D'Orsay International Partners v. Superior Court

20 Cal. Rptr. 3d 399, 123 Cal. App. 4th 836, 2004 Cal. Daily Op. Serv. 9721, 2004 Daily Journal DAR 13279, 2004 Cal. App. LEXIS 1825
CourtCalifornia Court of Appeal
DecidedOctober 29, 2004
DocketB174411
StatusPublished
Cited by2 cases

This text of 20 Cal. Rptr. 3d 399 (D'Orsay International Partners v. Superior Court) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
D'Orsay International Partners v. Superior Court, 20 Cal. Rptr. 3d 399, 123 Cal. App. 4th 836, 2004 Cal. Daily Op. Serv. 9721, 2004 Daily Journal DAR 13279, 2004 Cal. App. LEXIS 1825 (Cal. Ct. App. 2004).

Opinion

*838 Opinion

KLEIN, P. J.

Defendant and petitioner D’Orsay International Partners (D’Orsay) seeks a writ of mandate directing respondent superior court to enter an order releasing a mechanic’s lien filed by plaintiff and real party in interest Jeffrey C. Stone doing business as Summit Builders (Summit) without requiring D’Orsay to post a release bond in lieu of the mechanic’s lien.

The trial court granted D’Orsay’s motion for release of the mechanic’s lien but conditioned the order upon the posting of a statutory bond in the amount of $1.27 million, one and a half times the amount of the lien. We conclude the trial court’s ruling was error and that it should have released the lien outright. For a mechanic’s lien to attach, there must be “actual visible work on the land or the delivery of construction materials thereto.” (Walker v. Lytton Sav. & Loan Assn. (1970) 2 Cal.3d 152, 157 [84 Cal.Rptr. 521] (hereafter, Walker).) Here, that precondition to the filing of a mechanic’s lien was not met. Therefore, we grant D’Orsay’s petition.

FACTUAL AND PROCEDURAL BACKGROUND

D’Orsay is the successor to Long Beach Plaza Associates (LBPA), a California general partnership, and the record titleholder to certain real property in Long Beach. LBPA was formed for the purpose of constructing a new 176-room hotel/retail development complex, including onsite subterranean parking (the project).

In April 2001, D’Orsay entered into an agreement with Summit, a licensed general contractor, for construction of the project. In the next two years, Summit provided approximately $850,000 in design related services, both by performing design and planning services, and by hiring design professionals.

However, construction never commenced. A prerequisite to the start of construction was the securing of adequate financing. D’Orsay attempted to obtain financing, without success. No building permit was issued for the project. No building materials were delivered to the project site. No actual visible construction or other work was conducted at the project site by Summit or by anyone else.

On May 5, 2003, Summit recorded a mechanic’s lien with the county registrar-recorder in the amount of $846,434.26 against D’Orsay’s real property.

On August 1, 2003, Summit filed suit in the superior court, alleging various causes of action including breach of contract and seeking foreclosure of its mechanic’s lien.

*839 On February 18, 2004, D’Orsay filed a motion for release of the mechanic’s lien. D’Orsay contended good cause existed for removal of the mechanic’s lien in that in order to assert a mechanic’s lien, a claimant must have made a direct, permanent contribution to a work of improvement, and because Summit never improved the subject property, as a matter of law Summit had no basis for maintaining the lien.

In opposition, Summit argued, inter alia, a lien for design services is specifically authorized under Civil Code section 3081.2, 1 and it is immaterial that design services are performed by a licensed contractor, rather than by a design professional such as an architect, engineer or land surveyor.

Summit also contended that its lien was proper irrespective of the lack of work on the ground because an owner cannot defeat a lien by refusing to go ahead with construction.

On March 16, 2004, the matter came on for hearing and was taken under submission. Later that day, the trial court issued a minute order stating “[D’Orsay’s] Motion for Release of Lien is granted upon the posting of a bond in the amount of $1,270,000.00.” The ruling does not set forth the trial court’s rationale for its decision.

On April 12, 2004, D’Orsay filed the instant petition for writ of mandate, seeking an order directing Summit’s mechanic’s lien be released outright, without requiring the posting of a bond. This court issued an order to show cause.

CONTENTIONS

D’Orsay contends contractors providing design services are not entitled to assert mechanics’ liens in the absence of actual commencement of construction and the doctrine of owner prevention of completion is not applicable.

Summit asserts it was entitled to a mechanic’s lien; no actual contribution of labor or materials to the site was necessary in order for Summit to assert a lien for various services it rendered pursuant to the contract, namely, project design and management and obtaining permits and bonds; and the statutory scheme authorizing design professionals’ liens (§ 3081.1 et seq.) applies equally to a contractor such as Summit, which furnished design/planning services and hired design professionals.

*840 DISCUSSION

1. The lien filed by Summit was a mechanic’s lien, not a design professional’s lien. Therefore, Summit’s reliance on the design professional’s lien law, which authorizes the filing of a design lien despite the lack of commencement of construction, to allow the filing of a mechanic’s lien despite the lack of commencement of construction, is misplaced.

a. The statutory scheme authorizing design professionals’ liens.

In 1990, the Legislature added a new chapter 8 to title 14 of the Civil Code providing for design professionals’ liens. The newly created lien is not a mechanic’s lien. 2 The chapter is denominated “Design Professionals’ Liens,” and constitutes “the exclusive lien remedy for design professionals in cases where no actual construction of the planned work of improvement is commenced prior to recordation of the notice of lien . . . .” (Stats. 1990, ch. 1615, § 2, p. 7788, italics added.) The design professional’s lien remedy is separate and distinct and “does not affect the ability of a design professional to obtain a mechanic’s lien pursuant to Title 15” (§ 3081.6), provided the claimant can meet the criteria for a mechanic’s lien.

With respect to the circumstances giving rise to a design professional’s hen, section 3081.2 states in pertinent part: “A design professional shall, from the date of recordation pursuant to Section 3081.3, have a lien upon the real property for which the work of improvement is planned to be constructed, notwithstanding the absence of commencement of actual construction of the planned work of improvement, if the landowner contracted for the design professional’s services and is also the owner of the real property at the time of recordation of the lien.” (Italics added.)

The term “design professional” is defined in section 3081.1, which states: “For purposes of this chapter, ‘design professional’ means any certificated architect, registered professional engineer, or licensed land surveyor who furnishes services pursuant to a written contract with a landowner for the design, engineering, or planning of a work of improvement.”

*841 b.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Vita Planning & Landscape Architecture, Inc. v. HKS Architects, Inc.
240 Cal. App. 4th 763 (California Court of Appeal, 2015)
CP III Rincon Towers, Inc. v. Cohen
13 F. Supp. 3d 307 (S.D. New York, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
20 Cal. Rptr. 3d 399, 123 Cal. App. 4th 836, 2004 Cal. Daily Op. Serv. 9721, 2004 Daily Journal DAR 13279, 2004 Cal. App. LEXIS 1825, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dorsay-international-partners-v-superior-court-calctapp-2004.