Double C Contracting, Inc., Appellant/Cross-Appellee v. GBC Harbour Lights Marina, Ltd. and Harbour Lights Villas Phase One, Ltd., Appellees/Cross-Appellants

CourtCourt of Appeals of Texas
DecidedJuly 29, 2011
Docket12-10-00342-CV
StatusPublished

This text of Double C Contracting, Inc., Appellant/Cross-Appellee v. GBC Harbour Lights Marina, Ltd. and Harbour Lights Villas Phase One, Ltd., Appellees/Cross-Appellants (Double C Contracting, Inc., Appellant/Cross-Appellee v. GBC Harbour Lights Marina, Ltd. and Harbour Lights Villas Phase One, Ltd., Appellees/Cross-Appellants) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Double C Contracting, Inc., Appellant/Cross-Appellee v. GBC Harbour Lights Marina, Ltd. and Harbour Lights Villas Phase One, Ltd., Appellees/Cross-Appellants, (Tex. Ct. App. 2011).

Opinion

NO. 12-10-00342-CV

IN THE COURT OF APPEALS

TWELFTH COURT OF APPEALS DISTRICT

TYLER, TEXAS

DOUBLE C CONTRACTING, INC., § APPEAL FROM THE 392ND APPELLANT/CROSS-APPELLEE,

V. § JUDICIAL DISTRICT COURT GBC HARBOUR LIGHTS MARINA, LTD. and HARBOUR LIGHTS VILLAS PHASE ONE, LTD., APPELLEES/CROSS-APPELLANTS § HENDERSON COUNTY, TEXAS

MEMORANDUM OPINION Double C Contracting, Inc. sued GBC Harbour Lights Marina, Ltd., and Harbour Lights Villas Phase One, Ltd., (collectively Harbour Lights) for breach of contract and foreclosure of a mechanic’s and materialman’s lien. The jury found that Harbour Lights breached the contract, and the trial court rendered judgment against Harbour Lights for $31,005.30, interest, and attorney’s fees. The trial court denied Double C’s request to foreclose its mechanic’s and materialman’s lien. Double C raises one issue challenging the trial court’s denial of the foreclosure of its lien. In two cross-issues, Harbour Lights challenges the trial court’s denial of their motion for instructed verdict and the admission of evidence regarding oral agreements or course of conduct to change contract terms. We reverse and render.

BACKGROUND Harbour Lights was developing a property on Cedar Creek Lake. The development required sewer and water lines, and Harbour Lights requested that Double C submit a bid on the work. Double C informed Harbour Lights that two methods exist for the installation of sewer and water lines: (1) open cut and lay and (2) directional drilling. So long as problems do not arise with the open cut and lay method, the directional drilling method is more costly. But, when working around water, the open cut and lay method is more prone to problems, and can become even more costly than the directional drilling method. Harbour Lights contracted with Double C for the installation of the sewer and water lines and chose to have Double C use the open cut and lay method. Double C agreed to install the sewer and water lines for $143,675.50. However, the parties further agreed that Double C could charge additional amounts for additional work requirements caused by complications with completing the project. Pursuant to the contract, Double C’s work was to be “substantially completed on or before Sixty (60) working days following [Double C’s] receipt of written Notice to Proceed.” Although the contract was signed in April, Double C did not begin work on the project until July. When laying the sewer lines, Double C encountered problems, including some with water from the lake. Ultimately, Double C failed to complete the work timely because of several factors: the increased difficulty of the open cut and lay method near water, mistakes made by the engineers in charge of the project, the location of the water main, and delay in completion of the lift station for the development. On December 3, 2007, with ninety percent of the work complete and three more weeks of work to go, Harbour Lights terminated its contract with Double C. At that time, Harbour Lights had paid Double C more than $162,000.00. On December 10, 2007, Double C terminated the contract because of Harbour Lights’ failure to pay. Double C requested that Harbour Lights make final payment for Double C’s work in the amount of $31,005.30. Harbour Lights refused to pay the money Double C claimed it was owed. Harbour Lights then hired A&M Utility to finish the project. Harbour Lights paid A&M $42,000.00, and A&M finished the project in mid-January 2008. Because it still had not received payment from Harbour Lights by February 2008, Double C prepared and filed a mechanic’s and materialman’s lien. Double C then sued Harbour Lights for breach of contract, quantum meruit, and foreclosure of its mechanic’s and materialman’s lien. Harbour Lights generally denied the allegations and alleged the affirmative defenses of payment and Double C’s breach. The matter proceeded to trial. During the trial, Double C abandoned its quantum meruit claim. The jury found that Harbour Lights breached the contract, Double C did not breach the contract, and Double C was damaged in the amount of $31,005.30. By agreement, the parties submitted the issue of foreclosure of the mechanic’s and materialman’s lien to the court. The court denied the foreclosure. This appeal followed.

