Dominica Mining Co. v. Port Everglades Towing Co.

318 F. Supp. 500, 1970 A.M.C. 123, 1969 U.S. Dist. LEXIS 13723
CourtDistrict Court, S.D. Florida
DecidedNovember 10, 1969
DocketCiv. 67-433
StatusPublished
Cited by6 cases

This text of 318 F. Supp. 500 (Dominica Mining Co. v. Port Everglades Towing Co.) is published on Counsel Stack Legal Research, covering District Court, S.D. Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dominica Mining Co. v. Port Everglades Towing Co., 318 F. Supp. 500, 1970 A.M.C. 123, 1969 U.S. Dist. LEXIS 13723 (S.D. Fla. 1969).

Opinion

FINDINGS OF FACT AND CONCLUSIONS OF LAW

CHOATE, Senior District Judge.

This cause came on for trial before the Court sitting without jury upon a Complaint filed under Rule 9(h) of the Federal Rules of Civil Procedure for money *502 damages as the result of breach of charter and upon a Counterclaim for monies owed as the result of demurrage arising under the Charter. The Court, having considered the evidence, the exhibits filed herein and the testimony of the witnesses, makes the following findings of fact and conclusions of law.

FINDINGS OF FACT

1. On or about the 7th day of May 1966, Port Everglades Towing Company, Ltd., bareboat charterer of the barge B-12 and the tug “Wesley W”, entered 1 into a sub-charter with Dominica Mining Company, Ltd. by the terms of which Port Everglades Towing Company, Ltd. agreed to provide the tug “Wesley W” and the barge B-12 to carry a cargo of pumice from the Island of Dominica to the Island of St. Martin for the sum of $6,500. The pumice which was to be loaded aboard the barge weighed approximately one ton to a cubic yard.

2. The Charter Party provided that the barge B-12 had a mean draft of 10 feet 9 inches and could carry approximately 1600 tons of cargo. Although not noted in the Charter Party, the tug “Wesley W” had a draft of 9 feet 6 inches. The Charter Party also provided that barge was to be loaded and discharged free of risk and expense to the vessel or her owners.

3. The Charter Party further provided that the Charterer Dominica Mining Company have a total of 48 hours free time for loading and discharging the cargo. The Charter Party provided that demurrage was to run at the rate of $800 per day or pro rata for any part of a day, “payable day by day.”

4. On the 14th of June, 1966, at 1500 hours, the barge was positioned for loading at plaintiff’s dock, Roseau, Dominica. Thereafter, employees of plaintiff proceeded to load a cargo of crushed pumice aboard the barge. The tug was not in attendance. 1 A winch was to be used to move the barge forwards and backwards so that the pumice could be evenly distributed. By that night, however, an excessive amount of pumice was placed on the after third of the barge by plaintiff, causing her stern to sink, with the stern decks awash and the bottom in the mud.

5. This overloading of the stern of the barge required redistribution of the cargo. Because of the delays required to redistribute the cargo, loading was not completed until 2200 hours on June 16, 1966.*

6. Approximately 1500 tons of pumice were ultimately put on the barge by plaintiff. However, the barge could safely hold only about 1200 tons and 300 tons of pumice were jettisoned prior to departure.

7. On the morning of June 17, 1966, the tug and barge departed for St. Martin with about 1200 tons of cargo. The barge was listing slightly to starboard, with a 12 foot draft on the starboard side and 11 foot draft on the port side. 2 3

8. The barge arrived at St. Martin on June 18, 1966 at 1800 hours. There is an inner harbor and an outer harbor at St. Martin. In order to enter the inner harbor, it was necessary to cross a sand bar with a maximum clearance of about 9 Yz feet. The outer harbor at St. Martin had a pier or discharge berth available with water alongside over 30 feet deep. The pier or discharge berth in the inner harbor had water at its outer berth of a depth of 8 feet.

9. Because of the draft of the barge, the inner harbor could not be entered. Although the consignee had been advised *503 of the arrival of the barge, no representative consignee was on the island to receive the cargo nor had any preparations been made to have loading facilities and workmen available to commence discharge.

10. On the afternoon of June 20, 1966, the consignee’s representative arrived on the island and began at that time to make preparations for discharge. Because of the draft of the barge and the tug it was impossible to position the barge at any of the docks, in the inner harbor where efficient mechanical means could be used for discharging the cargo.

11. On the afternoon of June 22,1966 the consignee arranged to have a crew of workmen and a small crane alongside the barge at the dock in the outer harbor. The cargo was manually loaded into a bucket of approximately one cubic yard capacity, taken onto the dock and discharged into a truck. Plaintiff, or its agents, had not anticipated the necessity of this procedure and it proved to be extremely slow and inefficient.

12. Before June 26, 1966, and before the vessels had arrived at St. Martin, the defendant, through its agent, had demanded demurrage money from Plaintiff because of the loading delays at Dominica. Without conceding liability, plaintiff deposited $2,500 in escrow for the account of defendant with their bankers at Roseau, Dominica.

13. After approximately three and y2 days of unloading at the outer harbor at St. Martin only 300 to 400 yards of pumice had been discharged. At this time, the barge was drawing approximately 8 feet. Water adjacent to the dock in the inner harbor was 8 feet deep or less. The tug had previously explored the inner harbor and had hit bottom several times. Plaintiff, through its consignee or otherwise, never requested that the tug attempt to position the barge at the inner dock after it had been partially unloaded. In any event, the tug captain was not obligated to risk his vessel in an attempt to position the barge in the inner harbor.

14. Representatives of defendant realized that demurrage was accruing at the rate of $800 per day and that only about one-fourth of the cargo had been discharged in a period of 3 and y2 days. They were also concerned about the financial stability of the consignee (which later proved to be merited) and ultimately, on advice of counsel, instructed the tug captain to take the barge to St. Croix where the cargo could be disposed of. Without notifying plaintiff, the tug and barge departed for St. Croix on June 26th. At St. Croix, defendant proceeded in rem against the remaining cargo and ultimately had to give it away. 4 Defendant incurred expense at St. Croix of $950 wharfage, $600 stowage, and $476.75 unloading charges.

CLAIMS FOR RELIEF

1. Defendant asserts that it is entitled to demurrage for a period of 9 days, 16 hours, and 50 minutes. This is computed on an actual loading and discharging time of 11 days, 16 hours and 50 minutes (including 2 days to discharge, the cargo at St. Croix) allowing 2 lay days as provided by the charter, the net claim being $7,761.13. Defendant additionally claims as damages expenses incurred at St. Croix of $950 wharfage, $600 stowage, and $476.75 unloading. The total amount claimed is $9,787.88.

2.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Burmah Oil Tankers, Ltd. v. Trisun Tankers, Ltd.
687 F. Supp. 897 (S.D. New York, 1988)
Christian v. Bullock
205 S.E.2d 635 (Supreme Court of Virginia, 1974)
Gulf Puerto Rico Lines, Inc. v. Associated Food Co., Inc.
366 F. Supp. 631 (D. Puerto Rico, 1973)

Cite This Page — Counsel Stack

Bluebook (online)
318 F. Supp. 500, 1970 A.M.C. 123, 1969 U.S. Dist. LEXIS 13723, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dominica-mining-co-v-port-everglades-towing-co-flsd-1969.