Dolnikov v. Ekizian

222 Cal. App. 4th 419, 165 Cal. Rptr. 3d 658, 2013 WL 6680755, 2013 Cal. App. LEXIS 1023
CourtCalifornia Court of Appeal
DecidedDecember 19, 2013
DocketB226675
StatusPublished
Cited by26 cases

This text of 222 Cal. App. 4th 419 (Dolnikov v. Ekizian) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dolnikov v. Ekizian, 222 Cal. App. 4th 419, 165 Cal. Rptr. 3d 658, 2013 WL 6680755, 2013 Cal. App. LEXIS 1023 (Cal. Ct. App. 2013).

Opinion

Opinion

ALDRICH, J.

INTRODUCTION

We hold in this appeal that conduct can constitute actionable interference with the use and enjoyment of an easement even when the conduct does not physically obstruct the servitude. The easement in question is for ingress and egress to undeveloped lots in the Hollywood Hills. Plaintiff Flora Dolnikov, owner of the dominant tenement, was interrupted during her construction of two residences by defendants Dikran Ekizian and Diramesi Investments, LLC (defendants or Ekizian), the servient tenement owners who refused to sign both a covenant for community driveway and permission for a building permit to construct a retaining wall. The City of Los Angeles Department of Building and Safety (LADBS) required defendants’ signatures before it would issue plaintiff the permits necessary to make the easement roadway useable for its intended purpose. Plaintiff sued defendants seeking declaratory relief and damages. Defendants appeal from the ensuing judgment entered in favor of plaintiff. In the published portion of this opinion, we hold that the evidence supports the jury’s finding that defendants unreasonably interfered with plaintiff’s use and enjoyment of the easement. In the unpublished portion of this opinion, we reject defendants’ remaining challenges. Accordingly, we affirm the judgment.

FACTUAL AND PROCEDURAL BACKGROUND

1. The easement

In 1998, plaintiff acquired undeveloped lots 29 and 30 in tract 4202 located above Laurel Canyon. Her neighbor to the north and east, Amnon Gad, *423 through his company, Amgad, Inc., owned lot A, off of Floral Avenue, which consisted of four undeveloped acres in tract 4150.

In 1942, defendants’ predecessor in interest granted and recorded the easement at issue to plaintiff’s predecessor in interest (the easement). The easement provides in relevant part:

“EASEMENT—GENERAL
“A strip of land 14 Ft. wide, 7.00 Ft on each side of the following described center Une [beginning, curves, and ending described]. The foregoing described Right of Way is now improved and is used by the Bureau of Water Works and Supply of the City of Los Angeles, California [now the Los Angeles Department of Water and Power] .... NOW, THEREFORE, it is hereby agreed as follows; The said [defendants’ predecessor] does hereby grant, assign and set over to the said [plaintiff’s predecessor] ... A right of way for ingress and egress over the above described property for street purpose for the benefit of Lots 29 and 30 of Tract 4202 .... TO HAVE AND TO HOLD the said easement, right and right-of-way unto [plaintiff’s predecessor], his successors or assigns for a period of perpetuity. . . .” (Italics added.)

The easement begins at the top of Floral Avenue at the south end of lot A. It runs on the lot A side of the property line with plaintiff’s properties, uphill and roughly north in a wide curve, concave to the east, around a hill on lot A and ending at a point in lot A that is even with the northern boundary of plaintiff’s properties to the west. (A copy of a schematic is attached as an appendix to this opinion.)

In 2001, plaintiff obtained permits from LADBS to construct two houses on her land, to be designated 8027 and 8031 Floral Avenue. Her permit application included an unrecorded covenant and agreement for a community driveway executed in 1999 by defendants’ predecessor, Mr. Gad. LADBS issued the permits with the understanding the driveway would be 14 feet wide, the width of the easement, notwithstanding the zoning code required a 20-foot width.

In June 2002, while plaintiff’s construction was in progress, Amgad, Inc., sold lot A to defendant Diramesi Investments, LLC, a company owned by defendant Ekizian. Defendants purchased lot A for investment purposes with full knowledge of the easement and plaintiff's development.

