starscape] made payments under the contract totaling $24,448.91.

10. [Trim] is due the remaining balance of $23,772.77 under the terms of the contract.

11. [Trim] is not due any more money for work performed for [Wheelock and Starscape] outside of the contract.

12. There is no evidence that [Starscape] or its principal officer [Wheelock] communicated to [Trim] that they did not authorize Alan Michael to sign the construction agreement with [Trim].

13. . . . [Wheelock and Starscape], jointly and severally, held out to [Trim] that Alan Michael was an authorized agent to sign the construction agreement with [Trim] on [Starscape’s] behalf.

14. There is sufficient evidence of [Starscape’s] and its principal officer’s [Wheelock’s] knowledge, approval, and, thus, ratification of Alan Michael’s signature on behalf of [Starscape] to the construction contract with [Trim].

5 15. . . . Alan Michael possessed actual authority and, in the alternative, apparent authority to sign the parties’ agreement on behalf of Douglas Wheelock and Starscape . . . .

16. . . . Wheelock signed a valid and enforceable unconditional guaranty to pay [Trim] for the work and materials provided on behalf of [Wheelock and Starscape] and is individually liable to [Trim] for the sums of $23,772.77 under the parties’ contract and $0 for additional work performed pursuant to change orders requested by [Wheelock and Starscape] pursuant to the parties’ contract.

Conclusions of Law

8. [Trim] has provided sufficient evidence of entitlement to recovery for claim for breach of contract.

18. The greater weight of the credible evidence establishes that [Trim] and [Starscape] agreed that Trim would perform work and valuable materials on behalf of Starscape in exchange for, and that [Wheelock], individually provided an unconditional guaranty for the payment of the sum of

a. $47,093.68 for electrical work already performed by Trim at the properties;

c.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gaines v. Kelly
235 S.W.3d 179 (Texas Supreme Court, 2007)
Material Partnerships, Inc. v. Ventura
102 S.W.3d 252 (Court of Appeals of Texas, 2003)
BMC Software Belgium, NV v. Marchand
83 S.W.3d 789 (Texas Supreme Court, 2002)
Plas-Tex, Inc. v. U.S. Steel Corp.
772 S.W.2d 442 (Texas Supreme Court, 1989)
Quality Infusion Care, Inc. v. Health Care Service Corp.
224 S.W.3d 369 (Court of Appeals of Texas, 2006)
In Re Moers
104 S.W.3d 609 (Court of Appeals of Texas, 2003)
Insurance Co. of North America v. Morris
981 S.W.2d 667 (Texas Supreme Court, 1998)
Park Creek Associates, Ltd. v. Walker
754 S.W.2d 426 (Court of Appeals of Texas, 1988)
Briggs Equipment Trust v. Harris County Appraisal District
294 S.W.3d 667 (Court of Appeals of Texas, 2009)
City of Keller v. Wilson
168 S.W.3d 802 (Texas Supreme Court, 2005)
Reliant Energy Services, Inc. v. Cotton Valley Compression, L.L.C.
336 S.W.3d 764 (Court of Appeals of Texas, 2011)
Southwestern Bell Media, Inc. v. Lyles
825 S.W.2d 488 (Court of Appeals of Texas, 1992)
Cohen v. McCutchin
565 S.W.2d 230 (Texas Supreme Court, 1978)
Cain v. Bain
709 S.W.2d 175 (Texas Supreme Court, 1986)
Expro Americas, LLC v. Sanguine Gas Exploration, LLC
351 S.W.3d 915 (Court of Appeals of Texas, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
Douglas H. Wheelock and Starscape Holdings, LLC v. Trim Electric, Inc, Counsel Stack Legal Research, https://law.counselstack.com/opinion/douglas-h-wheelock-and-starscape-holdings-llc-v-tr-texapp-2013.