Dobbins v. Edmonds

18 Mo. App. 307, 1885 Mo. App. LEXIS 335
CourtMissouri Court of Appeals
DecidedJune 8, 1885
StatusPublished
Cited by29 cases

This text of 18 Mo. App. 307 (Dobbins v. Edmonds) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dobbins v. Edmonds, 18 Mo. App. 307, 1885 Mo. App. LEXIS 335 (Mo. Ct. App. 1885).

Opinion

Opinion by

Philips, P. J.

1. It is insisted by defendants, plaintiffs in error, that the petition counts on an absolute sale and delivery of the logs, and prays judgment for the contract price; and that to maintain such action, the proof must show such delivery of the property as would thereupon transfer the title unconditionally to the defendants. We do not think this is fair or admissible construction of the petition. It is quite manifest that the declaration avers that the plaintiff kept and performed all the conditions and provisions of the contract to be kept and performed on his part, but the defendants failed to observe the same on their part; that plaintiff, as required by the contract, made tender of the logs to defendants at the point of delivery designated in the contract, but the defendants refused to receive or pay for the same; wherefore plaintiff is damaged. The action is clearly for the breach of the contract on the part of defendants, and to recover damages therefor. As such, it was rightly brought.

2. It is next insisted that the contract was executory, and that the condition or event which was to make it consummate not having transpired, it thereafter had [315]*315no existence, except as the foundation for a suit by the injured party against the party in default for damages for wrongfully putting an end to it. This postulate is founded on the following clause in the contract: “The logs to be measured and scaled agreeably to Scribner’s, before being put into the river.” It is contended by defendants that this measurement and scaling were to be the concurrent act of the parties to the contract; and, therefore, when the defendants refused to participate therein, the thing to be done, which was in the nature of an act precedent, never occurred. Therefore, there could be no delivery of the logs under the contract, and the action should have counted on the wrongful refusal of defendants to join in making the measurement; in which event, the measure of damages would have been different from what plaintiff asserts in the case at bar. We concede that the proper construction of the clause in question is that the measurement and scaling were to be done by both parties. It was certainly not the intention of the parties that either should be bound by measurement, etc., to which he was not a party. And the rule, in such cases, is that it is to be presumed that it was the intent that both should participate, unless something to the contrary clearly appears in the case. Lingham v. Eggleston, 27 Mich. 331.

Besides this, among the recognized rules for the interpretation of contracts are the following : The circumstances under which the contract is made may be looked to in aid of its construction; and the acts of the parties to the instrument are entitled to great weight. Gathwright v. Callaway county, 10 Mo. 663; Patterson v. Camden, 25 Mo. 13. The evidence in this case shows that the lumber, which was on hand at the making of the contract, had been measured and scaled by both parties jointly; and it further shows that when the logs in question were ready for inspection on the river bank, before they were floated, the plaintiff notified the defendants of the fact, and requested them to come and make the measurement; and one of defendants did go, but refused to act. This clearly enough indicates [316]*316what was the understanding of the parties of this clause of the contract.

But does it follow, because the defendants refused to join in this matter, that they can now insist that their omission and wrong put an end to the contract? This participation in making the measurement was a mere right secured to the defendants by the contract for their protection. This right they might waive, and did waive. Benjamin on Sales (4th Ed.) 566-7, comprehends the whole law pertinent to this issue, as follows: “But the necessity of performing the condition precedent may be waived by the party in whose favor it is stipulated, either expressly or by the implication resulting from his acts or conduct. This waiver is implied in all cases in which the party entitled to exact performance either hinders or impedes the other party in fulfilling the condition, or incapacitates himself from performing his own promise, or absolutely refuses performance, so as to render it idle and useless for the other to fulfill the condition. No authority is needed, of course, for the proposition that the party in 'whose favor the condition has been imposed may expressly waive it. The cases are numerous, however, to establish the proposition above stated, in relation to implied waiver. If a man offer to perform a condition precedent in favor of another, and the latter refuses to accept the performance, or hinder, or prevent it, this is a waiver, and the latter’s liability becomes fixed and absolute. * * * If the performance of a condition precedent by the plaintiff has been rendered impossible by the neglect or default of the defendant, it is equal to performance. On the same principle, a positive, absolute refusal by one party to carry Qut the contract, or his conduct in incapacitating himself from performing his promise, is in itself a complete breach of the contract on his part, and dispenses the other party, on his part, from the useless formality of tendering performance of the condition.” See Attix, Noyes & Co. v. Pelan et al., 5 Iowa 342. So our supreme court have uniformly held, that where one party is prevented by the wrongful act, or refusal, of the other party [317]*317from performing a condition precedent, or completing his contract, lie is entitled to recover as on a contract fully performed. Little v. Mercer, 9 Mo. 218; Pond v. Wyman, 15 Mo. 176 ; Hearns v. Horbert, 25 Mo. 354.

