Doran-Maine, Inc. v. American Engineering & Testing, Inc.

608 F. Supp. 609, 1985 U.S. Dist. LEXIS 19829
CourtDistrict Court, D. Maine
DecidedMay 14, 1985
DocketCiv. 81-0158-P
StatusPublished
Cited by3 cases

This text of 608 F. Supp. 609 (Doran-Maine, Inc. v. American Engineering & Testing, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Doran-Maine, Inc. v. American Engineering & Testing, Inc., 608 F. Supp. 609, 1985 U.S. Dist. LEXIS 19829 (D. Me. 1985).

Opinion

FINDINGS OF FACT, CONCLUSIONS OF LAW AND OPINION

GENE CARTER, District Judge.

Plaintiff Doran-Maine, Inc. (Doran) is a manufacturer and distributor of concrete pipe in Maine and throughout New England. Defendant American Engineering & Testing, Inc. (AET) is a materials testing and consulting firm organized and existing under Massachusetts law. Doran was awarded a contract by Lisbon Contractors, Inc., the general contractor for the City of Concord, New Hampshire, to supply concrete pipe to be used in a storm and sewer construction project. AET was engaged by the supervising engineer on the project, Camp Dresser & McKee (CDM), to analyze tests and approve materials to be used on the project, including the concrete pipe supplied by Doran. AET performed tests on Doran’s pipe, and subsequently advised CDM that the tested pipe did not meet the absorption standards set forth in the contract specifications for the project. AET further advised CDM that any concrete pipe fabricated on the same machine as the tested pipe would not meet contract specifications. Lisbon Contractors subsequently terminated its contract with Doran for all pipe 24 inches in diameter and smaller.

Under two different theories, Doran alleged that AET was legally responsible for damages it suffered as a result of the contract termination. First, Doran alleged that AET negligently conducted the absorption tests and negligently failed to investigate Doran’s claims of inaccuracy, and that AET’s negligence caused Lisbon Contractors to terminate its contract with Do-ran. Second, Doran alleged that AET intentionally interfered with its contractual relations with Lisbon Contractors. The parties agree that Massachusetts law is to be applied. The case was tried to the Court without jury on March 4 and 5, 1985. The parties have submitted post-trial briefs in support of their respective positions.

I. Findings of Fact

Lisbon Contractors was the general contractor for a sewer construction project which commenced in Concord, New Hampshire in 1980. Lisbon entered into a contract with Doran on June 24, 1980, under which Plaintiff engaged to supply concrete pipe for the project varying in diameter from 12 inches to 36 inches. Doran began fabricating 18 inch Class IV pipe and 36 inch and 30 inch pipe for the project in the summer of 1980.

Camp Dresser & McKee, Inc. (CDM) was engaged by the City of Concord to be the supervising engineer for the project. CDM’s responsibilities included the duty to ensure that all project specifications were followed. In accordance with this duty, CDM entered into a contract with AET under which AET undertook to inspect and test reinforced concrete pipe and precast manholes to ensure conformance with CDM’s specifications. The agreement between CDM and AET was made on July 18, 1980. Paragraph 3.5 of the contract provided that CDM shall “[cjonsult with Consultant [AET] regarding the qualification of any contractor or subcontractor proposed for this Part of the Project.” The agreement provided that AET would be paid sixty-nine cents ($.69) per linear foot of pipe produced for its testing and consulting services. The contract provided that this payment would include all travel costs, tests and other items required by pertinent project specifications. Therefore, the compensation AET was to receive under the contract would not vary with the amount of testing it performed; it was determined by the amount of pipe produced by Doran.

Representatives of AET visited Doran’s plant prior to the time that production of the pipe began and periodically after construction began. Doran has two machines for the vertical fabrication of concrete pipe. The smaller machine is capable of fabricating pipe from 6 inches in diameter to 36 *611 inches in diameter. The larger machine is generally used for pipe from 21 inches in diameter to 72 inches in diameter. It was understood by both Doran and AET that Doran intended to use the smaller machine for producing pipe for the Concord project of 24 inches in diameter and smaller, and that the larger machine was to be used to fabricate all larger pipe.

AET was to perform several different tests on the concrete pipe, but only the test for absorption is at issue in this ease. The purpose of the absorption test is to determine how much water a piece of concrete pipe will absorb. The concern is that if pipe absorbs too much water, the water will eventually weaken the steel reinforcement embedded in the pipe and abbreviate the useful life of the pipe.

The parties agree that the acceptable method of testing concrete pipe is set forth by the American Society of Testing Materials (ASTM) in Standard C 497. The absorption test is fairly straightforward. It includes two alternative procedures. Method A is the standard test and requires three to six days to complete. Method B is intended as an accelerated test that requires about one and a half days to complete. AET used Method A to test Doran’s pipe.

Under Method A, the laboratory technician first dries a sample core from the wall of the pipe in an oven at a temperature of 221 to 239 degrees Fahrenheit for a minimum of forty-eight hours. The sample then must be weighed at intervals of not less than six hours until the increment of weight loss during an interval falls to .1% or lower. Then the dry weight of the sample is recorded. Then the sample is placed in water, which is heated to a boil, and the boil is continued for five hours. The technician then turns off the heat and permits the sample to cool in the water for not less than fourteen hours nor more than twenty-four hours. The technician then removes the sample from the water, places it on the drain rack and allows it to drain for one minute. Excess water is removed from the sample by quickly blotting with an absorbent cloth, and the technician is to weigh the sample immediately following the blotting. To calculate the absorption percentage, the technician subtracts the dry weight of the sample from the wet weight and divides that figure by the dry weight.

The job specifications call for an average absorption percentage not in excess of 5.5%, with no result to be above 6%. AET obtained its first set of absorption test results on August 1, 1980. These results reflected tests performed on samples taken by Doran at AET’s request and delivered to AET via parcel post. AET president, William Montgomery, had instructed Richard Davies, vice president of Doran, to take one core sample of 2 inches in diameter and one sample of 4 inches in diameter from each size and class of pipe for each day of production. He gave no instructions as to the location on a specific piece from which the samples should be taken. Tests' of samples of 18 inch pipe fabricated on July 17, 21 and 23 were completed by AET technician Henry Walter on August 1, 1980. Several of the absorption percentages were found to exceed the 6% maximum set forth in the specifications, and the average absorption percentage to significantly exceed the 5.5% average contained in the specifications. Montgomery immediately informed CDM and Doran of the test results.

If samples fail to meet specifications in the initial absorption test, the specifications require that two samples from pipe produced on each day be tested. Accordingly, Montgomery again requested Doran to take and to send him two samples of 18 inch pipe for each of the production days of July 17, 21 and 23 for retesting.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
608 F. Supp. 609, 1985 U.S. Dist. LEXIS 19829, Counsel Stack Legal Research, https://law.counselstack.com/opinion/doran-maine-inc-v-american-engineering-testing-inc-med-1985.