Doane College v. Lanham

42 N.W. 405, 26 Neb. 421, 1889 Neb. LEXIS 146
CourtNebraska Supreme Court
DecidedMay 16, 1889
StatusPublished
Cited by1 cases

This text of 42 N.W. 405 (Doane College v. Lanham) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Doane College v. Lanham, 42 N.W. 405, 26 Neb. 421, 1889 Neb. LEXIS 146 (Neb. 1889).

Opinion

Cobb, J.

This action was commenced in the district court of Saline county, by John Lanham against Doane College. The plaintiff in his petition alleges that Doane College is a corporation under the laws of this state; that on or about April 10, 1884, he contracted with the college through Thomas Doane, its legally authorized agent, to furnish the material and labor and to build and complete for Doane College the brick-work for a college building then being built for defendant on its grounds at Crete, Nebraska, and [425]*425known as Ladies’ Hall; that it was then and there agreed between the parties that the price of said labor and material should be: for brick laid in the wall with mortar mixed partly with cement, and with both sides of wall faced with repressed brick, $12.75 per one thousand brick; that chimneys should be computed as solid, and each cubic foot of such masonry, including door and window openings, should, be computed to contain two hundred and twenty-four and one-half bricks; that it was then and there verbally agreed by and between said parties that said work should be built on a foundation the dimensions of which were then determined, and should be two stories high, with plain outer walls, similar to those of the college building then standing on said grounds, and should contain as nearly as could then be estimated, a total of 275,000 brick; that subsequently and after said work was commenced, the plan was so changed by defendant as to make the main part of said building three stories high, instead of two as originally agreed upon, with outer walls buttressed instead of plain; that the plaintiff, without any agreed price therefor, did, at the request of defendant, proceed to furnish the labor and material and build and complete the third story, and the outer walls with buttresses instead of plain, according to said change of plan; that said third story contains the amount of 195,000 brick; that the first and second stories contain the total amount of 275,000 brick, all of which is laid in mortar mixed with cement, according to contract; that of said 275,000 brick, two-thirds are faced on both sides with repressed brick, and the plaintiff, according to said contract is entitled for building the same to the sum oí $12.75 per thousand; that the remainder, or one-third part thereof, were faced on one side with repressed brick, and the price of laying the same, according to the contract, is $10.75 per thousand. The plaintiff alleges that the extra expense of laying the third story over those of the first and second, amounts to $3 per thousand, and that to furnish [426]*426material and labor and to build the third story of said building was worth $15.75 per thousand of brick for walls faced on both sides with repressed brick, and $13.75 per thousand for walls with one face of repressed brick laid in mortar mixed, with cement, as stated; and that of the 195.000 brick laid in the third story of said building, 75.000 were faced with repressed brick on both sides, and 120.000 were so faced on one side; that all are laid with mortar properly mixed with cement; that the labor necessarily employed on the outer walls, buttressed instead of plain, is worth the sum of $15; and that the labor and material expended in the erection of the third story and the change in the outer walls amounts to $2,846.25. The plaintiff alleges that the total labor and material for the completion of the brick-work, according to the contract price for the first and second stories, and the actual value of labor and material for the third story, amounts to $6,170.50, furnished at the request and under the direction of defendant, completed September 1,1884, and was accepted by defendant, whereby the defendant was and is liable to the plaintiff for the full amount thereof.

The plaintiff alleges that there has been paid him on said work by the defendant the sum of $3,740, and no more, and that there is due the sum of $2,430.50, and that though said last-mentioned sum has been due since September 1, 1884, the defendant has neglected to pay the same or any part thereof; wherefore the plaintiff prays judgment therefor with interest thereon from September 1, 1884, and costs.

Doane College, by its answer, denied all the allegations of the petition except those in the answer expressly admitted.

Eor a second defense it admitted that it entered into a contract with John Lanham, April 10, 1884, for the erection of a building upon the college grounds, to be known as “Ladies5 Hall;55 that said contract was in writing, a [427]*427copy of which is made exhibit “A” to its answer; that it contains no provision as to the height or number of stories of the building ; that it provides for all the work thereon at the agreed prices set forth therein, and denies that there was any other contract than that set forth in exhibit “A;” and further denies that there was any verbal contract changing, modifying, or enlarging it, as alleged in the plaintiff’s petition, but avers that all of the work done by the plaintiff on said building was at the contract price as set forth in exhibit “A;” that upon the completion of the building, the matters in controversy between the contractor and the college, as to the completion of the building, were placed before and considered by the building committee of said college, which refused to pay the same; and that finally all the matters of difference between the parties were submitted to arbitration, in writing, a copy of which is made exhibit “B” to its answer; that in pursuance of said submission, J. J. Butler, T. E. Calvert, and J. H. Ames, arbitrators, made and published their award that there was due to the said Doane College the sum of $1,119.34, which is made exhibit “C” to its answer; that the college then tendered the contractor the balance due him, which was accepted, except the sum of $120.21, which is now tendered him, and brought into court.

The defendant further avers that the amounts which were due the plaintiff as contractor and builder, were as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wilkinson v. Prichard
123 N.W. 964 (Supreme Court of Iowa, 1909)

Cite This Page — Counsel Stack

Bluebook (online)
42 N.W. 405, 26 Neb. 421, 1889 Neb. LEXIS 146, Counsel Stack Legal Research, https://law.counselstack.com/opinion/doane-college-v-lanham-neb-1889.