2. The cut and the retaining wall permit

Plaintiff’s architect designed both residences so that their front doors and garages faced roughly east toward the easement. The slope of the easement *424 was too steep and the right-of-way had fallen into disrepair so that all that remained of the original pavement was substantially covered with dirt and rocks from uphill. As such, the easement was unsuitable for ingress and egress to plaintiff’s property. One of the first steps plaintiff took was to improve the easement roadway so that it could be used for access to plaintiff’s houses. LADBS approved a grading plan to lower the ground in the upper end of the easement to allow greater and more level access into the garage for 8031 Floral Avenue, on old lot 29. The grading would lower the soil level about six to eight feet below the level of what is the continuation of the old Los Angeles Department of Water and Power (LADWP) right-of-way at the end of the easement leading north into defendants’ property. The cut would create a roughly vertical face adjacent to the property line that needed shoring to stabilize the steep slope on defendants’ property and to comply with the building code. To stabilize the slope, the grading plan called for a retaining wall to be constructed across the face of the cut along the lot A (or defendants’) side of the easement and perpendicular across the end of the easement where the LADWP right-of-way continues into lot A.

After making the cut into the soil on the easement according to the approved grading plans, plaintiff discovered there was no permit to construct the retaining wall in the LADBS files. When she went to apply for the missing permit, she learned that Ekizian had complained and questioned plaintiff’s right to build on his property.

3. LADBS stops work on plaintiff’s project and revokes her permit.

LADBS notified plaintiff in June 2004 of its intent to revoke her building permits. LADBS explained that, among other things, the community driveway covenant from Gad was invalid because it was unrecorded, and LADBS required a new covenant signed by Ekizian as current owner of the property.

Plaintiff had numerous conversations with defendants, during which it became clear that Ekizian opposed her right to build. Ekizian did not recognize the unrecorded community driveway covenant from Gad; did not acknowledge plaintiff’s easement rights; insisted the driveway had to be 20 feet wide per then current code requirements, not the 14-foot width of the easement; and complained that he was damaged by her grading cut into the side of the easement. Ekizian demanded $100,000, then $200,000 from plaintiff. He stated variously that the money represented damages, or was a prerequisite to talks. He also demanded plaintiff cut into his hill, build a 20-foot-wide road, buy a $1 million insurance policy naming him beneficiary, and erect a retaining wall to his specifications for width, depth, and paint, before he would sign the community driveway covenant. Plaintiff felt Ekizian was “just trying to extort money,” and she could not comply with what she thought were Ekizian’s “outrageous” demands.

*425

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Berstein v. Sebring
California Court of Appeal, 2025
Rancho Carlton Properties v. Radnor CA2/5
California Court of Appeal, 2025
Schneider v. Lane
California Court of Appeal, 2024
Clement v. Jaworski CA1/5
California Court of Appeal, 2024
Grand View Real Property v. Kim CA2/3
California Court of Appeal, 2024
Blanco v. Cargasacchi CA2/6
California Court of Appeal, 2024
Knight v. Rosanta Company CA1/4
California Court of Appeal, 2023
Tulare Lake Canal Co. v. Sandridge Partners CA5
California Court of Appeal, 2023
Hall v. Sohn CA5
California Court of Appeal, 2023
Doss v. Brehaut CA4/3
California Court of Appeal, 2023
Rancho Carlton Properties, LLC v. Radnor CA2/5
California Court of Appeal, 2022
Tri-Dam v. Frazier
E.D. California, 2022
Acornhill Investments v. Pan City Plaza CA2/8
California Court of Appeal, 2021
Macciola v. Harms CA2/6
California Court of Appeal, 2021
18131 Ventura Blvd v. 5223 Lindley CA2/7
California Court of Appeal, 2021
Pear v. City & County of San Francisco
California Court of Appeal, 2021
Pear v. City & County of S.F.
California Court of Appeal, 2021
Valles v. Kim CA2/3
California Court of Appeal, 2020

Cite This Page — Counsel Stack

Bluebook (online)
222 Cal. App. 4th 419, 165 Cal. Rptr. 3d 658, 2013 WL 6680755, 2013 Cal. App. LEXIS 1023, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dolnikov-v-ekizian-calctapp-2013.