Dominion Trust Co. v. Kenbridge Construction Co.

448 S.E.2d 659, 248 Va. 393, 1994 Va. LEXIS 129
CourtSupreme Court of Virginia
DecidedSeptember 16, 1994
DocketRecord 931073
StatusPublished
Cited by21 cases

This text of 448 S.E.2d 659 (Dominion Trust Co. v. Kenbridge Construction Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dominion Trust Co. v. Kenbridge Construction Co., 448 S.E.2d 659, 248 Va. 393, 1994 Va. LEXIS 129 (Va. 1994).

Opinion

JUSTICE HASSELL

delivered the opinion of the Court.

In this appeal, we consider whether a mechanic’s lien was perfected in the manner prescribed by law.

I.

Plaza One Associates, a Virginia Limited Partnership, executed a contract with Kenbridge Construction Company, Inc. for the construction of a hotel upon approximately five acres of property. Plaza One failed to pay for certain work, and Kenbridge filed a memorandum for mechanic’s lien in the principal amount of *395 $316,603.88, later reduced to $315,048.88 to correct a clerical error.

Kenbridge filed its amended bill of complaint to enforce its mechanic’s lien against numerous defendants, including Dominion Trust Company and Riggs National Bank of Washington, D.C., the trustee and beneficiary, respectively, of a deed of trust upon the property. The cause was referred to a commissioner in chancery. Dominion and Riggs asserted (1) that the memorandum for mechanic’s lien was not filed timely and (2) that the memorandum is invalid because it includes the costs of labor performed and materials used on public roads which are neither located on the property nor described in the memorandum. The commissioner and the trial court rejected both defenses, and the trial judge entered a judgment in favor of Kenbridge. We awarded an appeal to Dominion and Riggs.

II.

As the commissioner found, the project architect certified that the hotel was “substantially complete” on May 5, 1989, and the hotel opened for business that day. As of that date, however, Ken-bridge was required to perform other work to fulfill its obligations under the construction contract. Kenbridge was required by the contract to complete work on a swimming pool enclosure, the hotel’s “Presidential Suite,” the employee locker room, the men’s lockers, and the landscape. This work was not correction of previous work or warranty repairs. Kenbridge would have been in breach of its contract if it had failed to perform this work.

Code § 43-4, states in relevant part:

A general contractor, or any other lien claimant ... in order to perfect the lien given by § 43-3, . . . shall file a memorandum of lien at any time after the work is commenced or material furnished, but not later than ninety days from the last day of the month in which he last performs labor or furnishes material, and in no event later than ninety days from the time such building, structure, or railroad is completed.

(Emphasis added.) Dominion and Riggs argue that the memorandum for mechanic’s lien was not filed timely because the memorandum was filed more than 90 days from the date that the hotel *396 was substantially completed. Dominion and Riggs, relying upon cases from other states, argue that the word “completed,” contained in Code § 43-4, “must be interpreted to mean the date of substantial completion of the building” and that insignificant work performed after the date of substantial completion “will not extend the time for filing a memorandum of lien.” Kenbridge, however, asserts that its memorandum for mechanic’s lien is timely because it was filed within 90 days of the date of completion. We agree with Kenbridge.

We have repeatedly articulated principles of statutory construction that we must apply when a statute, such as Code § 43-4, is clear and unambiguous.

While in the construction of statutes the constant endeavor of the courts is to ascertain and give effect to the intention of the legislature, that intention must be gathered from the words used, unless a literal construction would involve a manifest absurdity. Where the legislature has used words of a plain and definite import the courts cannot put upon them a construction which amounts to holding the legislature did not mean what it has actually expressed.

Barr v. Town & Country Properties, Inc., 240 Va. 292, 295, 396 S.E.2d 672, 674 (1990) (quoting Watkins v. Hall, 161 Va. 924, 930, 172 S.E. 445, 447 (1934)). Applying this rule of statutory construction, we decline the invitation of Dominion and Riggs to rewrite and change the plain meaning of Code § 43-4 by adding the word “substantially” as a modifier to “completed.”

