Dominion Rebar Co. v. L M Concrete Forms, Inc., 94-2588 (1997)

CourtSuperior Court of Rhode Island
DecidedFebruary 11, 1997
DocketC.A. No. 94-2588
StatusPublished

This text of Dominion Rebar Co. v. L M Concrete Forms, Inc., 94-2588 (1997) (Dominion Rebar Co. v. L M Concrete Forms, Inc., 94-2588 (1997)) is published on Counsel Stack Legal Research, covering Superior Court of Rhode Island primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dominion Rebar Co. v. L M Concrete Forms, Inc., 94-2588 (1997), (R.I. Ct. App. 1997).

Opinion

DECISION
Before this Court are cross motions for summary judgment brought pursuant to R.C.P. 56 by the plaintiff, Dominion Rebar (Dominion), and the defendants, LM Concrete (LM) and Hartford Fire Insurance (Hartford).

Facts and Travel
This dispute arises out of a project known as the Advanced Weapons Research Facility, Naval Underwater Systems Center (NUSC project), located in Newport, Rhode Island. North American Construction Corporation (North American) was the general contractor on the project and LM was a subcontractor to North American. As a term of the subcontractor agreement between LM and North American, LM was obligated to obtain a Labor and Materials Payment Indemnity Bond (performance bond) from Hartford. Hartford was the surety on the bond, LM was the principal, and North American was the obligee. On or about March 30, 1992, Dominion and LM entered into a contract for work on the project. Under the contract, Dominion, as a subcontractor to LM, was obliged to provide certain labor and equipment for the project. Dominion performed its obligations under this agreement, but has yet to receive full payment from either LM or Hartford. Previous to the establishment of the March 30 subcontractor agreement, Dominion and LM entered into another contractual relationship. This relationship did not include issuance of a performance bond. Again, performance was tendered by Dominion, and again, LM failed to make full payment to Dominion. Consequently, Dominion brings the instant action.

On January 7, 1997, the motions at issue herein were argued before Mr. Justice Fortunato. After considering the arguments of counsel, Justice Fortunato continued the matter until February 4, 1997. The parties are now before this Court.

Standard of Review
Summary Judgment is a drastic remedy that should be cautiously applied. McPhillips v. Zayre Corp., 582 A.2d 747, 749 (R.I. 1990); Rustigian v. Celona, 478 A.2d 187, 189 (R.I. 1984). Summary Judgment should be granted when there exists no genuine issue of material fact and the moving party is entitled to judgment as a matter of law. Alfano v. Landers, 585 A.2d 651, 652 (R.I. 1991).

In passing on a motion for summary judgment, the trial justice must review the pleadings in the light most favorable to the party opposing the motion. McPhillips, 582 A.2d at 749;O'Hara v. John Hancock Mutual Life Insurance Co., 574 A.2d 135, 136 (R.I. 1990). Nevertheless, the party opposing summary judgment may not rest upon mere allegations or denials in its pleading and has the affirmative duty to set forth specific facts showing a genuine issue of fact to be resolved at trial. Ouimettev. Moran, 541 A.2d 855, 856 (R.I. 1988). Failure to set forth such facts will result in summary judgment being entered against the party opposing the motion. Ardente v. Horan, 117 R.I. 254, 257-58, 366 A.2d 162, 164 (1976).

Defendants' Motion for Summary Judgment
In support of their motion for summary judgment, the defendants argue that this Court is without jurisdiction to adjudicate the plaintiff's claim. Specifically, the defendants argue that the Miller Act, 40 U.S.C.A. § 270a et. seq., rests exclusive jurisdiction over Labor and Material Bond payment dispute with the Federal District Court. Such an interpretation of the Miller Act is flawed.

Defendants correctly argue that the Miller Act requires procurement of Labor and Materials Payment Bonds on all contracts exceeding $25,000 in value. 40 U.S.C.A. § 270a(a). Moreover, the Defendants are correct when they assert that jurisdiction over Miller Act claims rests solely with the Federal District Court. 40 U.S.C.A. § 270b(b). However, the plain meaning of the statute clearly establishes that the Miller Act is inapplicable to the current dispute. Specifically, the Miller Act provides that

"Before any contract, exceeding $25,000 in amount, for the construction, alteration, or repair of any public building or public work of the United States is awarded to any person, such person shall furnish to the United States the following bonds, which shall become binding upon the award of the contract to such person, who is hereinafter designated as `contractor' . . . ."

40 U.S.C.A. § 270a. Clearly, this language indicates that performance bonds are to be furnished to the United States by thecontractor prior to the parties entering into a contractual relationship. However, it does not require subcontractors to issue similar bonds when said subcontractors are not in privity of contract with the United States.

Clearly, the general contractor, if it so desires, remains free to require its subcontractors to supply performance bonds. Such a bond affords the general contractor a valid means of protecting its financial interests in the project. However, the United States is not a party to such a bond and the language of 40 U.S.C.A. § 270a makes it clear that this type of an agreement falls outside the scope of the Miller Act. Since the bonds issued by Hartford were not issued under the Miller Act, but rather arose under the subcontract agreement between Dominion and LM, the Miller Act's jurisdictional requirements are inapplicable to the current action. In this regard, this Court finds itself in complete agreement with the Report and Recommendation of U.S. Magistrate Judge Robert W. Lovegreen. See Report and Recommendation of U.S. Magistrate Judge Robert W. Lovegreen, Lonsdale Concrete Construction, Inc. v. LM ConcreteForms Inc., et. al., C.A. No. 94-0446T (September 26, 1995).

Because the Miller Act doesn't apply, jurisdiction is not exclusively vested in the Federal District Court. The Plaintiff has properly come before this Court and its exercise of subject matter jurisdiction over the instant action is appropriate.

Plaintiff's Motion for Summary Judgment
The plaintiff's characterization of this action is very straightforward. Dominion alleges the existence of an unpaid debt and seeks a judgment against the debtor and its bonding agent for the outstanding balance due. The plaintiff further alleges that because there exists no genuine issue of material facts, summary judgment is warranted.

In support of its motion for summary judgment, Dominion offers the affidavit of Mr. John Pursche. Mr. Pursche is an officer of Dominion. In his affidavit, he attests to the fact that LM is indebted to Dominion in the amount of $68,886.75. Mr. Pursche further indicates that this amount is the aggregation of two separate and distinct debts. A debt of $4,167.50 arose out of Job No. 4365. Job No. 4365 is independent and distinct from the NUSC project and is therefore not covered by the Hartford performance bond. A further debt of $64,719.25 is attributable to the NUSC project and is designated internally on Dominion's books as Job No. of 4076A.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Alfano v. Landers
585 A.2d 651 (Supreme Court of Rhode Island, 1991)
Ouimette v. Moran
541 A.2d 855 (Supreme Court of Rhode Island, 1988)
Ardente v. Horan
366 A.2d 162 (Supreme Court of Rhode Island, 1976)
McPhillips v. Zayre Corp.
582 A.2d 747 (Supreme Court of Rhode Island, 1990)
O'Hara v. John Hancock Mutual Life Insurance
574 A.2d 135 (Supreme Court of Rhode Island, 1990)
Rustigian v. Celona
478 A.2d 187 (Supreme Court of Rhode Island, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
Dominion Rebar Co. v. L M Concrete Forms, Inc., 94-2588 (1997), Counsel Stack Legal Research, https://law.counselstack.com/opinion/dominion-rebar-co-v-l-m-concrete-forms-inc-94-2588-1997-risuperct-1997.