Dobbling v. York Springs Railway Co.
This text of 56 A. 349 (Dobbling v. York Springs Railway Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
Opinion by
In Dobbling v. York Springs Railway Company, 203 Pa. 628, we held that the determination of the amount of damages suffered by the plaintiff, in the loss of the contract when rescinded by the defendant, was not to be left to the defendant’s engineer. As the case then stood, the fact that the work had been stopped by the order of the defendant did not seem to be seriously disputed.
The question presented to us was whether the engineer was to be the sole arbitrator, as to the damages, under the allegation that the contract had been rescinded by the defendant. The truth of that averment was as a matter of course open to investigation upon the trial, and the record in the case as it is before us now shows clearly that the trial judge left it fairly to the jury to determine whether or not the contention of the plaintiff in this respect was correct. He says in his charge to the jury, “ The plaintiff brings this suit not to enforce the contract, because the contention on the part of the plaintiff is that the contract has been rescinded by the action of the defendant in ordering the work to be stopped .... the contention on the part of the defendant is that the contract was never rescinded or abrogated. The contention on the part of the plaintiff is that it was rescinded by the order to stop work, and not any order requesting him to resume work.” And again he says, “ If you believe this work was stopped in the manner as testified to by the plaintiff—by a telegram, and by a conver[125]*125sation with Mr. Trimmer, who was acting as manager of the company; and he was requested to stay there for a time, and that in a week or ten days the matter would be settled, and that he stayed there over that time, and then left the ground— then the court instructs you that he had a right to treat the contract as rescinded, and has the right to recover such damages as may have been proved to your satisfaction. It is for you to determine whether these fact are true—so far as the court remembers these facts, this was not seriously contradicted.”
The verdict of the jury must be taken as establishing the fact that the plaintiff was justified in stopping work on the contract and in considering the actions of the defendant as a rescission. (
Much of the argument upon the part of the appellant in the present appeal is practically a reargument of the question, which we have already decided in the case.
We have not been convinced that we were in error in holding that' the parties by their contract did not constitute the engineer the sole arbiter, to determine the amount of damages sustained by the plaintiff by the rescission of the contract. Aside from this, the assignments of error as to the admission and rejection of evidence are without merit, and are not seriously pressed in the argument.
They are all overruled and the judgment is affirmed.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
56 A. 349, 207 Pa. 123, 1903 Pa. LEXIS 454, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dobbling-v-york-springs-railway-co-pa-1903.