Accordingly, we hold that in the absence of evidence that a contractor acted in bad faith to delay the completion of work on a project, the contractor is required to file his memorandum for mechanic’s lien 90 days from the date of completion. See Burks’ Pleading and Practice § 459 (4th ed. 1952). Here, there is no evidence that Kenbridge delayed the completion of its work in bad faith to extend the time of filing its memorandum. Kenbridge’s work logs reveal that it completed work on the project on June 8, 1989 and, therefore, its memorandum for mechanic’s lien, filed August 21, 1989, was within the prescribed 90 day statutory period.

*397 III.

A.

Dominion and Riggs argue that the lien is invalid because the memorandum for mechanic’s lien includes the cost of labor and materials that Kenbridge furnished on the roads that are not part of the property. Kenbridge asserts that the roads are part of the property. We disagree with Kenbridge. The commissioner found that the labor and materials furnished on the roads constituted “off-site work,” and Kenbridge did not assign cross-error to the trial court’s order confirming the commissioner’s report.

Kenbridge contends, however, that when it began to construct the hotel Kenbridge believed that the roads had been vacated by the County, and when public roads are vacated, the fee simple interest in the roads vests in the party who owns the adjacent real estate. See Code § 15.1-483. Our review of the record reveals, however, that Kenbridge failed to prove either that the roads had been vacated or that the roads were adjacent to and had become a part of the property upon which the hotel was constructed.

Kenbridge also argues that even if the roads are not part of the property, they are permanently annexed to the freehold pursuant to Code § 43-2 and, thus, the value of work performed on the roads may be included in its mechanic’s lien memorandum. We disagree with Kenbridge because Code § 43-2 does not apply.

Code § 43-2 states:

For the purpose of this chapter, a well, excavation, sidewalk, driveway, pavement, parking lot, retaining wall, curb and/or gutter, breakwater (either salt or fresh water), water system, drainage structure, filtering system (including septic or waste disposal systems) or swimming pool shall be deemed a structure permanently annexed to the freehold, and all shrubbery, earth, sod, sand, gravel, brick, stone, tile, pipe or other materials, together with the reasonable rental or use value of equipment and any surveying, grading, clearing or earth moving required for the improvement of the grounds upon which such building or structure is situated shall be deemed to be materials furnished for the improvement of such building or structure and permanently annexed to the freehold.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lamarr Ramon Masean Smith v. Commonwealth of Virginia
785 S.E.2d 500 (Court of Appeals of Virginia, 2016)
Justin Sarafin v. Commonwealth of Virginia
748 S.E.2d 641 (Court of Appeals of Virginia, 2013)
Schwartz v. Schwartz
616 S.E.2d 59 (Court of Appeals of Virginia, 2005)
Hodges v. COM., DEPT. OF SOCIAL SERVICES
609 S.E.2d 61 (Court of Appeals of Virginia, 2005)
O'Neil v. United States Automobile Ass'n
57 Va. Cir. 257 (Virginia Circuit Court, 2002)
Carol Bowyer Johnson v. Commonwealth of Virginia
Court of Appeals of Virginia, 2001
Crislip v. Commonwealth
554 S.E.2d 96 (Court of Appeals of Virginia, 2001)
Johnson v. Commonwealth
543 S.E.2d 605 (Court of Appeals of Virginia, 2001)
Carolina Builders Corp. v. Cenit Equity Co.
512 S.E.2d 550 (Supreme Court of Virginia, 1999)
Patricia A. Smith v. Walter H. Warme, Jr.
Court of Appeals of Virginia, 1998
P. C. Goodloe & Son, Inc. v. Charter Communities, Inc.
44 Va. Cir. 193 (Stafford County Circuit Court, 1997)
Haislip v. Southern Heritage Insurance
492 S.E.2d 135 (Supreme Court of Virginia, 1997)
Davis v. Tazewell Place Associates
492 S.E.2d 162 (Supreme Court of Virginia, 1997)
Commonwealth v. Thomas
478 S.E.2d 715 (Court of Appeals of Virginia, 1996)
Frey v. Jefferson Homebuilders, Inc.
467 S.E.2d 788 (Supreme Court of Virginia, 1996)
Jim Carpenter Co. v. Ross Brothers Builders, Inc.
36 Va. Cir. 257 (Stafford County Circuit Court, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
448 S.E.2d 659, 248 Va. 393, 1994 Va. LEXIS 129, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dominion-trust-co-v-kenbridge-construction-co-va-1994.