Dormitory Authority v. Continental Casualty

Court of Appeals for the Second Circuit·Decided June 23, 2014·No. 13-1671·Published

Opinion

13‐1671 Dormitory Authority v. Continental Casualty

UNITED STATES COURT OF APPEALS FOR THE SECOND CIRCUIT

August Term, 2013

1 (Argued: March 12, 2014 Decided: June 23, 2014) 2 3 Docket No. 13‐1671 (L), 13‐1700 (xap) 4 5 ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐x 6 7 DORMITORY AUTHORITY OF THE STATE OF 8 NEW YORK, 9 10 Plaintiff‐Appellee‐Cross‐ 11 Appellant, 12 13 ‐ v.‐ 14 15 CONTINENTAL CASUALTY COM, AKA 16 CONTINENTAL CASUALTY COMPANY, 17 18 Defendant‐Appellant‐Cross‐ 19 Appellee. 20 21 ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐x

1 Before: JACOBS, POOLER, Circuit Judges, Román, District Judge.* 2 3 In this declaratory judgment action between the owner of a building and

4 the insurer of the architectural firm that designed it, the insurer appeals from the 5 judgment of the United States District Court for the Southern District of New 6 York (Forrest, J.), ruling, on summary judgment, that two design flaws in the 7 same structure were not “related.” Under the terms of a stipulation between the 8 parties, a separate limit of liability was therefore available to fix each flaw. The 9 building owner cross‐appeals the calculation of prejudgment interest. We affirm 10 as to the declaration and vacate as to interest.

11 RICHARD SIMPSON (Gary P. Seligman 12 and Leland H. Jones IV, on the brief), Wiley 13 Rein LLP, Washington, DC, for 14 Appellant‐Cross‐Appellee. 15 16 JERROLD J. GANZFRIED (Stephen B. 17 Shapiro, Frederick D. Page, Timothy B. 18 Froessel, on the brief), Holland & Knight 19 LLP, Washington, DC, for 20 Appellee‐Cross‐Appellant. 21 22 23 24

*

The Honorable Nelson S. Román, United States District Judge for the Southern District of New York, sitting by designation.

1 DENNIS JACOBS, Circuit Judge: 2 Continental Casualty Company issued claims‐made liability policies to the 3 architectural firm responsible for designing and overseeing the construction of a 4 building for the Dormitory Authority of the State of New York (“DASNY”). In 5 this declaratory judgment action, the insurer appeals from a judgment of the 6 United States District Court for the Southern District of New York (Forrest, J.), 7 ruling on summary judgment that the two design flaws in the same structure 8 were not “related.” The parties had stipulated that if the two flaws were held to 9 be unrelated, the insurer would indemnify loss caused by the second flaw with a 10 second limit of liability. 11 Continental appeals from the declaration, and further argues against the 12 imposition of prejudgment interest. DASNY’s cross‐appeal argues that the 13 district court should have calculated prejudgment interest at New York’s 14 statutory rate of nine percent. We affirm as to the declaration and vacate as to the 15 calculation of interest. 16 17 BACKGROUND 18 In September 1995, DASNY contracted with an architectural firm (the 19 “Architects”) to design and oversee the construction of a new building for Baruch

1 College of the City University of New York. Construction, begun in 1997, was 2 beset by delays from the outset. Plans drawn by the architects and its 3 subcontractor erred in their estimate of the steel requirement and in the 4 specifications of the structural steel girts and exterior facade (the “Steel Girt 5 Tolerance Issue”). To recover losses from the resulting delay and expense, 6 DASNY sent a demand letter to the Architects detailing the Steel Girt Tolerance 7 Issue in May 2002 (the “2002 Demand Letter”). 8 After the Project was finished in 2001, it was discovered that excessive 9 accumulations of snow and ice were sliding off the building onto sidewalks a 10 considerable distance away. In the winter of 2003‐04, the architects commissioned 11 a subcontractor to study the “Ice Control Issue.” The study concluded that the 12 design of the facade failed to account for temperature variations appropriate for a 13 building in New York, and that the problem could not be solved by adding 14 canopies, as had been hoped. Study of the problem continued into 2005. 15 In June 2004, Travelers Casualty & Surety Company (“Travelers”), the 16 surety on performance bonds purchased by the Project’s general contractor, sued 17 DASNY and the Architects. DASNY was sued for delay‐related expense and for 18 pass‐through claims from subcontractors, and the Architects were sued for 19 contributing to the delays and for breach of professional duties.

Free access — add to your briefcase to read the full text and ask questions with AI

Dormitory Authority v. Continental Casualty, (2d Cir. 2014).

Dormitory Authority v. Continental Casualty (Dormitory Authority v. Continental Casualty) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Salve Regina College v. Russell
499 U.S. 225 (Supreme Court, 1991)
Federal Insurance v. American Home Assurance Co.
639 F.3d 557 (Second Circuit, 2011)
Guippone v. BH S & B Holdings LLC
737 F.3d 221 (Second Circuit, 2013)