Dorse v. Armstrong World Industries, Inc.

716 F. Supp. 589, 1989 U.S. Dist. LEXIS 8775, 1989 WL 85895
CourtDistrict Court, S.D. Florida
DecidedApril 3, 1989
Docket82-2308-Civ
StatusPublished
Cited by11 cases

This text of 716 F. Supp. 589 (Dorse v. Armstrong World Industries, Inc.) is published on Counsel Stack Legal Research, covering District Court, S.D. Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dorse v. Armstrong World Industries, Inc., 716 F. Supp. 589, 1989 U.S. Dist. LEXIS 8775, 1989 WL 85895 (S.D. Fla. 1989).

Opinion

ORDER GRANTING PLAINTIFF’S MOTION FOR SUMMARY JUDGMENT ON GOVERNMENT CONTRACTOR DEFENSE

JAMES LAWRENCE KING, Chief Judge.

The plaintiff has filed a motion for summary judgment on the government contractor defense in this asbestos case for the wrongful death of her husband. In 1984, the defendant originally moved for summary judgment on the government contractor defense. The court denied this motion and later granted the plaintiff’s motion to strike the defense. The court based this decision on the conclusion that Florida law did not recognize such a defense. Subsequently, the parties stipulated and the court entered judgment for plaintiff in the amount of $250,000.00. The defendant, however, expressly reserved the right to challenge on appeal the striking of the government contractor defense.

On appeal, the Eleventh Circuit concluded that it had jurisdiction to hear the appeal, but certified to the Florida Supreme Court the question of whether Florida recognized the defense. Dorse v. Armstrong World Industries, 798 F.2d 1372 (11th Cir.1986). The Florida Supreme Court ruled that Florida law may recognize such a defense in limited circumstances. Dorse v. Armstrong World Industries, 513 So.2d 1265 (Fla.1987). The Florida court’s decision prompted the Eleventh Circuit to vacate this court’s earlier ruling and remanded the case for further consideration of the issue presented. Dorse v. Armstrong World Industries, 837 F.2d 957 (11th Cir.1988). Following these decisions, the United States Supreme Court clarified the con *590 tours of the government contractor defense.

I.

In Boyle v. United Technologies Corp., — U.S.-, 108 S.Ct 2510, 101 L.Ed.2d 442 (1988), the Supreme Court addressed the issue of “when a contractor providing military equipment to the Federal Government can be held liable under state tort law for injury caused by a design defect.” Boyle, 108 S.Ct. at 2513. The Court recognized two necessary conditions for the displacement of state law. The predicate for preemption is that the case must concern an area of uniquely federal interest, such as procurement of equipment by the United States. After this inquiry has been satisfactorily addressed, displacement will occur only where “a ‘significant conflict’ exists between an identifiable ‘federal policy or interest and the [operation] of state law,’ or the application of state law would ‘frustrate specific objectives’ of federal legislation”. Boyle, 108 S.Ct. at 2515 (citations omitted). The Supreme Court found that the facts in Boyle presented a case involving an area of uniquely federal interest in which a significant conflict existed between federal policy and state law.

Lieutenant Boyle, a United States Marine helicopter pilot, was killed when his helicopter crashed off the coast of Virginia during a training exercise. Although he survived the impact of the crash, Lieutenant Boyle drowned. He was unable to exit through the escape hatch because water pressure prevented it from being opened. The helicopter had been designed by a private contractor pursuant to government contract specifications. The government contract specified an escape hatch that swung outward. The complaint alleged that the escape hatch was defectively designed and should have opened inward.

After deciding procurement of military equipment is an area of uniquely federal interest, the Court concluded that the state-imposed duty of care that was the asserted basis of the contractor’s liability was “precisely contrary” to the duty imposed by the government contract. Boyle, 108 S.Ct. at 2516. The Court cautioned, however, that even in clear situations in conflict, a “significant interest” of federal policy must also exist to justify replacement of state law. Id. To determine the scope of displacement, the Court adopted the test set out in McKay v. Rockwell International Corp., 704 F.2d 444 (9th Cir.1983) cert. denied, 464 U.S. 1043, 104 S.Ct. 711, 79 L.Ed.2d 175 (1984). The Court concluded that liability for design defects in military equipment cannot be imposed, pursuant to state law, when

1. the United States approved reasonably precise specifications;
2. the equipment conformed to those specifications; and
3. the supplier warned the United States about the dangers in the use of equipment that were known to the supplier but not to the United States.

Boyle, 108 S.Ct. at 2518.

II.

The parties disagree whether Boyle applies to a “failure to warn” case such as the instant asbestos case. The plaintiff submits that the McKay test and the Boyle decision are clearly limited to design defect cases. The defendant, however, contends that the decisions apply to all types of product liability cases.

The court partially agrees with both parties. On the one hand, the court agrees with the defendant that Boyle is not strictly limited to design defect cases. The government contractor defense, for example, could arise when the government prohibits a specific warning. On the other hand, the court agrees with the plaintiff that the three-part test of McKay is necessarily limited to design defect cases. The Boyle decision, however, is not rendered completely meaningless in “failure to warn” cases.

To resolve the dilemma of applying Boyle to a “failure to warn” case, Boyle’s two-pronged analysis guides the court. The first prong, that the case concern an area of uniquely federal interest, is similarly satisfied in this failure to warn case. As in Boyle's design defect case, the procure *591 ment of asbestos in World War II for naval ships is undeniably an area of uniquely federal interest.

Having satisfied this threshold requirement, the court must address the more difficult question of whether a significant conflict exists between an identifiable federal policy and the operation of state law. The Court in Boyle faced a situation where the duty under the government contract required an escape-hatch mechanism opening outward. The “precisely contrary” duty, an inward-opening hatch, existed under the state-imposed duty of care that was the asserted basis of the contractor’s liability. The contractor could not possibly comply with both its contractual obligations and the state-prescribed duty of care, so state law was necessarily displaced.

The present case, however, presents an entirely different situation. Specifically, the state-imposed duty of care that is the asserted basis of the contractor’s liability (warning of the danger) is not “precisely contrary” to the duty imposed by the government contract (the duty of manufacture and deliver cement containing asbestos).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
716 F. Supp. 589, 1989 U.S. Dist. LEXIS 8775, 1989 WL 85895, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dorse-v-armstrong-world-industries-inc-flsd-1989.