Don Coleman Construction Co. v. Mid-South Mortgage, Inc.

368 So. 2d 758, 1979 La. App. LEXIS 3734
CourtLouisiana Court of Appeal
DecidedFebruary 20, 1979
DocketNos. 13775, 13776
StatusPublished

This text of 368 So. 2d 758 (Don Coleman Construction Co. v. Mid-South Mortgage, Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Don Coleman Construction Co. v. Mid-South Mortgage, Inc., 368 So. 2d 758, 1979 La. App. LEXIS 3734 (La. Ct. App. 1979).

Opinion

MARVIN, Judge.

These consolidated cases between a mortgage company and a builder arose because [759]*759the builder changed plans for the financing of a $2,000,000 apartment complex from a government-funded loan by the mortgage company (Mid-South) to a conventional loan by a bank. When the mortgage company obtained a refund of $15,000 as a,portion of the commitment fee it had paid the government, the builder sued the mortgage company for a refund. In turn, the mortgage company sued the builder for a $36,200 financing and service fee which it claims it had “earned” and to which it would have been entitled had the builder made the government funded loan as planned.1

The lower court rendered judgment in favor of the builder for $10,000 without interest, in effect allowing the mortgage company to retain $5,000 for its services to the builder and otherwise rejected the demands of each litigant. The appeal of the mortgage company was answered by the builder, who seeks to increase the judgment to an amount equal to the $15,000 refund.2

Under the National Housing Act (now 12 U.S.C.A. § 1701 et seq.), the government appropriates and provides funds to lenders at a lower than market interest rate to encourage the construction of multi-family housing. Lenders apply for approval of funds for proposed construction and “purchase” a commitment of funds for a specified period of time (in this case, three years) by paying a fee to the government. In this case the fee was two percent of the amount applied for, or $40,112. If the commitment is cancelled before its time period expires the lender may obtain a partial refund from the government. In this case $15,042 was refunded.

The builder here had done business with the mortgage company on other projects before the planning of this project was begun in 1974. This was the first project of these parties, however, which was to be funded under section 221 d(4) of the National Housing Act. The Act is silent with respect to the borrower’s right to claim refund from the mortgage company of amounts paid the mortgage company by the borrower. These parties expressed no agreement on a refund during the time they were planning for 221 d(4) funding from October 1974 to mid-July 1975.

The apartment project is known to those involved as Orleans Square. Preliminary planning began in October, 1974. On December 19, 1974, Mid-South mailed the initial application to the Federal Housing Administration’s Shreveport office (FHA) with supporting documents. This produced what is called a SAMA (Site Appraisal and Market Analysis) letter from FHA which was explained as the government’s approval of the feasibility of the project and its tentative willingness to insure the financing of the project with government funds by and through GNMA (Government National Mortgage Association). The SAMA letter from FHA was dated January 23, 1975. Telephonic request by the mortgage company to GNMA after the SAMA letter issued resulted in GNMA’s acceptance of the mortgage company’s offer to purchase a commitment of government funds. The mortgage company is referred to by GNMA sometimes as the seller of the mortgage securing the loan. This acceptance established generally that GNMA would allow the mortgage company to purchase a commitment [760]*760for three years beginning January 24, 1975, of funds at 8.25 percent interest expressly for the financing of the Orleans Square project. The amount GNMA would commit, subject to FHA requirements, was shown as $2,005,600 and the commitment fee required by GNMA was $40,112.

About the time the FHA SAMA letter and the GNMA commitment issued, the mortgage company bound itself to the builder to provide interim and permanent financing for the project and requested and obtained from the builder his check payable to the mortgage company for an amount equal to the commitment fee. The mortgage company then sent its own check to GNMA to purchase the commitment. The mortgage company then began preparing additional data for the multitude of forms required by FHA. The builder and the mortgage company sought to have FHA insure or guarantee the $2,000,000 figure, 90 percent of the estimated cost of the project. On April 17, 1975, FHA agreed to insure or guarantee only $1,800,000, or 80 percent, of the estimated cost of the project. The builder, however, made no complaint regarding the reduced guarantee of the government and as hereafter mentioned, constructed the apartment complex with a $1,500,000 conventional bank loan.

A few days before July 21, 1975, the builder informed the mortgage company that he did not want to proceed with the 221 d(4) financing because of “too much red tape”.3 The builder confirmed this by his letter of July 21, 1975, to the mortgage company and expressly requested the mortgage company to terminate the commitment which had been purchased (“our . commitment”, the letter said) “. and refund monies to [the builder].” The refund of $15,000, which was made payable to the mortgage company by GNMA on July 22, 1975, is the subject of this lawsuit.

Sometime before July 14,1975, the builder made application to a Shreveport bank for a conventional loan, for on that date the bank wrote the builder that it was willing to lend him $1,500,000 at 9.5 percent interest. The loan was eventually made and the project was constructed.

The builder contends that he should have judgment in his suit for the refund.

The mortgage company contends that it should have judgment in its suit for the $36,200 financing fee or alternatively, for an amount equal to the reasonable value of its services and its undertakings to and for the builder.

The lower court correctly concluded that there was no understanding between the litigants regarding the contingency of any refund. The lower court also correctly found no general practice to exist in the industry of this type financing for construction regarding refunds of amounts paid in this situation. We find that there was a general practice in the industry that the builder would be charged by the mortgage company an amount at least equal to the fee the mortgage company was required to pay the government for its commitment of the funds applied for. In this case the mortgage company committed itself to provide interim and permanent financing under this type project when the government conditionally agreed to guarantee or to insure the amount applied for. With the government guaranteeing or insuring the loan, the security (mortgage note) to be signed at final closing would become more merchantable by the mortgage company, who in this case could have sold the loan after closing and retained the status of servicer of the loan or who could have retained the position of the secured creditor itself.

Except in cases where the mortgage company performs more than routine services for the builder, the fee charged the builder [761]*761for the mortgage company’s commitment to provide interim and permanent financing is not more than the fee charged by the government for the purchase of the commitment. We also find that the parties in such instances, and whether the mortgage company is serving as mortgage' banker (which itself commits to provide interim and permanent financing) or as mortgage broker (which attempts to find others to make these commitments), contemplate that the mortgage company’s payment for its services and commitments will come from the financing fee which is usually paid by the builder-borrower when the final closing of the loan occurs.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Minyard v. Curtis Products, Inc.
205 So. 2d 422 (Supreme Court of Louisiana, 1967)
AE Landvoigt, Inc. v. LOUISIANA STATE EMP. RETIREMENT SYSTEM
337 So. 2d 881 (Louisiana Court of Appeal, 1976)
Moore v. Travelers Indemnity Co.
352 So. 2d 270 (Louisiana Court of Appeal, 1978)
State ex rel. Department of Highways v. McInnis
360 So. 2d 887 (Louisiana Court of Appeal, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
368 So. 2d 758, 1979 La. App. LEXIS 3734, Counsel Stack Legal Research, https://law.counselstack.com/opinion/don-coleman-construction-co-v-mid-south-mortgage-inc-lactapp-1979.