Domitrovich v. Stone & Webster Engineering Corp.

118 P. 760, 44 Mont. 7, 1911 Mont. LEXIS 71
CourtMontana Supreme Court
DecidedOctober 21, 1911
DocketNo. 3,007
StatusPublished

This text of 118 P. 760 (Domitrovich v. Stone & Webster Engineering Corp.) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Domitrovich v. Stone & Webster Engineering Corp., 118 P. 760, 44 Mont. 7, 1911 Mont. LEXIS 71 (Mo. 1911).

Opinion

MR. JUSTICE SMITH

delivered the opinion of the court.

Action for damages on account of the alleged negligence of the defendant in causing the death of plaintiff’s intestate. Plaintiff had verdict and judgment. Defendant appeals from the judgment and an order denying its motion for a new trial.

1. The action was originally begun against the appellant and one John Doe, alleged to have been its foreman and superintendent. The appellant is.a corporation, organized and existing under and by virtue of the laws of the state of Massachusetts. John Doe was not served with process and did not appear. After issues of fact were joined between plaintiff and the [1] appellant, the cause came on regularly for trial. The court inquired whether the parties were ready to proceed, whereupon plaintiff’s counsel said, “Plaintiff is ready, — ” when he was interrupted by defendant’s counsel with the remark that he desired to file a petition and bond to remove the case to the federal court. Plaintiff’s counsel, apparently continuing his original statement, said: “But we desire to reduce the amount of damages to $2,000.” The district judge, who was, of course, present and best able to determine the purpose and attitude of plaintiff’s counsel and to properly construe his conduct and judge of his intention, held in effect that he had not concluded his statement, and that what he intended to say, in answer to the court’s inquiry, was that plaintiff was ready for trial, “except that he desired to amend his complaint.” The court thereupon held that defendant’s tender of petition and bond came after plaintiff had asked leave to amend by reducing the amount of damages demanded. The motion to amend was granted, and the cause was retained for trial, after it had been agreed that the petition and bond were sufficient in form and substance to effect a removal, had not the amendment been requested and allowed. It was the province of the district judge to determine [16]*16the question of fact involved in the controversy, and he having decided that plaintiff’s counsel had not concluded his statement, this court cannot, under the circumstances, interfere with the finding. Counsel for plaintiff had the undoubted right to conclude his statement without interruption by counsel for the other side, and to have a ruling on his motion, and it was conceded at the time of the incident that, if the request to amend was made before the petition and bond were teudered, the court properly retained the cause for trial. We find no error in this action of the court.

2. The complaint alleges: “That the said defendant company and the said John Doe, so acting in its behalf in that regard, negligently failed to make said track reasonably safe for use, and negligently failed to provide in the ties used on said track sufficient ballast and support, and negligently failed to provide a reasonably safe roadbed for said track. That the said Alexander Marsenich [deceased employee of defendant], on said 13th day of March, 1909, so in the usual course of his employment, and while, with others, directing the movement of one of said cars on said track, so loaded as aforesaid, the said car, while moving on said track, on account of the insufficient ballast and support for said ties as aforesaid and on account of said track being unsafe as aforesaid, said rails on said track on which said car was running sagged, by reason whereof the said car jumped the track,’’ and plaintiff was injured.

Deceased, a native of Montenegro, twenty-one years of age, who had been in this country about two years, was engaged with others in loading rock into a dump-car on the banks of the Missouri river, at a point about 20 miles from Helena, where the defendant was engaged in constructing a power dam; their work was to fill the car by hand, then push it out over a track onto the dump, already constructed, into the river, where the rock was thrown into the water for the purpose of making a temporary dam to divert the water into a new channel. As the dump was extended, the track was moved closer to its edge in order to carry the work forward; the track was moved three [17]*17or four times a day; the ties in some places were three feet apart, and in others six feet apart; they were laid on the rock. One Tom Fee was the foreman or superintendent; he was “bossing the job.” Not anybody was above him in authority. He was the “head man.” Three men were keeping the track in repair. A brother of the deceased testified: “Those fellows were kicking that the track was played out, and Tom Fee he says, ‘Boys, go ahead,’ he say. Alex. Marsenieh was the one that was kicking about the track at the time. It was between 11 and 12 o ’clock that my brother complained, and Fee told him to go ahead. About a quarter to 12 that night, when my brother was injured, we started with the car loaded with rocks. We were running the ear by hand, just holding the car, not pushing, because the track was too much of an incline. The car upset because it got in a hole. That place was not in good condition. The rail was there, but it was not in good condition — not strong enough to support the car. At the time when the pressure came above that hole, the track incline a little bit— went down. After the track went down in that way, the ear upset. When the car upset, that throwed my brother under the rocks.”

Mike Chukish testified: “The last time that we took the trucks down there before Alex was injured, and when we started back with it, there were men repairing the track in the same time exactly as we were working there. When we got over to where these men were, they were raising up the track. When we went by with the trucks at the point where these men were repairing this track, these men went to the side and they let us go by. After we got by with the trucks, these men started in right away again to raise up the track. After the car was loaded (a second time), we went down to the track again — went to dump it. Q. And what, if anything, did Mr. Fee say to them before they started out? A. When the car was stopped, Mr. Fee said, ‘Go ahead.’ We stood there when Mr. Fee made that remark, because we could not take it over. Q. Now, then, when Fee told them, ‘Go ahead,’ and they went ahead, did they get [18]*18any signal at all from these men repairing the track there to stop? [This question was objected to as calling for testimony not within the issues framed by the pleadings.] A. No, sir; they didn’t give no signal. The ear went off the track. The truck got off the track at the same place where these men were repairing the track. The ear got off the track because the ties were set on the rock. The track was put on the rocks about three feet high. The track kind of sunk there. On both sides of the ties were rocks, and then between is an empty space. There was no rock between — just rock under the ties, the car kind of shaking, both sides, and they couldn’t stop the car, and it upset.”

It is contended that the court erred in allowing the witness to answer the question to which objection was made, as above indicated. It is said that this testimony can only relate to a failure to warn the deceased, which is not a ground of negligence as pleaded. We think the testimony was clearly admissible as being a part of the occurrence as the witness saw it. [2] Whether or not a ground of negligence, predicated upon a failure to warn of danger, could properly be considered by the jury was a matter to be decided upon settlement of the instructions. There is no complaint of the instructions.

3.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Northern Pacific Railroad v. Herbert
116 U.S. 642 (Supreme Court, 1886)
Kelley v. Fourth of July Mining Co.
41 P. 273 (Montana Supreme Court, 1895)
Allen v. Bell
79 P. 582 (Montana Supreme Court, 1905)
Schroder v. Montana Iron Works
100 P. 619 (Montana Supreme Court, 1909)
McAuley v. Casualty Co. of America
102 P. 586 (Montana Supreme Court, 1909)
Hill v. Nelson Coal Co.
104 P. 876 (Montana Supreme Court, 1909)
O'Brien v. Corra-Rock Island Min. Co.
105 P. 724 (Montana Supreme Court, 1909)
Osterholm v. Boston & Montana Con. C. & S. Mining Co.
107 P. 499 (Montana Supreme Court, 1910)
Eeraert v. Eureka Lumber Co.
117 P. 1060 (Montana Supreme Court, 1911)

Cite This Page — Counsel Stack

Bluebook (online)
118 P. 760, 44 Mont. 7, 1911 Mont. LEXIS 71, Counsel Stack Legal Research, https://law.counselstack.com/opinion/domitrovich-v-stone-webster-engineering-corp-mont-1911.