3. The important, and really only practical, question affecting the merits of this controversy is, what is the proper measure of damages in such case ? The jury have found necessarily, by their verdict, that the plaintiff has kept and performed the whole contract on his part. Unless, therefore, the court applied a wrong measure of damages, to defendants’ prejudice, they ought not to complain. Courts have to deal with few questions of more complexity and perplexity, in their application to varying facts, than the rule for the ascertainment of the proper measure of damages on broken contracts. In the multitude of adjudications bearing on the rule, in a case Hice this, it would be a discouraging task to undertake to reconcile the conflicting views of eminent judges. The controversy seems to lie between the three following-methods : First, whether the plaintiff, who is prevented from completing the contract by the refusal to perform of the other party in the case of a contract of sale of personal property, may go on and complete the contract on his part, and recover the contract price; or, second, whether he should treat the contract as ended, and retain the property as his own, and sue for the difference between the market value thereof and the contract price ; or, third, sell the property at auction or at private sale for the best price he can command, and sue for the recovery of the difference between the price realized and the contract price. I am free to admit that the weight of authority seems to indicate a preference for the latter mode as the best means for the protection of the interests and equities of both parties. The object of the law is to attain as exact justice as is practicable between man and man. It, therefore, often results, in dealing with a question of this character, that the court must recognize the peculiar facts and circumstances surrounding- each case as it arises.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Foster v. Montgomery Ward & Co.
163 P.2d 838 (Washington Supreme Court, 1945)
Knapp v. Strauss
58 S.W.2d 805 (Missouri Court of Appeals, 1933)
Turner Looker Co. v. Hindman
250 S.W. 388 (Supreme Court of Missouri, 1923)
Redman v. St. Joseph Hay & Grain Co.
239 S.W. 540 (Missouri Court of Appeals, 1922)
Weber Motor Car Co. v. Roberts
219 S.W. 994 (Missouri Court of Appeals, 1920)
J. E. Stewart Produce Co. v. Gamble Robinson Commission Co.
175 S.W. 319 (Missouri Court of Appeals, 1915)
Roaring Fork Potato Growers' Ass'n v. C. C. Clemens Produce Co.
171 S.W. 584 (Missouri Court of Appeals, 1914)
Paul E. Wolff Shirt Co. v. Sacks
168 S.W. 641 (Missouri Court of Appeals, 1914)
Pacific Bridge Co. v. Oregon Hassam Co.
134 P. 1184 (Oregon Supreme Court, 1913)
Oehler v. Conrad Schopp Fruit Co.
142 S.W. 811 (Missouri Court of Appeals, 1912)
Boulware v. Crohn
99 S.W. 796 (Missouri Court of Appeals, 1907)
Campbell v. Woods
99 S.W. 468 (Missouri Court of Appeals, 1907)
St. Louis Range Co. v. Kline-Drummond Mercantile Co.
96 S.W. 1040 (Missouri Court of Appeals, 1906)
American Cotton Co. v. Herring
84 Miss. 693 (Mississippi Supreme Court, 1904)
Osborne v. Mullikin
88 Mo. App. 350 (Missouri Court of Appeals, 1901)
Del Bondio v. Jacob Dold Packing Co.
79 Mo. App. 465 (Missouri Court of Appeals, 1899)
Logan v. Carroll
72 Mo. App. 613 (Missouri Court of Appeals, 1897)
D. M. Osborne & Co. v. Henry
70 Mo. App. 19 (Missouri Court of Appeals, 1897)
Winn v. Lippincott Investment Co.
28 S.W. 998 (Supreme Court of Missouri, 1894)

Cite This Page — Counsel Stack

Bluebook (online)
18 Mo. App. 307, 1885 Mo. App. LEXIS 335, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dobbins-v-edmonds-moctapp-1885.