2 BREACH OF CONTRACT In their first cross-issue, Harbour Lights argues that the trial court should have granted their motion for instructed verdict on their affirmative defense of material breach by Double C. Harbour Lights contends that Double C breached the contract by failing to perform the water and sewer installation in sixty days as required by the contract. They argue this was a material breach because time was of the essence.

STANDARD OF REVIEW A court properly instructs a verdict if no probative evidence raises a fact issue on the material questions in the suit. Prudential Ins. Co. v. Fin. Review Servs., Inc., 29 S.W.3d 74, 77 (Tex. 2000). A defendant establishes a right to a directed verdict when a plaintiff fails to present evidence raising a fact issue essential to the plaintiff’s right of recovery or when the plaintiff admits, or the evidence conclusively establishes, a defense to the plaintiff’s cause of action. Id. Thus, an appeal from the denial of a motion for directed verdict is essentially a legal sufficiency challenge. Lochinvar Corp. v. Meyers, 930 S.W.2d 182, 187 (Tex. App.–Dallas 1996, no pet.). A directed verdict is warranted when the evidence is such that no other verdict can be rendered and the moving party is entitled, as a matter of law, to judgment. Willet v. Cole, 249 S.W.3d 585, 590 (Tex. App. – Waco 2008, no pet.). When the party who had the burden of proof at trial attacks the legal sufficiency of an adverse finding, that party must show that the evidence establishes, as a matter of law, all vital facts in support of the issue. Dow Chem. Co. v. Francis, 46 S.W.3d 237, 241 (Tex. 2001). We credit favorable evidence if a reasonable factfinder could and disregard evidence contrary to the finding unless a reasonable factfinder could not. City of Keller v. Wilson, 168 S.W.3d 802, 807 (Tex. 2005).

APPLICABLE LAW An appellate court reviews a trial court’s construction of an unambiguous contract de novo. MCI Telecomms. Corp. v. Tex. Utils. Elec. Co., 995 S.W.2d 647, 650 (Tex. 1999). In performing a de novo review, we exercise our own judgment and redetermine each legal issue. Quick v. City of Austin, 7 S.W.3d 109, 116 (Tex. 1999). When construing a written contract, courts ascertain the intent of the parties as expressed in the instrument. Nat’l Union Fire Ins. Co. of Pittsburgh, Pa. v. CBI Indus., Inc., 907 S.W.2d 517, 520 (Tex. 1995). Courts examine and consider the entire writing in an effort to harmonize and give effect to all the provisions of the contract so that none will be rendered meaningless. Coker v. Coker, 650 S.W.2d 391, 393 (Tex. 1983). If there is no ambiguity in the 3 instrument, its construction is a question of law for the court. See id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mustang Pipeline Co. v. Driver Pipeline Co.
134 S.W.3d 195 (Texas Supreme Court, 2004)
Willet v. Cole
249 S.W.3d 585 (Court of Appeals of Texas, 2008)
Coker v. Coker
650 S.W.2d 391 (Texas Supreme Court, 1983)
Dow Chemical Co. v. Francis
46 S.W.3d 237 (Texas Supreme Court, 2001)
Lochinvar Corp. v. Meyers
930 S.W.2d 182 (Court of Appeals of Texas, 1996)
Wal-Mart Stores, Inc. v. Sturges
52 S.W.3d 711 (Texas Supreme Court, 2001)
Quick v. City of Austin
7 S.W.3d 109 (Texas Supreme Court, 1999)
City of Keller v. Wilson
168 S.W.3d 802 (Texas Supreme Court, 2005)
TrueStar Petroleum Corp. v. Eagle Oil & Gas Co.
323 S.W.3d 316 (Court of Appeals of Texas, 2010)
MCI Telecommunications Corp. v. Texas Utilities Electric Co.
995 S.W.2d 647 (Texas Supreme Court, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
Double C Contracting, Inc., Appellant/Cross-Appellee v. GBC Harbour Lights Marina, Ltd. and Harbour Lights Villas Phase One, Ltd., Appellees/Cross-Appellants, Counsel Stack Legal Research, https://law.counselstack.com/opinion/double-c-contracting-inc-appellantcross-appellee-v-gbc-harbour-lights-texapp-2011.