D'Olier Engineering Co. v. United States

244 F. 90, 156 C.C.A. 518, 1917 U.S. App. LEXIS 1994
CourtCourt of Appeals for the Third Circuit
DecidedApril 9, 1917
DocketNo. 2108
StatusPublished
Cited by1 cases

This text of 244 F. 90 (D'Olier Engineering Co. v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
D'Olier Engineering Co. v. United States, 244 F. 90, 156 C.C.A. 518, 1917 U.S. App. LEXIS 1994 (3d Cir. 1917).

Opinion

BUFFINGTON, Circuit Judge.

In the court below the United States brought an action at law against the D’Olier Engineering Com[91]*91pany, to recover an alleged mistakenly made overpayment in settlement oí a contract for furnishing and installing boilers for the Panama Canal. Trial by jury having been waived, the case was heard by a judge, who entered judgment for the government for the full amount of its claim. Thereupon the defendant took this writ of error. The opinion of the court below is reported in (D. C.) 215 Fed. 209. The proofs in the case tended to show that having been the accepted bidder on proposals submitted by the government, the D’Olier Engineering Company, hereafter called the contractor, on November 7, 1907, entered into a contract with the United States, represented by the Isthmian Canal Commission, to furnish and install two large boiler plants at Gatun and Mir aflores. By such contract the contractor guaranteed:

“Each boiler to develop tlie nominally rated horse power of not .more than five (5) per cent, above, at an efficiency of seventy-two (72) per cent,., and a capacity for evaporation of 17,000 pounds of water per hour under the conditions of the test prescribed in paragraph 4 of the specifications, under item 1 of circular 444.”

The test of this guaranty was an official one, provided for by article XI of the contract as follows:

“Article XI. As soon as practicable after erection of the respective plants on the Isthmus, and before acceptance, provided the boilers shall have successfully withstood the preliminary tests called for herein or in the specifications, there shall be conducted on at least one boiler of said plant an official test made by the engineer of the Commission in charge or his deputy designated for the purpose and an official representative of the contractor, the expense of said test to be borne by the Commission, and the same to be conducted under the conditions described in paragraph 4 of the specifications given under item 1 of circular No. 444.”

The price of the boilers was fixed by article XII, which is as follows :

“The price of the boilers as given in article I is based upon an efficiency of sixty-five (65) per cent, developed by the tost provided in article XI. Should the said test demonstrate that the efficiency falls short of sixty-five (65) per cent, there shall be deducted from the price of the entire plant to which the test applies one thousand dollars ($1,000) for each reduction of one below the said efficiency percentage and a proportionate amount for any fractional part of said reduction, fractions being carried to the second place of decimals. Should the said test demonstrate that tlie efficiency exceeds sixty-five (65) per cent., there shall be added to the price of the entire plant to which the test applies, one thousand dollars ($1,000) for each Increase of one above the said efficiency percentage and a proportionate amount for any fractional part of said increase, fractions being carried to the second place of decimals. Should the efficiency developed by the said test fall belotv sixty (60) per cent., the contractor inay be required to remove the boilers composing the plant and install, without extra cost to tlie Commission, boilers of the required efficiency. The boilers first installed will be used by the Commission until the substitutes have been installed, tested, and found to comply with this contract.”

The scope of the test is shown by the fact that if the boilers fall below the required test, the contractor could be required to remove them and construct others of the required efficiency. The nature of the test was fixed by article XIV of the contract, which provides as follows:

“All questions relating to final inspection and acceptance of the plants or materials to be supplied hereunder, or the failure of the said plants or materials to comply with the specifications, or default in the tune of delivery or [92]*92performance, or damages sustained by the Commission by reason of the failure of the contractor to comply with this agreement, shall be determined by the chairman of the Commission, or by any officer or deputy to whom the chairman may assign that duty; and such default or assessment of damages, when expressed in writing, shall be prima facie evidence of breach of contract and of the damages sustained by the Commission, and shall cast upon the contractor and his sureties the burden of showing that such finding or assessment of damages is unfair upon its face, or collusive, or was arrived at contrary to the provisions of this agreement.”

It will thus be seen that the exclusive right to make the test and to determine the Question of the fulfillment of the contract and its guaranties, was in the government, a situation akin to that of Kihlberg v. United States, 97 U. S. 398, 24 L. Ed. 1106, namely:

“The parties, however, concurred in designating a particular person, a chief quartermaster of the District of 'New Mexico, with power not simply to ascertain but to fix the distances 'which should govern in the settlement of the contractor’s accounts for transportation.”

The procedure provided by the contract was followed when the boilers were completed and ready for test. Such test was made on behalf of the government by one Schildhauer, representing the government, and in the presence of Lafore, the representative of the contractor. Both of these men joined in a report to George W. Goethals, the chairman and chief engineer of the Isthmian Commission, who, as provided by article XIV of the contract, either by himself or by any officer or deputy to which he might assign that duty, at the final inspection and acceptance of the plant, had the right to determine “all questions relating to final inspection and acceptance of the plants.” Having received this report, Col. Goethals took up the question of closing the contract, and with the expressed purpose of “closing up the contract” and preparing a report in such shape that the “general purchasing officer of the Commission can prepare the necessary supplemental agreements, if any are necessary, or take action in the matter of making final settlement,” addressed the following letter:

“Dt Col. W. D. Sibert, Division Engineer, Gatun, Dt. Col. C. A. Devol, Chief Quartermaster, Culebra. Mr. W. W. Warwick, Examiner of Accounts, Empire. Gentlemen: Closing up the contract with the D’Olier Engineering Company for boilers, etc., at Gatun and Miraflores requires consideration and recommendation on changes in the contract, interpretation of contract specifications, and various points of fact in connection with the time of delivery, completion and delivery of the plant.
“I have received a joint report from Mr. Schildhauer and Mr. Dafore,,the' latter being the representative of the contractor, and before forwarding the-papers to the general purchasing officer in the United States it is desired that all matters at issue between the contractor and the Commission be considered and passed upon by a committee, which is, therefore, appointed with Mr. Warwick as chairman. Col. Sibert and Col. Devol will please appoint representatives to act on this committee with Mr. AVarwiek, who will appoint times and places of meetings. It is expected that Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ohio Sav. Bank & Trust Co. v. Willys Corp.
16 F.2d 859 (Third Circuit, 1926)

Cite This Page — Counsel Stack

Bluebook (online)
244 F. 90, 156 C.C.A. 518, 1917 U.S. App. LEXIS 1994, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dolier-engineering-co-v-united-states-ca3-1917.